Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD05-01177
StatusFinaled
Name BORUP CONSTRUCTION CO
Site Address 3236 S ROOKERY LN
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a two bedroom, two and half bathroom 1953 sq. ft. three story town home on a zero lot line (238 sq. ft. first floor/800 sq. ft. second floor/915 sq. ft. third floor) with a attached 532 sq. ft. two car garage and a 148 sq. ft. deck off the second floor. Per approved plans, engineering and requirement list. DRH04-00103 Mod #1 per Sarah Schafer and CUP04-00032 per Susan Riggs with Planning and Zoning. An alternate approval letter by George Slane, dated 10/31/06 is attached to this permit and approved plans which allows common access across property lines from both units. This alternate requires a two hour wall enclosure, protected eave overhangs, 90 minute rated assemblies and inspection requirements with deed restrictions (x refer recorded Instrument Nos. 103196878, 104164281 and 106027814). (SAM and SRZ)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  5/24/2016 DONE
BLD-Final6/6/20076/7/20076/7/2007APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 6/6/2007 at 11:41:46 AM. Contact: ###-####.
DOC - Permit Finaled6/7/20076/7/20076/7/2007PPASS
DetailsJim Storey
BLD-Energy code compliance12/26/200612/26/200612/26/2006PPASS
DetailsJim Storey
framing and ec ok
BLD-Energy code compliance12/19/200612/20/200612/20/2006AFAIL
DetailsMike Jordan
Scheduled by a contractor via Hello! on 12/19/2006 at 3:28:06 PM. Contact: ###-####. . Complete airseal package @ main level north wall. Openin g protection issues on 2nd floor @ rated wall, 2x6 does not allow for continous fire wall and are structurally insufficient. Needs to complete other items from previous c/n. New c/n posted. not ok to cover.
BLD-Energy code compliance12/19/200612/19/200612/19/2006PNR
DetailsTony Young
Scheduled by a contractor via Hello! on 12/19/2006 at 7:45:43 AM. Contact: ###-####.
BLD-Framing/Rough-in12/7/200612/8/200612/8/2006APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/7/2006 at 2:20:14 PM. Contact: ###-####.need to finsh 2 hr wall ok to insulate.
BLD-Framing/Rough-in10/31/200611/1/200611/1/2006ANR
DetailsJim Storey
dean borup ###-#### conf
Case Summary (BLD)  10/31/2006  
Permit Ready to Issue  10/31/2006 DONE
CHANGE STATUS TO (ISS)  10/31/2006  
paid the 250.00 fee for lost plans
Telephone call  10/3/2006 DONE
I called Tod with Borup Construction and requested him to fill out his own Alternate design request. (R104.11 Alternate materials, design and methods of construction and equipment.) I also requested he hire his own independent code expert to review his design and formulate a written opinion on his projects specifics. The directive given is that he has his own paperwork for approval. (SRZ)
Plan Reviewer's activity  9/25/2006 FAIL
Plan Review completed. Plans do not meet 2003 IRC. New Plans required that meet current building code, or New agreement, or Condo. (SRZ)
Telephone call  9/25/2006 DONE
I called Applicant and requested new plans that meet current building code. Applicant lost plans and new submittals do not match Master file set that has a Legal agreement attached for Common Entry. The Options are to Meet building code, get new approval, or Condo.(SRZ)
BLD-Framing/Rough-in9/15/20069/18/20069/19/2006PNR
DetailsJim Storey
Scheduled by a contractor via Hello! on 9/15/2006 at 10:46:15 AM. Contact: ###-####.
Plan Reviewer's activity  9/19/2006 FAIL
Borup construction requested a new plan review due to losing the Approved set of plans. Plans do not match the Approved Master file set, what's being constructed at the site, or the alternate approval agreements for the common access across property lines. (SRZ)
Telephone call  9/19/2006 DONE
I spoke with Todd at Borup construction. I requested a new set for re-approval that matches what is actualy being built.(Per review with Field inspector) He stated what he submitted matches what's being built. He stated he would touch base with Jim Story and verify the plans matching what is being built. I told him I was also looking into the previous agreements with this project and would get back to him. (SRZ)
BLD-Framing/Rough-in9/15/20069/15/20069/15/2006PCANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 9/15/2006 at 10:41:53 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Sep 15 2006 10:55AM.
BLD-Wall cover7/5/20067/6/20067/6/2006APASS
DetailsJim Storey
Dale; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt 3rd floor gyp ok
BLD-Footing5/23/20065/23/20065/23/2006PPART
DetailsJim Storey
ben; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie set backs ok wip
Issue PAID IN FULL permit  5/8/2006 DONE
PLANS/APPL TAKEN TO FRONT DESK  5/5/2006 DONE
Inspection Record Card- Bld  5/5/2006 DONE
Telephone call  5/5/2006 DONE
Spoke with Trevor and told her that permit is ready & fees///5/5/06 @10:25am BAS
Permit Ready to Issue  5/5/2006  
Plan Reviewer's activity  4/13/2006 DONE
9:35 I called and left a message for Lee H. to call me. I need information on the cantilever with no backspan and location of all beams. Plans are on hold.
CHANGE STATUS TO (PND)  3/31/2006  
Per Steve Munroe change status to pending & he took plans

Builder brought in plan mod. New plan review required.
Telephone call  1/5/2006 DONE
left mess for derick o'neill that permit is ready
Telephone call  9/12/2005 DONE
left mess that permit is ready--will pickup soon
Plan assigned to (SAM)5/2/20056/7/20056/24/2005 PASS
6/24/2005 09:35:34 SAM - activity updated through activity BLDA022 from case BLD05-01177.
PLANS/APPL TAKEN TO FRONT DESK  6/24/2005 DONE
Inspection Record Card- Bld  6/24/2005 DONE
Permit Ready to Issue  6/24/2005 DONE
Telephone call  6/24/2005 DONE
called left message on derrick o'neil's voicemail permit is ready and fees
Routing - PLAN CHECK5/17/2005 6/24/2005 PASS
Plan Reviewer's activity  6/8/2005 DONE
08:45 I called and talked to Rob Powell. He said he will get me a new sheet A5.0. I will issue the permits once I get the new sheet.
Routing - Erosion and Sediment5/16/2005 5/17/2005 PASS
ESC approved under "masterplan" with attached conditions.
Routing - PUBLIC WORKS5/11/2005 5/12/2005 PASS
Routing - PLANNING5/2/2005 5/9/2005 PASS
Routed to Susan Riggs per CUP04-00032.
Ok for CUP, pending DR passed to Sara
Approved per DRH04-00103 Mod. #1
Application received  5/2/2005