BLD-Final | 10/4/2005 | 10/5/2005 | 10/5/2005 | A | PASS |
Mike Jordan
|
|
|
greg ###-#### re-insp
|
DOC - Permit Finaled | 10/5/2005 | 10/5/2005 | 10/5/2005 | P | PASS |
Mike Jordan
|
|
|
handrail and footing depth have been repaired.
|
BLD-Final | 10/4/2005 | 10/4/2005 | 10/4/2005 | P | NR |
Mike Jordan
|
|
|
craig; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Final | 9/30/2005 | 9/30/2005 | 9/30/2005 | P | FAIL |
Tom Arcoraci
|
|
|
###-#### craig frost depth at west side to be 24 in and handrail ht to be 34-38 in cn posted
|
BLD-Energy code compliance | 8/15/2005 | 8/16/2005 | 8/16/2005 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/15/2005 at 4:43:33 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/15/2005 | 8/16/2005 | 8/16/2005 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/15/2005 at 4:42:55 PM. Contact: ###-####.
|
BLD-Energy code compliance | 8/16/2005 | 8/16/2005 | 8/16/2005 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/15/2005 at 4:42:55 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/12/2005 | 8/15/2005 | 8/15/2005 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/12/2005 at 1:02:52 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/10/2005 | 8/10/2005 | 8/10/2005 | P | FAIL |
Tom Arcoraci
|
|
|
cn posted
|
BLD-Framing/Rough-in | 8/9/2005 | 8/10/2005 | 8/10/2005 | A | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/9/2005 at 12:30:23 PM.
|
Extend Permit 180 days | 8/10/2005 | 8/10/2005 | 8/10/2005 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Energy code compliance | 8/8/2005 | 8/8/2005 | 8/8/2005 | P | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/8/2005 at 10:51:06 AM.
|
BLD-Framing/Rough-in | 8/8/2005 | 8/8/2005 | 8/8/2005 | P | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/8/2005 at 10:51:06 AM. no app plans on site
|
BLD-Footing | 6/15/2005 | 6/15/2005 | 6/15/2005 | P | PART |
Tom Arcoraci
|
|
|
###-#### - paul wip ok
|
(F) Reprint permit | | | 6/14/2005 | | |
|
|
|
|
(F) Reprint permit | | | 6/14/2005 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/13/2005 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 6/6/2005 | 6/6/2005 | 6/8/2005 | | PASS |
|
|
|
6/8/2005 09:48:50 SRZ - activity updated through activity BLDA022 from case BLD05-01179.
|
Plan assigned to (SAM) | 5/2/2005 | 5/2/2005 | 6/8/2005 | | PASS |
|
|
|
6/8/2005 09:48:50 SRZ - activity updated through activity BLDA022 from case BLD05-01179.
|
Routing - PLAN CHECK | 5/12/2005 | | 6/8/2005 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 6/8/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/8/2005 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/8/2005 | | DONE |
|
|
|
One set red-lined.
|
Telephone call | | | 6/8/2005 | | DONE |
|
|
|
tlk to secretary ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 6/8/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/8/2005 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 6/6/2005 | | PASS |
|
|
|
Pending New Floor framing, Foundation plans. (SRZ)
|
Routing - PLANNING | 5/12/2005 | | 5/12/2005 | | PASS |
|
|
|
discussed with applicant 5/11 and 5/12 to resolve site plan. Approved as noted on site plan - setbacks shall be met per foundation plan and redlined site plan. eeg.
|
Routing - PUBLIC WORKS | 5/12/2005 | | 5/12/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 5/2/2005 | | 5/3/2005 | | FAIL |
|
|
|
5/3/05 fail for side street setback - 15' needs to be 20'
|
Application received | | | 5/2/2005 | | |
|
|
|
|