Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD05-01216
StatusFinaled
Name K2 CONSTRUCTION
Site Address 605 S AMERICANA BLVD
Project NameCaledonia Station
Customer Number 
ePlanReviewNo
Description
Caledonia Station (Addition and Remodel) - to add a 5545 sq. ft. two story type IIIB addition to the existing 2,275 sq. ft one story building. The building will have three separate tenant spaces with the existing space plus addition at 2905 sq. ft. the other 1st floor tenant space with vanilla finish at 2240 sq. ft. and the second floor space with vanilla finish at 2675 sq. ft. Other work includes remodeling of the existing building, all site improvements, paving and landscaping per approved plans. This building is proposed to have a fire alarm system. Areas of the two story addition are 2870 sq. ft. first floor and 2675 second floor. The building will not be fire sprinklered. Exterior walls are masonry and the entire building meets requirements for Type IIIB construction. Separate permits and possible plans required for occupancy of each tenant space. MIS PERMIT FOR CALEDONIA FINE FABRICS - MIS05-00107 for C.O.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  10/3/2006 DONE
Letter of Compliance issued 10-3-06
BLD-Final9/18/20069/19/20069/19/2006APASS
DetailsDave Hannah
jason; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
PubWorks Occupancy Approval9/19/20069/19/20069/19/2006 DONE
FIRE-Final Inspection9/18/20069/18/20069/18/2006PPASS
DetailsForrest France
Fire life safety passed inspection.
Override - Condition Holds1/1/19001/1/19009/18/2006  
Override - Condition Holds1/1/19001/1/19009/18/2006  
BLD-Other8/2/20068/2/20068/2/2006PPASS
DetailsMike Jordan
shawn - Note: ceiling grid; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Override - Condition Holds1/1/19001/1/19008/2/2006  
Override - Condition Holds1/1/19001/1/19008/2/2006  
BLD-Framing/Rough-in7/5/20067/5/20067/5/2006PPASS
DetailsDave Hannah
shane ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie front oning
Override - Condition Holds1/1/19001/1/19007/5/2006  
needed fr insp
Case Summary (BLD)  6/26/2006  
BLD-Energy code compliance6/9/20066/12/20066/12/2006APART
DetailsDave Hannah
shane ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie second floor back half ok to cover
Override - Condition Holds1/1/19001/1/19006/9/2006  
need insulation insp
BLD-Energy code compliance6/7/20066/8/20066/8/2006APART
DetailsDave Hannah
shane; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to cover ground floor walls
Override - Condition Holds1/1/19001/1/19006/7/2006  
BLD-Framing/Rough-in6/5/20066/5/20066/5/2006PPART
DetailsDave Hannah
shane; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley framing ground floor back area ,restroom and elev on 1st and second floors ok
Override - Condition Holds1/1/19001/1/19006/5/2006  
rough in only
FIRE-Conference5/5/20065/8/20065/8/2006PDONE
DetailsForrest France
Confrence to discuss requirements related to duct smoke detection for HVAC unit shutdown.
BLD-Framing/Rough-in4/17/20064/18/20064/18/2006APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 4/17/2006 at 1:56:28 PM. Contact: ###-####. ok to cover roof need to verify east to west blk added between trusses north side missed butt joint on sheathing.
BLD-Framing/Rough-in4/4/20064/5/20064/5/2006APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 4/4/2006 at 4:26:23 PM. Contact: ###-####. secton floor nailing and straping ok ok to cover
BLD-Framing/Rough-in4/4/20064/4/20064/4/2006PFAIL
DetailsDave Hannah
Scheduled by a contractor via Hello! on 4/4/2006 at 8:55:39 AM. Contact: ###-####. second floor nailing not per plan
Inspection Record Card- Bld  4/3/2006 DONE
Print Occupancy Form  4/3/2006 DONE
BLD-Footing1/18/20061/18/20061/18/2006PPART
DetailsDave Hannah
shane; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie crew working on rebar talked with forman they need to clean out mud they will have spec inspection sign offf and test concrete
Issue PAID IN FULL permit  10/21/2005 DONE
Telephone call  10/5/2005 DONE
talked to a jerrod wallgreen at ###-#### to verify plans are still here and will expire nov 6th 2005/mls
Inspection Record Card- Bld  7/21/2005 DONE
Permit Ready to Issue  7/21/2005 DONE
Permit Ready to Issue  7/21/2005 DONE
Telephone call  7/21/2005 DONE
called jerod, permit is ready and fees and need ACHD
Permit Ready to Issue  7/21/2005 DONE
Routing Off Site - STRUCTURAL7/14/2005 7/20/2005 PASS
Called PDQ for pick up
Routing - PLAN CHECK7/19/2005 7/20/2005 PASS
Case Summary (BLD)  7/20/2005  
PLANS/APPL TAKEN TO FRONT DESK  7/20/2005 DONE
Plan assigned to (MLO)5/12/2005 7/20/2005 PASS
7/20/2005 11:33:21 MLO - activity updated through activity BLDA022 from case BLD05-01216.
Plan resubmittals received  7/18/2005  
Received (2) copies of sheet A-3.0 and A-6.0. Routed to Mike O.
Routing - PLAN CHECK7/14/2005 7/14/2005 FAIL
architect contacted by phone MLO.
Plan resubmittals requested  7/14/2005 DONE
correction for fire rated windows and doors.
Plan resubmittals received  7/14/2005  
Plans to plan reviewer after end of work hours on 7/13/2005, plans stamped received on 7/12/2005. MLO. Received (3) copies of sheet S1.0, S2.0, S3.0, S4.0, S4.1, S5.0 and S5.1.; received (2) copies of sheet A3.0, A4.3, A6.0 and E-2L. Also received (2) structural calcs, (1) occupancy request application and (1) start-up form for special inspections. Routed to Mike O.
Routing - FIRE6/8/2005 6/10/2005 PASS
approved with conditions. review faxed to architect.
1st review completed  6/10/2005 FAIL
failed structural and plan check.
Routing - PLAN CHECK6/10/2005 6/10/2005 PEND
Routing - PLAN CHECK6/2/2005 6/8/2005 FAIL
corrections sent to architect
Plan resubmittals requested  6/8/2005 DONE
IBC corrections
Routing Off Site - STRUCTURAL5/16/2005 6/8/2005 FAIL
Routed off site to outside structural engineer for review. corrections sent to architect
Routing - PLANNING6/1/2005 6/2/2005 PASS
Approved per DRH04-54.
Routing - PLUMBING6/2/2005 6/2/2005 PASS
approved per plan and 2003 upc
Routing - Erosion and Sediment5/31/2005 6/1/2005 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS5/17/2005 5/31/2005 PASS
Routing - PLANNING Land Div5/17/2005 5/17/2005 PASS
Approved. Lots combined into one parcel with one Tax Parcel #.
Plan routing begun/NEW & ADDTN  5/17/2005  
Plan resubmittals received  5/16/2005 DONE
Received all new stamped and signed plan sheets C-1.0 and C-2.0 from Lance Warnick, Civil Engr., Treasure Valley Engineers. Inserted into plans and began routing.
Plans ACCEPTED BY PLAN TECH  5/16/2005 DONE
Resubmitted C-1.0 and C2.0 sheets received. Inserted into plans and routing process began.
Plans ACCEPTED BY PLAN TECH  5/12/2005 HOLD
Plans on hold waiting for 7 new copies of sheets C1.0 and C2.0. Once received plans can begin routing.
Application received  5/6/2005  
Recd Pcfee & Taken To Pln CK  5/6/2005  
Fee Review-notes5/6/20055/6/2005