Permit Information
Permit NumberBLD05-01063
StatusFinaled
Name MCCARTHY
Site Address 1055 N CURTIS RD
Project NameST AL'S-FAMILY MATERNITY CNTR
Customer Number 
ePlanReviewNo
Description
(ST ALPHONSUS)(FAMILY MATERNITY CENTER EXPANSION/RENOVATION) To finish the exterior & interior of a 38,020 square foot, two story addition with mechanical penthouse, adjacent to and connected to the existing Labor & Delivery Unit by two connecting links; to create patient rooms, exam rooms, nursing stations, administrative support and Neonatal Intensive Care Unit on the second floor; installation of millwork, electrical, plumbing, mechanical, electrical, fire suppression, alarm and medical gas as per tenant needs and compliance with codes and ordinances; to install a suspended ceiling grid system and interior finishes; to remodel a portion of the existing FMC for sleeping rooms for medical personnel; and to install exterior glazing and finishes. (drs)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD2/22/20072/22/20072/26/2009 DONE
DetailsAlexandra L. DeYoung
Second Notice has not been responded to.
Second Notice BLD2/7/20072/7/20072/22/2007 DONE
First Notice has not been responded to.
First Notice 1/25/20072/7/2007 DONE
Permanent occupancy  1/25/2007 DONE
Perm. Occ. Cert. # 11409 issued 1-25-07 to St. Al's Family Maternity Center.
BLD-Final1/19/20071/22/20071/22/2007PPASS
DetailsTom Arcoraci
FIRE-Final Inspection1/19/20071/22/20071/22/2007APASS
DetailsTroy Cobbley
life safety finaled
Permanent Occupancy 1/22/20071/22/2007 DONE
Details
FIRE-Final Inspection1/19/20071/19/20071/19/2007PFAIL
DetailsTroy Cobbley
Need fire alarm and fire sprinkler finaled first.
BLD-Final1/19/20071/19/20071/19/2007PNR
DetailsTom Arcoraci
carl - late afternoon; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
BLD-Other11/30/200612/1/200611/30/2006ACANC
DetailsTom Arcoraci
see Karl
BLD-Aging Inspection11/17/200611/17/200611/17/2006 PASS
DetailsTom Arcoraci
Plan resubmittals received  9/29/2006  
Received 1 cover transmittal, 2 copies of the following sheets--E-9, E-10, HR-1HR-2, HR-3, HR-4, HR-5, HR-7, B78, ST1, ST2, ST3, ST4, ST5, ST6 as deferred submittals and taken to Dan Stuart
Plan resubmittals received  9/21/2006  
Received deferred resubmittals; transmittal sheet, copy of proposed deferred submittals, 2 copies of the following: Wausau Window and Wall Systems (29 pgs/ea), calculations for Exterior Framing - Structural, specifications for Exterior Stud Wall System, specifications for Firestopping, specifications for Air Barriers(firestop for electrical penetration), specifications for Air Barriers(firestop for floor & wall penetration), specifications for Preformed Wall Panels, specifications for Curtian Wall System, specifications for Plant-Precast Architectural Concrete, specifications for Fireproofing; 4 copies of the following pages: E-9, E-10, B78, ST1, ST2, ST3, ST4, ST5, ST6; 2 copies of the following pages: HR1, HR2, HR3, HR4, HR5, HR6, 05-21(sheet 1), 05-21(sheet 2), D1.1, 1.1, 1.2, 2.1, 2.2, 4.1, T1, P1, P2, E1, E2, E3, E4, E5, D1; taken to Dan Stuart
FIRE-Final Inspection9/13/20069/14/20069/15/2006ACANC
DetailsTroy Cobbley
Duplicate inspection
FIRE-Final Inspection9/13/20069/13/20069/15/2006PPART
DetailsTroy Cobbley
A temporary occupancy was given until the phase II (remodeled existing area) is complete. The new FMC building is complete.
BLD-Final9/14/20069/15/20069/15/2006APART
DetailsTom Arcoraci
richard cal 1st before insp ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie handrail at ext ,ramp at south ext and barrier under stair tower
Temporary occupancy  9/15/2006 DONE
Temp. Occ. Cert. # 5445 issued 9-14-06 to St. Al's Family Maternity Center.
BLD-Wall cover8/25/20068/25/20068/25/2006PPASS
DetailsTom Arcoraci
rich - Note: above ceiling fire wall inspection; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Wall cover7/19/20067/19/20067/19/2006PPASS
DetailsTom Arcoraci
richard; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Framing/Rough-in6/21/20066/22/20066/22/2006APART
DetailsDave Hannah
tom ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley hard lid in entry way ok to cover
BLD-Other6/15/20066/15/20066/15/2006PCANC
DetailsDave Hannah
Rich, above ceiling firewall; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
BLD-Framing/Rough-in3/21/20063/22/20063/22/2006APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 3/21/2006 at 12:43:00 PM. Contact: ###-####. 2nd floor walls ok excp washer box and some elec back to back
Plan resubmittals received  3/17/2006  
Received from Action Courrier 2 transmittal cover letter, 1 copy of product data sheet, 1 copy of material safety data sheet and taken to Dan S.
BLD-Framing/Rough-in3/8/20063/8/20063/8/2006PPART
DetailsTom Arcoraci
rich george; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok to cover int walls on 1st floor ok to one side 2nd floor and partial cover at south end needs to address floor sink pents 2 of them at floor ceiling
BLD-Framing/Rough-in3/2/20063/3/20063/3/2006APART
DetailsTom Arcoraci
rich george; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok to one side
BLD-Framing/Rough-in2/21/20062/21/20062/21/2006PPART
DetailsTom Arcoraci
tom ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ext walls ok for insul
BLD-Framing/Rough-in1/11/20061/11/20061/11/2006PPART
DetailsTom Arcoraci
tom ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie par ok for cover
Plan resubmittals received  11/1/2005  
Received (2) copies of sheet E-9, E-10, B78, ST1, ST2, ST3, ST4, ST5, ST6, HR1, HR2, HR3, HR4, HR5 and HR6. Routed to Dan S.
Issue PAID IN FULL permit  10/20/2005 DONE
Plan resubmittals received  10/20/2005 DONE
Received 1 letter to George S., 1 elevation @ beam penetration,1 plan scetion@ beam /2 hr wall taken to Dan S.
Telephone call  10/17/2005 DONE
left mess for jeff cramer at ###-#### that permit is ready
Plan resubmittals received  10/17/2005  
Received 1 Letter to George S.,1 beam /2 hr wall,beam penetration. taken to Dan S.
Routing - PLAN CHECK10/12/2005 10/14/2005 PASS
Approved as noted on and all attached plan review conditions as part of the approved plans.
PLANS/APPL TAKEN TO FRONT DESK  10/14/2005 PASS
Ready to issue.
Inspection Record Card- Bld  10/14/2005 DONE
Inspection Record Card- Bld  10/14/2005 DONE
Print Occupancy Form  10/14/2005  
Permit Ready to Issue  10/14/2005 DONE
Plan assigned to (DRS)4/29/2005 10/14/2005 PASS
10/14/2005 15:38:27 DRS - activity updated through activity BLDA022 from case BLD05-01063.
Routing - FIRE9/20/2005 10/12/2005 PASS
resubmittal acceptable. review faxed to architect.
Additional plans submitted  9/27/2005 DONE
Received ONE COPY of engineering for stairs and ONE COPY of sheets E-9, E-10, B78, ST1, ST2, ST3, ST4, ST5 & ST6 for review.
Plan resubmittals received  9/20/2005  
Received (2) copies of sheet MH-101-5 and MP-101-5. Routed to Dan S.
Routing - PLAN CHECK6/24/2005 9/20/2005 PEND
Routing to fire code analyst for re-review.
Plan resubmittals received  9/19/2005 DONE
Received cover letter of explanation and two copies of Sheets A-101A, A102A, A103A, P101A-5, P102A-5 & PP-103A-5 in response to fire code analyst plan review comments. Inserted into plans and routed back to fire code analyst for re-review.
Plan resubmittals received  8/18/2005 DONE
Received 1Transmittal,2 Response Letters, 2 Door Schedules & 2 Copys of sheets G-002,A-102A,A-214,A-401,A-511,AC-101A,AC-102A,IFF-102A,MH-101A-5,MH-102A-5,EL-102A-2 Taken to Dan S.
Routing - PLAN CHECK6/17/2005 6/24/2005 FAIL
Plans being re-routed to plumbing code review analyst. Received plumbing code resubmittals 6/24/05 with copies attached to plans.
Plan resubmittals received  6/24/2005 DONE
Received Transmittal , 1 Plumbing Plan Revirw, & 2 Copys of sheets M-802-5,P-101D-5,P10FA-5,M802-5 Taken to Dan S.
Routing - PLUMBING6/24/2005 6/24/2005 PASS
per plans and 2003 upc.
Routing - FIRE6/10/2005 6/17/2005 FAIL
review faxed to architect.
1st review completed  6/17/2005 FAIL
failed plumbing, plan check and fire.
Plan resubmittals requested  6/10/2005 DONE
Copy of plan review conditions requiring response from architect e-mailed to Jeff Cramer, HDR, for response.
Routing - PLAN CHECK5/13/2005 6/10/2005 FAIL
Resubmittals required. Routing to fire code analyst for review.
Routing - PLUMBING5/4/2005 5/13/2005 FAIL
provide double wall heat exchanger with leak detection for water heaters. extend 6" waste main south to the next 4" branch to the east. provide existing loading on the med. gas and vacuum system at tie in.
Routing - PLANNING5/2/2005 5/4/2005 PASS
Approved per DRH05-00002.
Routing - PUBLIC WORKS4/29/2005 5/2/2005 PASS
Pending Assignment by MYS4/21/2005 4/29/2005 DONE
4/29/2005 11:45:25 MYS - activity updated through activity BLDA168 from case BLD05-01063.
Plans ACCEPTED BY PLAN TECH  4/25/2005  
Application received  4/21/2005  
Told Jeff he will need the ESC plan with this submittle
Recd Pcfee & Taken To Pln CK  4/21/2005  
Fee Review-notes4/21/20054/21/2005