Case Summary (BLD) | | | 1/23/2013 | | DONE |
|
|
|
|
Second Notice BLD | 4/23/2008 | 4/23/2008 | 4/25/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | 3/5/2008 | 3/5/2008 | 4/23/2008 | | DONE |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 3/5/2008 | 3/5/2008 | 3/5/2008 | | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 3/5/2008 | 3/5/2008 | 3/5/2008 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 10/17/2005 | 10/17/2005 | 10/17/2005 | | PASS |
Dave Hannah
|
|
|
wip
|
Case Summary (BLD) | | | 7/19/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/18/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/20/2005 | | 6/21/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/21/2005 | | |
|
|
|
|
Permit Ready to Issue | | | 6/21/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/21/2005 | | DONE |
|
|
|
|
Telephone call | | | 6/21/2005 | | DONE |
|
|
|
left mess for katie butler ###-#### is ready
|
Routing - FIRE | 6/15/2005 | | 6/20/2005 | | PASS |
|
|
|
Resubmittal acceptable; revised comments faxed to architect.
|
Plan resubmittals received | | | 6/15/2005 | | DONE |
|
|
|
Received 2 Copys of sheets C1.1,C1.4,L1.1 inserted into plans and routed to Fire ///DLD
|
Routing - PUBLIC WORKS | 6/14/2005 | | 6/15/2005 | | |
|
|
|
Brian, you stamped and signed this on 5-4-05 but they resubmitted the c1.4 sheet so i need you to re stamp that sheet then send to fire... Thanks Darla
|
Plan resubmittals received | | | 6/14/2005 | | DONE |
|
|
|
Received Transmittal Letter ,1 Letter for Sam R. & 2 Copys of sheets C1.1,C1.3,C1.4,L1.1 inserted into plans and routed beck to Public Works & Fire ///DLD
|
Routing - FIRE | 5/27/2005 | | 6/3/2005 | | FAIL |
|
|
|
Applicant came in and made changes to plans. Re-routed to Fire. Review comments faxed to architect.
|
Routing - PLAN CHECK | 5/25/2005 | | 5/25/2005 | | FAIL |
|
|
|
Failed by Fire. Plans in hold bin.
|
Routing - FIRE | 5/23/2005 | | 5/25/2005 | | FAIL |
|
|
|
address on application does not match the address on plan title page and the streets on the site planare incorrectly labled. Called architect, Katie Butler and discussed. She will come in and red-line the corrections on the plans. Plans returned to Plan Tech.
|
1st review completed | | | 5/25/2005 | | FAIL |
|
|
|
Plans failed in fire- plans put in hold box waiting for resubmittals
|
Routing - PLAN CHECK | 5/12/2005 | | 5/23/2005 | | PEND |
|
|
|
5/23/05 - Plans accidentally placed behind Darla's desk and not routed to Fire. Routing to Fire now and can be issued once Fire approves.
|
Routing - PLANNING | 5/10/2005 | | 5/12/2005 | | PASS |
|
|
|
Sarah S. DRH05-00080
Approved per DRH05-00080.
|
Routing - PLUMBING | 5/9/2005 | | 5/10/2005 | | PASS |
|
|
|
note on backlow valve pemit if installed for landscaping.
|
Routing - Erosion and Sediment | 5/6/2005 | | 5/9/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 4/29/2005 | | 5/6/2005 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 4/29/2005 | | 4/29/2005 | | PASS |
|
|
|
Approved, site is over 5 acres in size.
|
Plans ACCEPTED BY PLAN TECH | | | 4/29/2005 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 4/29/2005 | | |
|
|
|
|
Application received | | | 4/28/2005 | | |
|
|
|
|
Routing - PLAN CHECK | 6/3/2005 | | | | FAIL |
|
|
|
Failed by Fire. Plans in hold bin.
|