Permit Information
Permit NumberBLD05-01077
StatusFinaled
Name DEVCON CONSTRUCTION INC
Site Address 495 S CAPITOL BLVD
Project NameBODO BLDG #8
Customer Number 
ePlanReviewNo
Description
BODO BLDG #8-Hampton Inns Hotel/Garage (Tenant Completion) per Cody R. no TEMP occupancy until the DR requirements are met. Exterior Paint color not correct.To finish the tenant improvement for the new 235,965 square foot, eleven story high rise, parking and Hampton Inn hotel portion of this building. The first floor contains 7,775 sq. ft. of retail space (to be finished under separate tenant improvement permits), 9,000 sq. ft. of hotel lobby space and 19,020 sq. ft. of parking garage space (total 35,795 sq. ft.). The second, third and fourth floors are parking garage (34,750 sq. ft. each floor, total of 104,250 sq. ft.). The fifth floor contains hotel rooms, laundry, meeting rooms, exercise room and indoor swimming pool (16,000 sq. ft.). The sixth through eleventh floors contain hotel guest rooms (13,320 sq. ft. per floor, total 79,920 sq. ft.). The fire-resistance rating reductions allowed by IBC, Sections 403.3.1 and 403.3.2 is being used to reduce the required fire-resistive rating from Type IB to Type IIA. The reduction is allowed in this building with the use of sprinkler control valves equipped with supervisory initiating devices and water-flow initiating devices for each floor. The other requirement of this reduction is the construction of two-hour fire-barriers between the first floor mercantile occupancies and the remainder of the building. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  4/7/2016 DONE
Case Summary (BLD)  12/6/2007 DONE
Third Notice BLD7/23/20077/23/200710/4/2007 DONE
Second Notice has not been responded to.
Fee Review-notes4/22/20054/22/200510/4/2007 DONE
Routing Off Site - STRUCTURAL1/3/2006 10/4/2007 PASS
Called PDQ for pick up
Routing - PLAN CHECK1/5/2006 10/4/2007 PASS
Routing - PLAN CHECK2/10/2006 10/4/2007 PASS
Routing - PLAN CHECK2/17/2006 10/4/2007 PASS
Sheets A2.1, A2.1.1, (rated corridor modification) A3.11 and fire pump tank modification plan FP1 routed to building for approval.
Routing - PLUMBING6/29/2006 10/4/2007 PASS
Routing - PLAN CHECK9/19/2006 10/4/2007 PASS
Telephone call  10/4/2007 DONE
lft vm with jmeas woodbury ###-#### to verify no plum on permit but have values on the cofv 8:45 am
Telephone call  8/2/2007 DONE
lft vm with james woodbury ###-#### that plm fees are not on this permit need to find out where he got the amount
Second Notice BLD7/12/20077/12/20077/23/2007 DONE
First Notice has not been responded to.
First Notice 6/28/20077/12/2007 DONE
Permanent Occupancy 6/28/20076/28/2007 DONE
Details
Permanent occupancy  6/28/2007 DONE
Perm. Occ. Cert. # 11682 issued 6-28-07 to te Hampton Inns Htel.
Plan Reviewer's activity  6/19/2007 PASS
Reviewed submitted information for proposed ceiling insulation at the hotel lobby areas. I have approved the modified energy envelope information and routed the plans to George Slane to determine best course to inspect and verify compliance and issue permanent final. JCM
Plan resubmittals received  5/14/2007 DONE
received 1 letter of transmittal, report for building 8 (revised 1st floor hotel function /mid-retail) and 2 copys of sheet A6.1.1 taken to John M
Temporary occupancy  5/7/2007 DONE
Temporary Occupancy extended (4-23-2007) for 90 days beginning May 7, 2007. New expiration date is August 6, 2007. Only item remaining is fire protection issue related to potential freezing pipes in the lobby area. jlg.
BLD-Final5/3/20075/4/20075/4/2007APART
DetailsDave Hannah
jim; Phone #: ###-#### Internet Inspection Request from: Victoria Beall everything ok but for zoning and code enforcment
FIRE-Final Inspection5/2/20075/3/20075/3/2007APASS
DetailsForrest France
Fire life safety finaled.
FIRE-Final Inspection4/30/20075/2/20075/2/2007ADEFR
DetailsForrest France
Inspection rescheduled per conversation with building engineer.
FIRE-Final Inspection4/30/20075/2/20074/30/2007ACANC
DetailsForrest France
jim - fire life safety ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith Inspection cancelled from web by: Andrea Whiteman
FIRE-Final Inspection2/14/20072/14/20072/14/2007PFAIL
DetailsTroy Cobbley
All items on the correction notice have been taken care of. I signed the sign-off card. But befor I could make a computer entry I was contacted by Sam ROges about a sprinkler issue above the lobby ceiling. I told Dennis that there would be no sign off from me until the issue is resolved. He is going to take care of the issue and then contact me.
BLD-Final2/8/20072/8/20072/8/2007PPART
DetailsDave Hannah
going over c/n items
BLD-Final2/2/20072/5/20072/5/2007APART
DetailsDave Hannah
dennis; Phone #: ###-#### Internet Inspection Request from: Victoria Beall ok for temp occ c/n ada issuse
BLD-Final2/2/20072/2/20072/5/2007PPART
DetailsDave Hannah
ok for temp occ c/n to follow needs other trafdes to go perm and ada issuse addressed
FIRE-Final Inspection2/2/20072/2/20072/2/2007PPART
DetailsForrest France
Approved temporary occupancy, final approval pending the completion of all items on the correction notice left on site and discussed with general contractor.
Temporary occupancy  2/2/2007 DONE
Temp. Occ. Cert. # 5532 issued 2-2-07 to the Hampton Inn Hotel/Garage.
FIRE-Final Inspection1/30/20071/31/20072/1/2007PFAIL
DetailsForrest France
Missing directional arrows at the 8th floor exit signs, repair the exit sign at the pool room, missing emergency lighting at the elevator lobby and adjacent hall on the first floor.
BLD-Final1/29/20071/30/20071/30/2007PNR
DetailsDave Hannah
katie - swimming pool; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
FIRE-Final Inspection1/29/20071/30/20071/30/2007ADEFR
DetailsForrest France
Rescheduled per conversation with contractor.
BLD-Framing/Rough-in1/11/20071/12/20071/12/2007APART
DetailsDave Hannah
dennis; Phone #: ###-#### Internet Inspection Request from: Victoria Beall ok to cover wall between garage and hotel
BLD-Conference1/9/20071/9/20071/10/2007PDONE
DetailsDave Hannah
dennis - 2 hr wall enclosure ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
BLD-Framing/Rough-in1/8/20071/8/20071/8/2007PPART
DetailsDave Hannah
BLD-Framing/Rough-in1/5/20071/5/20071/8/2007PDEFR
DetailsDave Hannah
Routing - FIRE1/8/2007 1/8/2007 PASS
Plan modification of fire pump & secondary water tank-Acceptable per final approved fire sprinkler plans under permit FIR05-00425.
BLD-Wall cover1/4/20071/4/20071/5/2007ANR
DetailsDave Hannah
Dennis, ###-####
CHANGE STATUS TO (ISS)  1/5/2007 DONE
paid fee and picked up plan mod
(F) Reprint permit  1/5/2007 DONE
OVERRIDE  1/4/2007  
OVERRIDE  1/4/2007  
OVERRIDE  1/4/2007  
OVERRIDE  1/4/2007  
OVERRIDE  1/4/2007  
OVERRIDE  1/4/2007  
OVERRIDE  1/4/2007  
Override - Parcel Holds  1/4/2007  
Override - Parcel Holds  1/4/2007  
Override - People Holds  1/4/2007  
Telephone call  1/4/2007 DONE
lft vm with james woodbury ###-#### that permit and fees are ready to be picked up
Override - Parcel Holds  1/4/2007  
Override - Parcel Holds  1/4/2007  
Override - People Holds  1/4/2007  
Permit Ready to Issue  1/4/2007  
Telephone call  12/29/2006 DONE
lft vm with james woodbury ###-#### to verify the additional val added 9:50 am
BLD-Wall cover12/11/200612/12/200612/13/2006APART
DetailsDave Hannah
###-#### - dennis
Plan assigned to (JCM)11/13/200611/13/200612/13/2006 PASS
12/13/2006 08:32:22 JCM - activity updated through activity BLDA022 from case BLD05-01077.
Routing - PLAN CHECK12/12/2006 12/13/2006 PASS
PLANS/APPL TAKEN TO FRONT DESK  12/13/2006 DONE
Routing - PLUMBING11/30/2006 12/12/2006 PASS
Override - Parcel Holds  12/11/2006  
Override - Parcel Holds  12/11/2006  
BLD-Other11/27/200611/28/200611/29/2006PPART
DetailsDave Hannah
###-#### - dennis note: t-bar tile cover up on 4th floor ok to cover after fire oks
Plan resubmittals received  11/29/2006  
Received resubmittals for plan modification: Letter of transmittal and 2 copies of the following pages: P1.1, P2.1, P3.1, M1.1, M2.1, M4.1; taken to John Menard
Override - Parcel Holds  11/27/2006  
Override - Parcel Holds  11/27/2006  
Routing - PLAN CHECK11/17/2006 11/22/2006 PASS
Plan resubmittals requested  11/22/2006 DONE
E-mailed the applicant requesting revised plumbing and mechanical plans associated with the proposed plan modification. JCM
Plan resubmittals received  11/17/2006  
Received 1 cover transmittal, 2 copies of sheet A2.1.1 and taken to John Menard
Routing - FIRE11/15/2006 11/17/2006 PASS
Attached plan mod comments to plans.
Routing - PLAN CHECK11/14/2006 11/15/2006 FAIL
Plan Reviewer's activity  11/15/2006 FAIL
Reviewed plan modification to relocate the retail trash enclosure to the parking garage; relocate the business center to the west end of meeting room #104; to move the west wall of meeting room #104 approximately eight feet to the west; and to relocate the domestic, hydronic and geothermal water piping and equipment to the old retail trash and business center areas.
Plan resubmittals requested  11/15/2006 DONE
E-mailed the applicant requesting additional information. JCM
BLD-Final11/13/200611/14/200611/14/2006APART
DetailsDave Hannah
###-#### - dennis part elec rooms 5thru 11 ok
BLD-Final11/13/200611/13/200611/13/2006PNR
DetailsDave Hannah
###-#### - dennis
BLD-Final11/9/200611/13/200611/13/2006ANR
DetailsDave Hannah
###-#### - dennis
Override - Parcel Holds  11/9/2006  
Permit Ready to Issue  11/9/2006  
Plan Modification Accepted  11/9/2006  
Plan modification accepeted due to the congestion in the mechanical room housing the fire tank, fire pump, domestic, hyronic & geothermal system it became apparent that additional space is required to adequately house & service the equipment. The proposal is to relocate the biz center next to the meeting room. Relocate the retail trash next to stair #2. Relocating the domestic, hydronic & geothermal to these spaces on pages A0.1, A2.1, A3.14, A6.1, AT4.2, AT4.33, AT4.43, D-1, D-2, D-3; routed to John Menard
Override - Parcel Holds  11/9/2006  
BLD-Final10/26/200611/3/200611/7/2006ACANC
DetailsDave Hannah
Gene ###-####
BLD-Final10/26/200611/2/200611/2/2006ADEFR
DetailsDave Hannah
Gene ###-####
BLD-Final10/26/200611/1/200611/2/2006ADEFR
DetailsDave Hannah
Gene ###-####
BLD-Final10/26/200610/31/200611/1/2006ADEFR
DetailsDave Hannah
Gene ###-####
BLD-Final10/26/200610/30/200610/30/2006ANR
DetailsDave Hannah
Gene ###-####
Override - Parcel Holds  10/26/2006  
Override - Parcel Holds  10/26/2006  
Override - Parcel Holds  10/26/2006  
Override - Parcel Holds  10/26/2006  
Override - Parcel Holds  10/26/2006  
Override - Parcel Holds  10/26/2006  
BLD-Other10/12/200610/13/200610/13/2006ADONE
DetailsDave Hannah
dennis - ###-#### - wall cover up
Override - Parcel Holds  10/12/2006  
Override - Parcel Holds  10/12/2006  
Plan assigned to (JCM)9/19/20069/19/200610/5/2006 PASS
10/5/2006 09:41:13 JCM - activity updated through activity BLDA022 from case BLD05-01077.
Plan Reviewer's activity  10/5/2006 PASS
Reviewed and approved fire sprinkler secondary water tank modification. JCM
PLANS/APPL TAKEN TO FRONT DESK  10/5/2006  
BLD-Framing/Rough-in10/2/200610/4/200610/4/2006PPART
DetailsDave Hannah
interior 5th thru 11th floor \\###-#### dennis x10 room fire proofing ok
Routing Off Site - STRUCTURAL9/21/2006 10/4/2006 PASS
per john menard call courier for pickup - Received letter from consulting structural engineer approving the secondary water tank modifications with caution on not filling the upper tank completely full. JCM
Override - Parcel Holds  10/2/2006  
Plan Modification Accepted  9/19/2006  
Plan modification accepted for Bld05-01077 to relocate fire pump from mechanical room to new fire pump room. Fire tank modification from two tanks to one tank on sheets A2.1.1, A3.11, A3.14, S6.5. Routed to John Menard.
BLD-Wall cover9/15/20069/15/20069/15/2006PPART
DetailsDave Hannah
ok to cover elev lobbys 2 and 3rd floors
BLD-Conference9/13/20069/14/20069/14/2006APART
DetailsDave Hannah
Dave, need inspection on exterior? TMC will start brick tomorrow, so do we need a screw sign off on the dens gold? dennis part ok to start brick firs two floors
BLD-Wall cover9/9/20069/11/20069/11/2006APART
DetailsDave Hannah
Dave, our door labels are stamped into the frames and hard to read, could you check them out next time you are here. Dennis door frames are marked 1 and 1/2 hr
BLD-Wall cover9/7/20069/8/20069/8/2006AFAIL
DetailsDave Hannah
Dave, need the 4th floor shaft wall, and 10th 11th floor ceilings, and check the stair handrailing for code. Thanks Dennis ; Phone #: ###-#### ned to rework shafts
BLD-Wall cover8/28/20068/28/20068/28/2006PPART
DetailsDave Hannah
Dave, pool eq room and 11th elev lobby ok to cover
BLD-Wall cover8/26/20068/28/20068/28/2006ANR
DetailsDave Hannah
Dave, pool eq room and 11th elev lobby
BLD-Wall cover8/21/20068/23/20068/23/2006ANR
DetailsDave Hannah
Dave, Pool eq room 4th floor cover up. Dennis; Phone #: ###-####
BLD-Framing/Rough-in8/16/20068/17/20068/17/2006ADONE
DetailsDave Hannah
Dave, t-bar ceiling areas. Dennis
BLD-Framing/Rough-in8/16/20068/17/20068/17/2006APART
DetailsDave Hannah
Dave, t-bar ceiling areas. Dennis ok to cover 9th floor
BLD-Wall cover8/16/20068/16/20068/17/2006PPART
DetailsDave Hannah
Dave, t-bar ceiling areas. Dennis ok to cover 8th floor
FIRE-Sprinkler Rough-in8/15/20068/15/20068/15/2006PPART
DetailsForrest France
Inspection requested for sprinkler cover at the guest rooms adjacent to the temp. elevator at the 10th floor is okay, the 11th floor guest room at this location is not ready for inspection.
FIRE-Conference8/10/20068/14/20068/14/2006ADONE
DetailsForrest France
On site confrence to discuss occupancy requirements for the fourth floor parking area.
BLD-Wall cover8/9/20068/10/20068/10/2006PPART
DetailsDave Hannah
walk through on 4th and x10 rooms, misc t-bar areas. ok to drop 7th floor ceiling tile and cover ceilings x10 restrooms 6th and 7th fl
BLD-Wall cover8/4/20068/4/20068/4/2006APART
DetailsDave Hannah
Dave, late am would be best. or early afternoon. 6th floor. thanks Dennis ok to cover hard lids
BLD-Wall cover8/2/20068/3/20068/3/2006APART
DetailsDave Hannah
ok to cover lobby ceiling
BLD-Wall cover7/26/20067/27/20067/27/2006APART
DetailsDave Hannah
Please view the 11th floor hallway framing for cover. Thannk you. hallway hard lids ok to cover
BLD-Wall cover7/25/20067/26/20067/26/2006PPASS
DetailsDave Hannah
dave 7th and 8th floor corridor
BLD-Conference7/25/20067/26/20067/26/2006APASS
DetailsDave Hannah
Re-inpection at 7th & 9th floor plumbing pipe fire caulking for wall cover.

BLD-Wall cover7/24/20067/25/20067/25/2006APART
DetailsDave Hannah
Framing inspection for levels 8, 9, 10 & 11 room # x10. Please call Ray to view.; Phone #: ###-#### ok to cover walls
BLD-Conference7/21/20067/24/20067/24/2006APART
DetailsDave Hannah
Fire Caulking room x10 6th and 7th floor ok to cover walls
BLD-Final7/20/20067/21/20067/21/2006AFAIL
DetailsDave Hannah
Dave, thought you might want to walk the job. Dennis
BLD-Wall cover7/12/20067/13/20067/13/2006PPART
DetailsDave Hannah
5th floor drop ceilings in rooms ok to cover
BLD-Other7/11/20067/12/20067/13/2006PFAIL
DetailsDave Hannah
dennis Note: cover up on the 5th floor; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles room ceilings
Plan Reviewer's activity  7/13/2006 DONE
IFC question: Sent the following email answer to Linda Shinshiro's (Devcon's HVAC Consulting Engineer) email request for clarification on IFC 509.1 items 5 and 6.
"Linda, thank you for following up on this, as I somehow overlooked your letter. Instead of sending your letter back with your question/answer sections filled in, I will send my answers by this email to expedite them to you.

In my opinion, the short answers to your two questions are: 1) Item 5 refers to all building air handling systems; and 2) No, the stairwell pressurization fans are not the air-handling equipment referred to in Item 5.
However, I need to elaborate further, because you may have been confused by our parenthetical review comment on Item 6.

IFC 509.1 Item 5 refers to all building air handling systems.

IFC 509.1 Item 6 refers to the fire fighters control panel required by IFC 909.16 for building smoke control systems. Our parenthetical comment on this section “Not applicable” only referred to the fact that there is not a building smoke control system; I apologize that this is misleading. The pressurized stair option is addressed under “smoke proof exit enclosures” in the IBC 909.20, which specifies design requirements which are different than the criteria for building smoke control systems which are addressed in preceding sections of IBC 909 and IFC 909. So technically a stair pressurization system is different than a building smoke control system, but nonetheless it is a type of smoke control system. Refer to IFC 909.16.2 which states “The fire-fighter’s smoke control panel shall provide control capability over the complete smoke-control system equipment within the building as follows…” and then sub-Item 1 states “This includes stairway pressurization fans…”.

So my interpretation is that a fire-fighter’s control panel is required in the FD Command Center per 509.1 item 6 and it will have to include control capability over the stairway pressurization fans per IFC 900.16.2. Again, I apologize if our parenthetical review comment was the source of any confusion.

I will be out of the office tomorrow and next week. I'll be back on 7/24 if you need to discuss this further.
Regards,
Sam
Telephone call  7/13/2006 DONE
Conf call with James Woodbury and Gary Filizetti, Devcon, Keith Dilworth, BeDest, D. Hanneman, and others. Agreed: they will submit revised hydraulic calculations for the standpipes based on 750 gpm total demand and use of the tank/pump supply; they will recirculate the PRV discharge back into the fire tank; they will have a Calif. firm design a quality leak detection system (it will not be a low-bid design/build); fire pump and jockey pressure settings will be shown on the final pump/tank test documents given to the fire inspector at the final inspection; the 250 gpm hose demand will remain as specified; the fire tank capacity will remain as shown on the most recently approved plans.
Override - Condition Holds1/1/19001/1/19007/11/2006  
cover up only
BLD-Framing/Rough-in7/6/20067/7/20067/7/2006APART
DetailsDave Hannah
south half 11th floor heaters ok to cover
BLD-Wall cover7/6/20067/6/20067/6/2006PPART
DetailsDave Hannah
ok to cover canopy
BLD-Wall cover6/30/20067/5/20067/5/2006APART
DetailsDave Hannah
inspection 11th floor heater closets north half ok to cover
Plan resubmittals received  6/29/2006  
Recieved letter to Jennifer Gilliland, and letter to Lee Rice from Engineering Inc., duct system codes attachement #1 & #2, 3pg. specifications for Fire Smoke Dampers, pg. M5.0 & M5.1; taken to Lee Rice
BLD-Wall cover6/27/20066/28/20066/28/2006APART
DetailsDave Hannah
Dave please see Paul for lobby Ceiling re-inspection. ok to cover hard lids in lobby and lobby restrooms after other trades have signed off
BLD-Wall cover6/23/20066/27/20066/28/2006PPART
DetailsDave Hannah
5th floor walls and 11th floor ceilings in rooms ok to cover
BLD-Wall cover6/23/20066/26/20066/27/2006PNR
DetailsDave Hannah
BLD-Conference6/15/20066/15/20066/15/2006PPART
DetailsDave Hannah
early afternoon 10 floor south half room ceilings ok to cover
BLD-Wall cover6/9/20066/13/20066/14/2006PPART
DetailsDave Hannah
ext walls 5th fl ok to cover drop ceiling north half 10th floor ok to cover in rooms
BLD-Wall cover6/9/20066/12/20066/12/2006APART
DetailsDave Hannah
7th and 8th floor hallway harde lid areas ok to cover
BLD-Wall cover6/7/20066/8/20066/8/2006APART
DetailsDave Hannah
ground floor lobby ok to cover
BLD-Wall cover6/5/20066/6/20066/7/2006PPART
DetailsDave Hannah
fire proofing at floor levels in stair towers ok to start walls
Additional plans submitted  6/6/2006 FAIL
A single plan sheet was submitted to Lee Rice, Mechanical Insp Mgr by the Fire alarm vendor, Protex, showing a duct detector at the top of each of the shafts in lieu of the required detector at each on the three smoke dampered air duct openings on each floor into the shafts. No alternative design request or explanation of equivalency was included. Plan forwarded to Fire. The proposed design is not acceptable to Fire. Plan returned to Lee Rice.
BLD-Wall cover5/30/20065/31/20065/31/2006PNR
DetailsDave Hannah
Phone #: ###-####
BLD-Conference5/24/20065/31/20065/31/2006PNR
DetailsDave Hannah
Phone #: ###-####
BLD-Conference5/24/20065/30/20065/30/2006PPART
DetailsDave Hannah
Phone #: ###-####ext wall 11th floor ok to cover
BLD-Wall cover5/25/20065/26/20065/26/2006APART
DetailsDave Hannah
Fire proofing inspection at 9th floor ceiling. Please call Ray when you arrive to inspect. 9th floor room drop ceilings ok to cover
BLD-Conference5/24/20065/25/20065/25/2006APART
DetailsDave Hannah
Phone #: ###-#### south half of 10th floor ok to cover walls
BLD-Wall cover5/23/20065/23/20065/23/2006PPART
DetailsDave Hannah
Phone #: ###-#### north half of 10th floor ok to cover int walls
BLD-Wall cover5/17/20065/22/20065/22/2006ANR
DetailsDave Hannah
Phone #: ###-####
BLD-Wall cover5/17/20065/19/20065/19/2006AFAIL
DetailsDave Hannah
Phone #: ###-####
BLD-Wall cover5/16/20065/17/20065/17/2006APART
DetailsDave Hannah
walked 10th floor int walls not ready but ext wall ok to cover
BLD-Wall cover5/9/20065/16/20065/17/2006PDEFR
DetailsDave Hannah
BLD-Wall cover5/9/20065/15/20065/15/2006PPART
DetailsDave Hannah
ceilings on south half 8th floor rooms ok to cover
BLD-Wall cover5/9/20065/12/20065/15/2006PPART
DetailsDave Hannah
ext walls 10th floor ok to insulate
BLD-Wall cover5/9/20065/11/20065/11/2006PPART
DetailsDave Hannah
ceiling for rooms north half 8th floor ok to cover
BLD-Wall cover5/9/20065/10/20065/10/2006PPART
DetailsDave Hannah
ok to cover walls on south half of 9th floor
BLD-Wall cover5/9/20065/9/20065/9/2006PPART
DetailsDave Hannah
ok to insulate south half of 9th floor
BLD-Wall cover5/2/20065/5/20065/8/2006PDEFR
DetailsDave Hannah
Please call Dennis or Ray when you arrive.
BLD-Conference5/4/20065/5/20065/5/2006APASS
DetailsDave Hannah
dave, YMC and Devcon would like to go over the elevator shaft fire rating one more time. this would be at the roof level. give me a call to set a time. thanks Dennis; Phone #: ###-####
BLD-Wall cover5/2/20065/4/20065/4/2006PPART
DetailsDave Hannah
Please call dennis or Ray when you arrive. furcaces the rest of 8th floor and walls north half of 9th ok to cover
BLD-Wall cover5/2/20065/3/20065/4/2006PDEFR
DetailsDave Hannah
Please contact Dennis or Ray when you arrive. out of time for the day
BLD-Wall cover5/2/20065/2/20065/3/2006PPART
DetailsDave Hannah
Please call Dennis or Ray when you arrive.
BLD-Wall cover4/27/20064/28/20064/28/2006APASS
DetailsTom Arcoraci
8th floor floor holes ok 7th floor drops in rooms ok
BLD-Wall cover4/21/20064/27/20064/27/2006PPART
DetailsTom Arcoraci
Phone #: ###-#### wip
BLD-Wall cover4/21/20064/26/20064/26/2006PPART
DetailsDave Hannah
Phone #: ###-#### ok to insulste 9th floor ext walls ok to cover 6th floor heater units
BLD-Wall cover4/21/20064/25/20064/25/2006PPART
DetailsDave Hannah
Phone #: ###-#### north half of 8th floor ok to cover walls
BLD-Wall cover4/24/20064/24/20064/24/2006PFAIL
DetailsDave Hannah
Dave, could we get you first thing monday, say by 9am. for the heater closets at the 6th floor. Thanks Dennis; Phone #: ###-####
BLD-Wall cover4/21/20064/24/20064/24/2006ACANC
DetailsDave Hannah
Dave, could we get you first thing monday, say by 9am. for the heater closets at the 6th floor. Thanks Dennis; Phone #: ###-####
BLD-Wall cover4/14/20064/21/20064/21/2006PPART
DetailsDave Hannah
Phone #: ###-#### wip
BLD-Wall cover4/20/20064/21/20064/21/2006APART
DetailsDave Hannah
Dave, RAy say we are ready. south side 6th floor hard lids ok to cover
BLD-Wall cover4/14/20064/20/20064/20/2006PNR
DetailsDave Hannah
Phone #: ###-####
BLD-Wall cover4/14/20064/19/20064/20/2006PPART
DetailsDave Hannah
Phone #: ###-#### wip
BLD-Wall cover4/14/20064/18/20064/19/2006PCANC
DetailsDave Hannah
Phone #: ###-####
BLD-Wall cover4/14/20064/17/20064/17/2006PPART
DetailsDave Hannah
Phone #: ###-####
BLD-Wall cover4/8/20064/14/20064/14/2006PPART
DetailsDave Hannah
Phone #: ###-#### ok to install hard lids on north half of 6th floor
BLD-Wall cover4/8/20064/13/20064/14/2006PNR
DetailsDave Hannah
Phone #: ###-####
BLD-Wall cover4/8/20064/12/20064/13/2006PDONE
DetailsDave Hannah
Phone #: ###-####
BLD-Wall cover4/8/20064/11/20064/11/2006PPART
DetailsDave Hannah
Phone #: ###-####
BLD-Wall cover4/8/20064/10/20064/10/2006PNR
DetailsDave Hannah
Phone #: ###-####
BLD-Wall cover4/3/20064/10/20064/10/2006ADONE
DetailsDave Hannah
Phone #: ###-####
BLD-Wall cover4/3/20064/7/20064/7/2006ADONE
DetailsDave Hannah
Phone #: ###-####
BLD-Wall cover4/7/20064/7/20064/7/2006PPART
DetailsDave Hannah
Phone #: ###-#### pent house ok to cover
BLD-Wall cover4/3/20064/6/20064/6/2006APART
DetailsDave Hannah
Phone #: ###-####
BLD-Wall cover4/3/20064/5/20064/5/2006ANR
DetailsDave Hannah
Phone #: ###-####
BLD-Wall cover4/3/20064/4/20064/4/2006PPART
DetailsDave Hannah
Phone #: ###-#### ext walls on 8th floor
BLD-Wall cover4/3/20064/3/20064/3/2006ADONE
DetailsDave Hannah
Phone #: ###-####
BLD-Wall cover3/28/20063/31/20064/3/2006PPART
DetailsDave Hannah
Phone #: ###-#### north half int walls ok to cover on 7th floor
BLD-Wall cover3/28/20063/30/20063/30/2006PPART
DetailsDave Hannah
Phone #: ###-#### 8th floor ext wall fire proofing ok
BLD-Wall cover3/28/20063/29/20063/30/2006PCANC
DetailsDave Hannah
Phone #: ###-#### out of time rescheduled
BLD-Wall cover3/22/20063/28/20063/29/2006PPART
DetailsDave Hannah
Phone #: ###-#### south half of 6th floor mins 3 rooms ok to cover
BLD-Wall cover3/27/20063/27/20063/28/2006PFAIL
DetailsDave Hannah
call me, Dennis; Phone #: ###-#### floor and ceiling fire proofing not completed on south half of 6th floor
BLD-Wall cover3/20/20063/27/20063/27/2006AFAIL
DetailsDave Hannah
call me, Dennis; Phone #: ###-#### south half of 6th floor
BLD-Wall cover3/20/20063/24/20063/27/2006ANR
DetailsDave Hannah
call me, Dennis; Phone #: ###-####
BLD-Framing/Rough-in3/24/20063/24/20063/24/2006PNR
DetailsDave Hannah
call me, Dennis; Phone #: ###-####
BLD-Conference3/23/20063/23/20063/24/2006PPART
DetailsDave Hannah
dave; Phone #: ###-#### 6th floor ok to cover int walls on north half of floor
BLD-Wall cover3/20/20063/23/20063/24/2006PPART
DetailsDave Hannah
call me to see if you need to come by. Dennis; Phone #: ###-#### 7th floor ok to insulate ext walls
BLD-Wall cover3/22/20063/23/20063/23/2006APART
DetailsDave Hannah
dave some time in am like 9:30, thanks Dennis; Phone #: ###-#### 5th floor plumbing fire caulking ok
BLD-Wall cover3/20/20063/22/20063/22/2006PPART
DetailsDave Hannah
Dave, cover up walls, ; Phone #: ###-#### ok to insulate ext walls on 7th floor
BLD-Wall cover3/20/20063/21/20063/21/2006APART
DetailsDave Hannah
Dave, cover up walls, i have 10 am meeting so eairler will be better. ; Phone #: ###-#### north half of 6th floor ok to cover ext wall
BLD-Wall cover3/10/20063/17/20063/17/2006AFAIL
DetailsDave Hannah
Dave, cover up of walls; Phone #: ###-#### wrong kind if vapor bar on 6th flr
BLD-Wall cover3/10/20063/16/20063/16/2006APART
DetailsDave Hannah
Dave, fire proofing inspections give me a call, Dennis; Phone #: ###-#### work in progress oh 5th and 6th floors
BLD-Conference3/10/20063/16/20063/16/2006APART
DetailsDave Hannah
Dave, cover up of walls; Phone #: ###-#### ok to open 1st,second and third floors of parking garage
FIRE-Final Inspection3/15/20063/16/20063/16/2006APART
DetailsForrest France
Correction notice items related to the parking garage ground level, 2nd and 3rd levels have been verified for completion, fire alarm and sprinkler associated with the garage 1st,2nd and 3rd levels for temporary occupancy in this limited area ONLY are completed.
BLD-Wall cover3/10/20063/15/20063/16/2006APART
DetailsDave Hannah
Dave, fire proofing inspections give me a call, Dennis; Phone #: ###-#### work in progress on 5th and 6th floors
BLD-Final3/14/20063/15/20063/16/2006ANR
DetailsDave Hannah
Dave please contact me on time, Forest has to look at the e-lights one more time, like to get the sign off tomorrow am. thanks Dennis; Phone #: ###-#### still needs fire F/L/S sign off
BLD-Wall cover3/10/20063/14/20063/15/2006PPART
DetailsDave Hannah
Dave, fire proofing inspections give me a call, Dennis; Phone #: ###-####
FIRE-Final Inspection3/14/20063/15/20063/15/2006AFAIL
DetailsForrest France
Provide keys in knox box, relocate temporary fence at alley to allow access to fire dept. WPI and FDC, provide signage at the door to the riser/pump room, provide lockout for air compressor circut switches, provide emergency egress illumination for the exit corridor from the fire command center, install work table for the fire command center.
BLD-Wall cover3/7/20063/14/20063/14/2006ACANC
DetailsDave Hannah
Call Dennis Harter for time.; Phone #: ###-####
BLD-Final3/13/20063/14/20063/14/2006ANR
DetailsDave Hannah
Dave, Forest will walk tomorrow at 8:30 for the life safety, if you could be down here shortly after that say 9:30 to walk. thanks Dennis; Phone #: ###-####
FIRE-Final Inspection3/13/20063/14/20063/14/2006AFAIL
DetailsForrest France
Life safety Inspection for the parking structure ground level, 2nd, and 3rd floors for temp. occupancy failed due to non-functional emergency lights at the 2nd and 3rd levels, fire extinguishers at two locations are mounted too high, minor fire sprinkler issues,emergency lighting at stair #3 not tested, fire apparatus access roads must meet requirements of IFC 2003 503.2.1 and 503.4.
BLD-Final3/7/20063/10/20063/14/2006PNR
DetailsDave Hannah
Call Dennis Harter for time.; Phone #: ###-####
FIRE-Final Inspection3/10/20063/13/20063/13/2006PNR
DetailsForrest France
The project related alarm and sprinkler must be approved prior to life safety final.
BLD-Wall cover3/7/20063/13/20063/13/2006APART
DetailsDave Hannah
Call Dennis Harter for time.; Phone #: ###-####
BLD-Wall cover3/7/20063/10/20063/10/2006AFAIL
DetailsDave Hannah
Call Dennis Harter for time.; Phone #: ###-#### still working on fire proofing
BLD-Final3/7/20063/9/20063/9/2006APART
DetailsDave Hannah
Call Dennis Harter for time.; Phone #: ###-####
BLD-Wall cover3/7/20063/9/20063/9/2006APART
DetailsDave Hannah
Call Dennis Harter for time.; Phone #: ###-####
BLD-Wall cover3/7/20063/8/20063/8/2006ADONE
DetailsDave Hannah
Call Dennis Harter for time.; Phone #: ###-####
BLD-Wall cover2/28/20063/7/20063/8/2006PPART
DetailsDave Hannah
Phone #: ###-####
BLD-Wall cover3/1/20063/6/20063/6/2006APART
DetailsDave Hannah
Phone #: ###-#### fite protection 6th floor
BLD-Framing/Rough-in3/3/20063/3/20063/6/2006PPART
DetailsDave Hannah
Dave, Hanna, AM inspection ; Phone #: ###-#### 5th and 6th floor fire proofing
BLD-Wall cover2/28/20063/3/20063/6/2006APART
DetailsDave Hannah
Dave, Hanna, AM inspection ; Phone #: ###-#### 5th and 6th floor
BLD-Wall cover3/2/20063/2/20063/3/2006PPART
DetailsDave Hannah
fire protection floor and columns 5th flr
Print Occupancy Form  3/3/2006 DONE
BLD-Wall cover3/1/20063/2/20063/2/2006ACANC
DetailsTom Arcoraci
Phone #: ###-####
BLD-Wall cover2/28/20063/1/20063/1/2006APART
DetailsDave Hannah
Dave, Hanna, AM inspection ; Phone #: ###-#### ext beam fire proofing ok6th fl
BLD-Framing/Rough-in2/23/20062/24/20062/24/2006ANR
DetailsDave Hannah
Inspection---please call Dennis Harter at ###-#### Internet Inspection Request from: Alex Monge
Routing - FIRE2/17/2006 2/24/2006 FAIL
DetailsBill Alexander
FIR05-00425 Secondary Water Supply
1. This re-modified secondary water supply system for the new 235,965-ft/2, eleven story high rise structure is currently not a standard secondary water storage holding system. Under IFC 104.7.2, this reviewing authority shall require the following minimum requirements:
A. Obtain and submit approval incorporating (wet) stamped plan/s and reviewing comment letter from an approved, current, registered certified Fire Protection Engineer, of a design meeting the minimum requirements in regard to the associated current adopted NFPA 13, 20, 22 and 72 pamphlets, with approval of the secondary water supply "tank" that includes, (but may not be limited to) associated sizing's, locations, fire pump connection/s, fill line/s, overflow and associated (listed) manufacturer's controls, sensing and related devices and appurtenances being incorporated in the required automatic secondary water supply system in this facility.
February 10, 2006 - Provided revised tank and piping plans. Several issues found under this submittal which need addressed, verified and corrected:
i) Possible pump cavitation problem relating to the upper tank draw down level equal to the "0" head level of the lower tank allowing suction (entrance) of air being drawn into the pump suction line. Provide a design which will verify and prevent possible pump cavitation and failure.
February 24, 2006 - Designers revised plan include a "P" trap on the suction line for the 2nd (upper) tank. There is no design verification data provided to address the draft characteristics of each tank, but it would appear the combined tank draw down would draft air since the "P" trap is still above the level of the tank floor (where the level of the required draw down is designed for). This would still enable the suction (entrance) of air in the suction piping and thus create fire booster pump cavitation. Revise and resubmit corrected drawings.
Telephone call  2/17/2006 DONE
Telcon from Keith at DeBest. He can't get "stamped" plans from the FPE until Thursday, will submit to us on Friday. He wants to bring over revised fire tank plans now for us to start review to expedite things. I agreed to do that but would not show it as official submittal of plans or release "approved" plans until they submitted the stamped plans. He will bring them in tomorrow morning.
Routing - FIRE2/7/2006 2/10/2006 FAIL
DetailsBill Alexander
FIR05-00425 - February 10, 2006 - Received revised tank and piping plans submitted by Devcon. Several issues found under this submittal which need addressed, verified and corrected:
i) Possible pump cavitation problem relating to the upper tank draw down level equal to the "0" head level of the lower tank, allowing suction (entrance) of air being drawn into the pump suction line. Provide a design which will verify and prevent possible pump cavitation and failure. Called FPE, Mike Madden and explained. He will re-design and have DeBest submit revised plans with his "review" stamp on them.
ii) The tank fill lines have butterfly separation valves located on the discharge sides of the "Cla-Val" valves? It would be wise to relocate these "butterfly" valves to the supply sides of these valves for separate isolation of the same. This will accommodate individual instead of double deactivation if either requires repair. Review comments sent to DeBest.
February 10, 2006 - The wall extensions, tank load of one over the other, pipe penetrations, modification of tank floor, etc., will require written approval verification by an approved structural engineer by prior to IFC final tank approval.
Resubmittal also included sheets A2.1 and A2.1.1 modified to show rated corridor wall from exterior to Fire Command center. Proposed corridor design and rating acceptable from fire standpoint. Plans routed to JCM for Building approval and distribution of modified plans.
Plan resubmittals received  2/7/2006  
5 copies of each of the following; A3.11, A2.1, A2.1.1, cover sheet, classic schedule layout, Hughes Associates response letter. Taken to John M.
Routing - FIRE12/28/2006 1/5/2006 FAIL
DetailsBill Alexander
1. This re-modified secondary water supply system for the new 235,965-ft/2, eleven story high rise structure is currently not a standard secondary water storage holding system. Under IFC 104.7.2, this reviewing authority shall require the following minimum requirements:
Obtain and submit approval incorporating (wet) stamped plan/s and reviewing comment letter from an approved, current, registered certified Fire Protection Engineer, of a design meeting the minimum requirements in regard to the associated current adopted NFPA 13, 20, 22 and 72 pamphlets, with approval of the secondary water supply "tank" that includes, (but may not be limited to) associated sizings, locations, fire pump connection/s, fill line/s, overflow and associated (listed) manufacturer's controls, sensing and related devices and appurtenances being incorporated in the required automatic secondary water supply system in this facility.
Any structural related issues possibly affected by the F.P.E.'s reviewing design (which have not been incorporated in these resubmitted structural tank plans/documents), shall be fully coordinated and under the full responsibility of DEVCON and it's Architect for the same.
Plan resubmittals received  12/28/2005 DONE
Received cover transmittal from Sylvester Ramirez, 3 copies of revised structural calcs and 3 copies of plan sheets A3.11and S6.5 which are structural revisions for the fire tank. Forwarded all items to John M.
Permit Ready to Issue  12/22/2005  
(F) Reprint permit  12/22/2005 DONE
CHANGE STATUS TO (ISS)  12/22/2005 DONE
re-issued
Routing - PLAN CHECK12/9/2005 12/21/2005 PASS
PLANS/APPL TAKEN TO FRONT DESK  12/21/2005 DONE
Permit Ready to Issue  12/21/2005 DONE
Print Occupancy Form  12/21/2005 DONE
CHANGE STATUS TO (PND)  12/21/2005 DONE
Plan assigned to (JCM)4/26/2005 12/21/2005 PASS
12/21/2005 13:52:31 JCM - activity updated through activity BLDA022 from case BLD05-01077.
Routing Off Site - STRUCTURAL11/28/2005 12/16/2005 PASS
Called P D Q for pick up
Routing Off Site - STRUCTURAL12/5/2005 12/16/2005 PASS
E-mailed a copy of the additional structural calculations for the secondary water tank. JCM
Routing Off Site - STRUCTURAL12/12/2005 12/15/2005 PASS
Called P D Q for pick up - Received an e-mailed letter from the consulting structural engineer approving the last submittals on the secondary water tank. JCM
Plan resubmittals received  12/12/2005 DONE
Received 1 transmittal , 3 plan check response books , & 3 copy of sheet S6.5 Taken to John M.
Routing - FIRE11/23/2005 12/9/2005 PASS
Resub acceptable subject to Fire Command center functions being provided as indicated and annotated on sheet A0.1. Phoned architect to advise; review faxed to architect.
Plan resubmittals received  12/5/2005  
Received copies of additional structural calculations for the secondary water tank. JCM
Plan resubmittals requested  12/2/2005 DONE
E-mailed Sylvester with a copy of the comment list for the secondary water tank requesting revisions. JCM
Plan Reviewer's activity  12/1/2005 PASS
Reviewed and approved last resubmitted plan sheets. JCM
Routing Off Site - STRUCTURAL11/18/2005 12/1/2005 FAIL
Called PDQ for pick up - received an e-mailed comment list from the consultng structural engineer for the secondary water tank requesting revisions. JCM
Plan resubmittals received  11/30/2005  
Received (2) copies of sheet A2.1, A3.8 and A8.3. Routed to John M.
Plan resubmittals received  11/25/2005  
Received (3) copies of sheet S1.1, S1.2, S2.1, S6.5 and (3) sets of structural calcs for water tank. Routed to John M.
Routing - PLAN CHECK10/31/2005 11/24/2005 FAIL
Plan resubmittals requested  11/23/2005 DONE
E-mailed Sylvester Ramirez with a request for additional revisions.
Plan resubmittals received  11/18/2005  
Received (1) copy of S6.5 and (3) copies of structural calcs. Routed to John M.
Plan resubmittals received  11/18/2005 DONE
Received 1 (Copy of Structural Calcs) & 1 copy of sheets S6.5,A2.1, A2.2,A2.11 Taken to John M.
Plan resubmittals received  11/17/2005  
Received (2) copies of sheet A2.1, A2.1.1, A2.2, A2.2.1, kA2.3, A2.3.1, A2.4, A2.4.1, A2.5.1, A2.6.1, A2.7.1, A2.8.1, A2.9.1, A2.10.1, A2.11.1, A3.8, A3.9, A3.11, A5.3.1, A5.4, A7.3, A8.1, A8.2, A8.4, A8.10, AT4.2, S6.5, M1.1, M2.4, P1.4, P1.5, P1.6, P2.3, P2.4 and P2.5. Routed to John M.
Plan resubmittals received  11/17/2005  
Received (3) copies of Polyurea tank lining details and product data. Routed to John M.
Plan resubmittals requested  11/10/2005 DONE
E-mailed the architect with a copy of the second plan review comment list requesting additional revisions. JCM
Routing - FIRE10/14/2005 10/31/2005 FAIL
Revised review comments faxed to architect and discussed by phone today; he will bring revised plans in on Wed and discuss with us.
Plan resubmittals received  10/27/2005 DONE
Received 1 Building code review, & 2 copys of sheets A2.1,A2.2,A2.3,A2.4,A2.5,A2.6,A2.6.1,A2.7,A2.7.1,A2.8,A2.8.1,A2.9,A2.9.1,A2.10,A2.10.0,A2.11,A2.11.1,A3.7,A3.9,A4.2,A4.3,A4.5,A4.6,A4.7,A5.3.1,A5.3.2,A5.3.3,A5.3.4,A5.3.5,A5.3.6,A5.3.7,A5.3.8,A5.3.9,A7.1,A7.2,A7.3,A8.1,A8.2,A8.4,A8.10,AT4.0,AT4.2,AT4.14,AT4.22,AT4.24AT4.29,AT4.31,AT4.45,M2.2,M2.3,M2.4,M4.2,E-2.1,E-2.5 taken to John M.
Plan resubmittals requested  10/14/2005 DONE
E-mailed Sylvester a copy of the second plan review letter requesting additional revisions. JCM
Routing - PLAN CHECK6/22/2005 10/14/2005 FAIL
Plan resubmittals received  9/23/2005  
Received (4) copies of sheet M1.0, M1.1, M1.2, M1.3, M1.4, M1.5, M1.6, M1.7, M2.1, M2.2, M2.3, M2.4, M3.1, M4.1, M4.2 and (4) sets of LM100A Fire Alarm System Wiring Drawings. Two of these sets are included with full plans submittal listed below. Received (2) copies of sheet A0.1, EN.1, A1.1, A1.2, A1.3, A1.4, A1.5, A2.1, A2.1.1, A2.2, A2.2.1, A2.3, A2.3.1, A2.4, A2.4.1, A2.5, A2.5.1, A2.3, A2.6.1, A2.7, A2.7.1, A2.8, A2.8.1, A2.9, A2.9.1, A2.10, A2.10.1, A2.11, A2.11.1, A2.12, A3.1, A3.2, A3.3, A3.4, A3.5, A3.6, A3.7, A3.8, A3.9, A3.10, A4.1, A4.2, A4.3, A4.4, A4.5, A4.6, A4.7, A5.1, A5.2, A5.3, A5.3.1, A5.3.2, A5.3.3, A5.3.4, A5.3.5, A5.3.6, A5.3.7, A5.3.8, A5.3.9, A5.4, A6.1, A6.2, A6.3, A6.4, A6.5, A6.5, A6.6, A6.7, A6.8, A6.9, A6.10, A6.11, A7.1, A7.2, A7.3, A7.4, A7.5, A8.1, A8.2, A8.3, A8.4, A8.5, A8.6, A8.7, A8.8, A8.9, A8.10, AT2.1, AT2.5, AT2.6, AT2.7, AT2.8, AT2.9, AT2.10, AT2.11, AT4.0, AT4.1, AT4.2, AT4.4, AT4.4.1, AT4.4.2, AT4.4.3, AT4.5, AT4.6, AT4.7, AT4.8, AT4.9, AT4.10, AT4.11, AT4.12, AT4.13, AT4.14, AT4.15, AT4.16, AT4.17, AT4.18, AT4.19, AT4.20, AT4.21, AT4.22, AT4.23, AT4.24, AT4.25, AT4.26, AT4.27, AT4.28, AT4.29, AT4.30, AT4.31, AT4.32, AT4.33, AT4.34, AT4.35, AT4.36, AT4.37, AT4.38, AT4.39, AT4.40, AT4.41, AT4.42, AT4.43, AT4.44, AT4.45, AT4.46, AT4.47, AT4.48, AT4.49, AT4.50, AT5.0, AT5.1, AT5.2, AT5.3, AT5.4, AT5.5, AT5.6, AT5.7, AT5.8, AT5.9, AT5.10, PL1.1, PL1.2, Pl1.3, PL1.4, PL1.5, E-001, E-1.0, E-1.2, E-1.4, E-1.5, E-1.6, E-1.7, E-1.8, E-1.9, E-1.10, E-1.11, E-1.12, E-2.1, E-2.2, E-2.3, E-2.4, E-2.5, E-2.6, E-2.7, E-2.8, E-2.9, E-2.10, E-2.11, E-2.12, E-3.1, E-3.2, E-3.3, E-3.4, E-3.5, E-3.6, E-3.7, E-3.8, E-3.9, E-3.10, E-3.11, E-3.12, E-4.01, E-4.02, E-4.03, E-4.04, E-4.05, E-4.06, E-4.07, E-5.01, E-8.01, E-8.02, E-8.03, E-8.04, E-8.05, SE-1, P1.1, P1.2, P1.3, P1.4, P1.5, P1.6, P2.1, P2.2, P2.3, P2.4, P2.5, P2.6, P2.7, P3.1, P4.1 and P4.2. Routed to John M.
Meeting  7/14/2005  
Met with Sylvester Ramerez and two representatives from the project mechanical engineering firm to discuss some building design options and several items on the plan review comment list.
1st review completed  6/22/2005 FAIL
failed plan check and fire.
Routing - FIRE6/16/2005 6/22/2005 FAIL
review comments faxed to architect.
Plan resubmittals requested  6/16/2005 DONE
E-mailed a copy of the plan review cover letter and comment list to Sylvester Ramirez. JCM
Routing - PLAN CHECK5/17/2005 6/16/2005 FAIL
Routing - PLUMBING5/4/2005 5/17/2005 PASS
per plans(P1.1 submitted 5/16) and 2003 upc.
Plan resubmittals received  5/16/2005 DONE
Received Transmittal , & 2 Copys of sheet P1.1 Taken to John M.
Routing - PLANNING5/2/2005 5/4/2005 PASS
Approved per DRH03-00187.
Routing - PUBLIC WORKS4/26/2005 5/2/2005 PASS
Voucher Form  4/28/2005 DONE
DetailsDave Hannah
Plans ACCEPTED BY PLAN TECH  4/26/2005  
Application received  4/22/2005  
Recd Pcfee & Taken To Pln CK  4/22/2005 DONE