BLD-Final | 7/27/2005 | 7/27/2005 | 7/27/2005 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/27/2005 at 8:45:47 AM. Contact: ###-####. ok for c.c
|
BLD-Final | 7/13/2005 | 7/14/2005 | 7/15/2005 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/13/2005 at 2:00:50 PM. Contact: ###-####. ok to occ needs mec on new gas piping
|
FIRE-Final Inspection | 7/14/2005 | 7/14/2005 | 7/14/2005 | P | PASS |
Forrest France
|
|
|
Fire life safety passed inspection.
|
FIRE-Final Inspection | 7/13/2005 | 7/14/2005 | 7/14/2005 | A | FAIL |
Forrest France
|
|
|
Remove thumbturn bolt lock on back kitchen door NW corner, post max occupant load sign, remove thumbturn bolt lock on exit door at brewing room (see plan review notes #22 and #24).
|
BLD-Conference | 7/7/2005 | 7/8/2005 | 7/8/2005 | P | DONE |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/7/2005 at 1:22:35 PM. Contact: ###-####.
|
FIRE-Conference | 7/7/2005 | 7/8/2005 | 7/8/2005 | A | DONE |
Forrest France
|
|
|
On site discussion with Chris regarding door hardware requirements, fire ext. placement, building addressing, type 2 hood, occ. load sign, and emergency light testing.
|
BLD-Wall cover | 6/15/2005 | 6/15/2005 | 6/16/2005 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/15/2005 at 7:11:10 AM. Contact: ###-####. ok to cover wall between bar tanks and partions after plmb r/i
|
FIRE-Conference | 6/15/2005 | 6/16/2005 | 6/16/2005 | A | DONE |
Forrest France
|
|
|
Discussed emergency lighting placement and exit sign locations with Tim the GC and electrical contractor.
|
Plan assigned to (R_H) | 5/2/2005 | | 6/6/2005 | | PASS |
|
|
|
6/6/2005 14:42:48 MYS - activity updated through activity BLDA022 from case BLD05-01107.
|
Routing - FIRE | 6/1/2005 | | 6/6/2005 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 6/6/2005 | | 6/6/2005 | | PASS |
|
|
|
Passed and taken to the permit desk on behalf of Ron Hill.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/6/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/6/2005 | | |
|
|
|
|
Permit Ready to Issue | | | 6/6/2005 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/6/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/23/2005 | | 6/1/2005 | | PEND |
|
|
|
Resubmittals reviewed and approved, plans were rerouted to fire on 6/01/05, permit pending fire departments approval.
|
Plan resubmittals received | | | 5/31/2005 | | |
|
|
|
Received (4) copies of sheet F2.11, M2.0 and (2) copies of sheet A2.11 , E2.0 and E3.0. Routed to Ron H.
|
Routing - FIRE | 5/18/2005 | | 5/23/2005 | | FAIL |
|
|
|
review faxed to architect.
|
1st review completed | | | 5/23/2005 | | FAIL |
|
|
|
failed plan check and fire.
|
Routing - PLAN CHECK | 5/13/2005 | | 5/18/2005 | | FAIL |
|
|
|
Faxed and mailed requirements to the architect on 5/18/04
|
Routing - PLUMBING | 5/6/2005 | | 5/13/2005 | | PASS |
|
|
|
approved per plan an 2003 UPC: retest building DCVA if not done in last 12 months and provide thermal expansion tank if one does not exist.
|
Routing - PLANNING | 5/4/2005 | | 5/6/2005 | | PASS |
|
|
|
Approved per DRH03-00067.
|
Routing - PUBLIC WORKS | 5/2/2005 | | 5/4/2005 | | PASS |
|
|
|
|
Pending Assignment by MYS | 4/26/2005 | | 5/2/2005 | | DONE |
|
|
|
5/2/2005 13:41:30 MYS - activity updated through activity BLDA175 from case BLD05-01107.
|
Override - Parcel Holds | | | 4/26/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/26/2005 | | DONE |
|
|
|
|
Application received | | | 4/26/2005 | | |
|
|
|
|
Fee Review-notes | 4/26/2005 | 4/26/2005 | | | |
|
|
|
|