BLD-Final | 5/10/2006 | 5/12/2006 | 5/12/2006 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Internet Inspection Request from: Titus Gilliam
|
DOC - Permit Finaled | 5/12/2006 | 5/12/2006 | 5/12/2006 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 5/9/2006 | 5/10/2006 | 5/10/2006 | P | FAIL |
Dave Hannah
|
|
|
please call titus for garage access ###-#### Internet Inspection Request from: Titus Gilliam needs hand rail on top flight of stairs
|
PubWorks Occupancy Approval | 5/10/2006 | 5/10/2006 | 5/10/2006 | | DONE |
|
|
|
Final Grading Inspection of retaining wall drainage swale done by Public Works. Public Works / Final Occupancy permit issues have been resolved based upon Contractor activities.
|
BLD-Grading Inspection | 5/3/2006 | 5/3/2006 | 5/3/2006 | | BOND |
|
|
|
The rough grading and drainage have been completed at the above mentioned address. However, the placement of the retaining walls was not done according to plan which will require that a drainage swale be constructed between the two walls. For this incomplete work the engineer has recommended a $500.00 bond. Upon receipt of this bond the grading and drainage is conditionally approved.
|
BLD-Final | 5/2/2006 | 5/2/2006 | 5/2/2006 | P | CANC |
Dave Hannah
|
|
|
please call titus for access ###-####; Phone #: ###-#### Internet Inspection Request from: Titus Gilliam
|
BLD-Final | 4/28/2006 | 4/28/2006 | 4/28/2006 | P | FAIL |
Jim Sly
|
|
|
Please call Titus at ###-#### in advance to get access to home or meet at site.; Phone #: ###-#### Internet Inspection Request from: Titus Gilliam Need final sign off from Terry Records
|
BLD-Final | 4/27/2006 | 4/28/2006 | 4/28/2006 | A | CANC |
Tony Young
|
|
|
titus; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Inspection cancelled from web by: Titus Gilliam
|
BLD-Energy code compliance | 9/9/2005 | 9/15/2005 | 9/15/2005 | A | PASS |
Dave Hannah
|
|
|
call dave w/ problems ###-####; Phone #: ###-#### Internet Inspection Request from: Titus Gilliam ok to cover framing
|
BLD-Framing/Rough-in | 9/12/2005 | 9/12/2005 | 9/12/2005 | P | PASS |
Dave Hannah
|
|
|
call Joel w/ problems ###-#### Internet Inspection Request from: Titus Gilliam
|
BLD-Framing/Rough-in | 9/9/2005 | 9/12/2005 | 9/12/2005 | A | NR |
Dave Hannah
|
|
|
call Joel w/ problems ###-#### Internet Inspection Request from: Titus Gilliam needs seal package installed
|
BLD-Energy code compliance | 9/8/2005 | 9/14/2005 | 9/9/2005 | A | CANC |
Dave Hannah
|
|
|
also please call titus at ###-#### if you have problems; Phone #: ###-#### Internet Inspection Request from: Titus Gilliam Inspection cancelled from web by: Titus Gilliam
|
BLD-Framing/Rough-in | 9/8/2005 | 9/9/2005 | 9/9/2005 | P | CANC |
Dave Hannah
|
|
|
also please call titus at ###-#### if you have any problems; Phone #: ###-#### Internet Inspection Request from: Titus Gilliam Inspection cancelled from web by: Titus Gilliam
|
BLD-Foundation | 7/13/2005 | 7/13/2005 | 7/13/2005 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 7/13/2005 at 6:53:47 AM. Contact: ###-####.
|
BLD-Footing | 7/11/2005 | 7/12/2005 | 7/12/2005 | P | PASS |
Mike Jordan
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
PubWorks Subgrade Approval | 5/10/2005 | 5/10/2005 | 6/30/2005 | | PASS |
|
|
|
Footing subgrade approved by the geotechnical engineer. 6/30/05
A letter from the applicant's geotechnical engineer indicating that the footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Terry Records at ###-####.
|
Override - Activity Holds | | | 6/10/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/10/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/20/2005 | | 6/9/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/9/2005 | | DONE |
|
|
|
|
Override - Activity Holds | | | 6/9/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/9/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/9/2005 | | DONE |
|
|
|
|
Override - Activity Holds | | | 6/9/2005 | | |
|
|
|
|
Permit Ready to Issue | | | 6/9/2005 | | |
|
|
|
|
Telephone call | | | 6/9/2005 | | DONE |
|
|
|
lft vm with avision lc ###-#### that permit and fees are ready to be picked up
|
Plan assigned to (SAM) | 6/8/2005 | | 6/9/2005 | | PASS |
|
|
|
6/9/2005 08:22:55 SAM - activity updated through activity BLDA022 from case BLD05-01199.
|
Plan Reviewer's activity | | | 6/8/2005 | | DONE |
|
|
|
12:05 & 14:00 I called and left a message for Titus to send me the engineering calculations so I can finish the plan review. Plans are on hold.
|
Case Summary (BLD) | | | 6/8/2005 | | |
|
|
|
|
Routing - Erosion and Sediment | 5/20/2005 | | 5/20/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - FIRE | 5/20/2005 | | 5/20/2005 | | PASS |
|
|
|
No fire sprinklers required (Nativa Terra Block 4)
|
Routing - PLANNING | 5/10/2005 | | 5/20/2005 | | PASS |
|
|
|
Per CFH05-14 / appeal ended May 16, 2005.
|
Routing - PUBLIC WORKS GRADING | 5/5/2005 | | 5/10/2005 | | PASS |
|
|
|
Approved as category 1
|
Routing - PUBLIC WORKS | 5/10/2005 | | 5/10/2005 | | PASS |
|
|
|
|
Application received | | | 5/5/2005 | | |
|
|
|
|