Letter of compliance | | | 10/3/2006 | | DONE |
|
|
|
Letter of Compliance issued 10-3-06
|
BLD-Final | 9/18/2006 | 9/19/2006 | 9/19/2006 | A | PASS |
Dave Hannah
|
|
|
jason; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
PubWorks Occupancy Approval | 9/19/2006 | 9/19/2006 | 9/19/2006 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/18/2006 | 9/18/2006 | 9/18/2006 | P | PASS |
Forrest France
|
|
|
Fire life safety passed inspection.
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 9/18/2006 | | |
|
|
|
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 9/18/2006 | | |
|
|
|
|
BLD-Other | 8/2/2006 | 8/2/2006 | 8/2/2006 | P | PASS |
Mike Jordan
|
|
|
shawn - Note: ceiling grid; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 8/2/2006 | | |
|
|
|
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 8/2/2006 | | |
|
|
|
|
BLD-Framing/Rough-in | 7/5/2006 | 7/5/2006 | 7/5/2006 | P | PASS |
Dave Hannah
|
|
|
shane ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie front oning
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 7/5/2006 | | |
|
|
|
needed fr insp
|
Case Summary (BLD) | | | 6/26/2006 | | |
|
|
|
|
BLD-Energy code compliance | 6/9/2006 | 6/12/2006 | 6/12/2006 | A | PART |
Dave Hannah
|
|
|
shane ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie second floor back half ok to cover
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 6/9/2006 | | |
|
|
|
need insulation insp
|
BLD-Energy code compliance | 6/7/2006 | 6/8/2006 | 6/8/2006 | A | PART |
Dave Hannah
|
|
|
shane; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to cover ground floor walls
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 6/7/2006 | | |
|
|
|
|
BLD-Framing/Rough-in | 6/5/2006 | 6/5/2006 | 6/5/2006 | P | PART |
Dave Hannah
|
|
|
shane; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley framing ground floor back area ,restroom and elev on 1st and second floors ok
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 6/5/2006 | | |
|
|
|
rough in only
|
FIRE-Conference | 5/5/2006 | 5/8/2006 | 5/8/2006 | P | DONE |
Forrest France
|
|
|
Confrence to discuss requirements related to duct smoke detection for HVAC unit shutdown.
|
BLD-Framing/Rough-in | 4/17/2006 | 4/18/2006 | 4/18/2006 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/17/2006 at 1:56:28 PM. Contact: ###-####. ok to cover roof need to verify east to west blk added between trusses north side missed butt joint on sheathing.
|
BLD-Framing/Rough-in | 4/4/2006 | 4/5/2006 | 4/5/2006 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/4/2006 at 4:26:23 PM. Contact: ###-####. secton floor nailing and straping ok ok to cover
|
BLD-Framing/Rough-in | 4/4/2006 | 4/4/2006 | 4/4/2006 | P | FAIL |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/4/2006 at 8:55:39 AM. Contact: ###-####. second floor nailing not per plan
|
Inspection Record Card- Bld | | | 4/3/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/3/2006 | | DONE |
|
|
|
|
BLD-Footing | 1/18/2006 | 1/18/2006 | 1/18/2006 | P | PART |
Dave Hannah
|
|
|
shane; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie crew working on rebar talked with forman they need to clean out mud they will have spec inspection sign offf and test concrete
|
Issue PAID IN FULL permit | | | 10/21/2005 | | DONE |
|
|
|
|
Telephone call | | | 10/5/2005 | | DONE |
|
|
|
talked to a jerrod wallgreen at ###-#### to verify plans are still here and will expire nov 6th 2005/mls
|
Inspection Record Card- Bld | | | 7/21/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/21/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/21/2005 | | DONE |
|
|
|
|
Telephone call | | | 7/21/2005 | | DONE |
|
|
|
called jerod, permit is ready and fees and need ACHD
|
Permit Ready to Issue | | | 7/21/2005 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 7/14/2005 | | 7/20/2005 | | PASS |
|
|
|
Called PDQ for pick up
|
Routing - PLAN CHECK | 7/19/2005 | | 7/20/2005 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 7/20/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/20/2005 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 5/12/2005 | | 7/20/2005 | | PASS |
|
|
|
7/20/2005 11:33:21 MLO - activity updated through activity BLDA022 from case BLD05-01216.
|
Plan resubmittals received | | | 7/18/2005 | | |
|
|
|
Received (2) copies of sheet A-3.0 and A-6.0. Routed to Mike O.
|
Routing - PLAN CHECK | 7/14/2005 | | 7/14/2005 | | FAIL |
|
|
|
architect contacted by phone MLO.
|
Plan resubmittals requested | | | 7/14/2005 | | DONE |
|
|
|
correction for fire rated windows and doors.
|
Plan resubmittals received | | | 7/14/2005 | | |
|
|
|
Plans to plan reviewer after end of work hours on 7/13/2005, plans stamped received on 7/12/2005. MLO. Received (3) copies of sheet S1.0, S2.0, S3.0, S4.0, S4.1, S5.0 and S5.1.; received (2) copies of sheet A3.0, A4.3, A6.0 and E-2L. Also received (2) structural calcs, (1) occupancy request application and (1) start-up form for special inspections. Routed to Mike O.
|
Routing - FIRE | 6/8/2005 | | 6/10/2005 | | PASS |
|
|
|
approved with conditions. review faxed to architect.
|
1st review completed | | | 6/10/2005 | | FAIL |
|
|
|
failed structural and plan check.
|
Routing - PLAN CHECK | 6/10/2005 | | 6/10/2005 | | PEND |
|
|
|
|
Routing - PLAN CHECK | 6/2/2005 | | 6/8/2005 | | FAIL |
|
|
|
corrections sent to architect
|
Plan resubmittals requested | | | 6/8/2005 | | DONE |
|
|
|
IBC corrections
|
Routing Off Site - STRUCTURAL | 5/16/2005 | | 6/8/2005 | | FAIL |
|
|
|
Routed off site to outside structural engineer for review. corrections sent to architect
|
Routing - PLANNING | 6/1/2005 | | 6/2/2005 | | PASS |
|
|
|
Approved per DRH04-54.
|
Routing - PLUMBING | 6/2/2005 | | 6/2/2005 | | PASS |
|
|
|
approved per plan and 2003 upc
|
Routing - Erosion and Sediment | 5/31/2005 | | 6/1/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 5/17/2005 | | 5/31/2005 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 5/17/2005 | | 5/17/2005 | | PASS |
|
|
|
Approved. Lots combined into one parcel with one Tax Parcel #.
|
Plan routing begun/NEW & ADDTN | | | 5/17/2005 | | |
|
|
|
|
Plan resubmittals received | | | 5/16/2005 | | DONE |
|
|
|
Received all new stamped and signed plan sheets C-1.0 and C-2.0 from Lance Warnick, Civil Engr., Treasure Valley Engineers. Inserted into plans and began routing.
|
Plans ACCEPTED BY PLAN TECH | | | 5/16/2005 | | DONE |
|
|
|
Resubmitted C-1.0 and C2.0 sheets received. Inserted into plans and routing process began.
|
Plans ACCEPTED BY PLAN TECH | | | 5/12/2005 | | HOLD |
|
|
|
Plans on hold waiting for 7 new copies of sheets C1.0 and C2.0. Once received plans can begin routing.
|
Application received | | | 5/6/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/6/2005 | | |
|
|
|
|
Fee Review-notes | 5/6/2005 | 5/6/2005 | | | |
|
|
|
|