BLD-Final | 1/5/2006 | 1/6/2006 | 1/6/2006 | P | PASS |
Mike Jordan
|
|
|
med ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
DOC - Permit Finaled | 1/6/2006 | 1/6/2006 | 1/6/2006 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 10/11/2005 | 10/11/2005 | 10/11/2005 | P | PASS |
Tom Arcoraci
|
|
|
ned ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 10/11/2005 | 10/11/2005 | 10/11/2005 | P | PASS |
Tom Arcoraci
|
|
|
ned ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 10/4/2005 | 10/4/2005 | 10/4/2005 | P | PART |
Jim Storey
|
|
|
ned; Phone #: ###-#### Internet Inspection Request from: Barbara Moore framing ok stairs outstanding c/n
|
BLD-Framing/Rough-in | 9/22/2005 | 9/22/2005 | 9/22/2005 | P | FAIL |
Tom Arcoraci
|
|
|
###-#### Nad cn posted
|
BLD-Framing/Rough-in | 9/12/2005 | 9/12/2005 | 9/12/2005 | P | FAIL |
Tom Arcoraci
|
|
|
Phone #: ###-#### Internet Inspection Request from: Barbara Moore needs plans truss eng ect..... not ready
|
Issue PAID IN FULL permit | | | 7/7/2005 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 5/26/2005 | 5/26/2005 | 6/20/2005 | | PASS |
|
|
|
6/20/2005 08:42:55 SRZ - activity updated through activity BLDA022 from case BLD05-01128.
|
Case Summary (BLD) | | | 6/20/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/20/2005 | | DONE |
|
|
|
ONE SET RED-LINED.
|
Inspection Record Card- Bld | | | 6/20/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/20/2005 | | DONE |
|
|
|
|
Telephone call | | | 6/20/2005 | | DONE |
|
|
|
tlk to Ned ###-#### that permit and fees are ready to be picked up
|
Routing - PLAN CHECK | 5/4/2005 | | 6/20/2005 | | PASS |
|
|
|
|
BLD-Footing | 6/6/2005 | 6/7/2005 | 6/7/2005 | A | PASS |
Mike Jordan
|
|
|
###-#### - WADE
|
Early Start Permit | | | 6/6/2005 | | DONE |
|
|
|
|
Early Start Permit | | | 6/6/2005 | | |
|
|
|
|
Early Start Permit | | | 6/6/2005 | | |
|
|
|
|
Early Start Permit | | | 6/6/2005 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 5/27/2005 | | |
|
|
|
|
Plan Reviewer's activity | | | 5/27/2005 | | PASS |
|
|
|
Pending roof framing plan from the Builders Truss company. I spoke with Erin at Western Truss. She's in the process of getting info to me so I can complete the plan Review. (SRZ) I spoke with Truss Company again on 06-07-05. Truss Company is waiting on re-design from Designer to be able to finish the roof design. (SRZ)
|
Routing - PUBLIC WORKS | 5/4/2005 | | 5/4/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 4/27/2005 | | 5/2/2005 | | PASS |
|
|
|
4/29 fail - meet driveway distance from intersection
5/2/05 - met with applicant, plans approved as noted
|
Application received | | | 4/27/2005 | | |
|
|
|
|