BLD-Final | 1/27/2006 | 1/30/2006 | 1/30/2006 | A | PASS |
Mike Jordan
|
|
|
Ben -- call 1st for access; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
DOC - Permit Finaled | 1/30/2006 | 1/30/2006 | 1/30/2006 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 11/23/2005 | 11/23/2005 | 11/23/2005 | P | PASS |
Mike Jordan
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. All items on c/n have been repaired. ok to cover.
|
BLD-Framing/Rough-in | 11/22/2005 | 11/22/2005 | 11/22/2005 | P | FAIL |
Mike Jordan
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. All hangars not nailed off (downstairs)
|
BLD-Energy code compliance | 11/17/2005 | 11/18/2005 | 11/18/2005 | A | FAIL |
Mike Jordan
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. Items on previous c/n not repaired. Not ok to cover.
|
BLD-Framing/Rough-in | 11/14/2005 | 11/15/2005 | 11/15/2005 | P | FAIL |
Mike Jordan
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. Needs to complete lateral bracing on attic trusses. see c/n.
|
BLD-Foundation | 9/19/2005 | 9/20/2005 | 9/20/2005 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/19/2005 at 10:23:05 AM. Contact: ###-####.
|
BLD-Foundation | 9/19/2005 | 9/20/2005 | 9/20/2005 | A | NR |
Tom Arcoraci
|
|
|
|
BLD-Footing | 9/19/2005 | 9/19/2005 | 9/19/2005 | P | CANC |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/19/2005 at 10:22:46 AM. Contact: ###-####.
|
CHANGE STATUS TO (ISS) | | | 9/16/2005 | | DONE |
|
|
|
|
(F) Reprint permit | | | 9/16/2005 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/13/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/13/2005 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 9/13/2005 | | |
|
|
|
|
Permit Ready to Issue | | | 9/13/2005 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 9/13/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/13/2005 | | DONE |
|
|
|
|
Telephone call | | | 9/13/2005 | | DONE |
|
|
|
called ###-#### and told Rebecca permit is ready and fees
|
Routing - PLAN CHECK | 8/29/2005 | | 9/13/2005 | | PASS |
|
|
|
|
CHANGE STATUS TO (PND) | | | 9/12/2005 | | PEND |
|
|
|
Builder resubmitted new plans to meet minimum square footage for architectural design community.
|
Routing - PUBLIC WORKS | 8/26/2005 | | 8/29/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 8/26/2005 | | 8/26/2005 | | PASS |
|
|
|
Revised plans meet setback requirements. Plans were not received by Planning Staff until 8/26/05. EG posessed plans prior to this date. CER
|
Plan resubmittals received | | | 8/24/2005 | | |
|
|
|
Plan Resubmittals received. Original plan approved for this lot did not meet 1st floor minimum square footage for the architectural design committee. Construction stopped. Modified plan submitted.
|
BLD-Foundation | 7/28/2005 | 7/29/2005 | 7/29/2005 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/28/2005 at 7:24:40 AM. Contact: ###-####.
|
BLD-Footing | 7/28/2005 | 7/28/2005 | 7/28/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 7/28/2005 at 7:24:22 AM. Contact: ###-####. wip ok
|
Issue PAID IN FULL permit | | | 7/22/2005 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 7/18/2005 | 7/18/2005 | 7/19/2005 | | PASS |
|
|
|
7/19/2005 10:41:57 SRZ - activity updated through activity BLDA022 from case BLD05-01335.
|
Case Summary (BLD) | | | 7/19/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/19/2005 | | DONE |
|
|
|
ONE SET RED-LINED
|
Inspection Record Card- Bld | | | 7/19/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/19/2005 | | DONE |
|
|
|
|
Telephone call | | | 7/19/2005 | | DONE |
|
|
|
tlk to secretary ###-#### that permit and fees are ready to be picked up
|
Routing - PLAN CHECK | 6/28/2005 | | 7/19/2005 | | PASS |
|
|
|
|
Plan assigned to (SAM) | 5/19/2005 | 5/19/2005 | 7/18/2005 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 6/28/2005 | | 6/28/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 6/27/2005 | | 6/27/2005 | | PASS |
|
|
|
received revised site plan and discussed with Mike Toft - approved as noted. eeg.
|
Application received | | | 5/19/2005 | | |
|
|
|
|
Routing - PLANNING | 5/20/2005 | | | | FAIL |
|
|
|
driveway width greater than 33' before adding the side drive to the detached garage. called applicant 2nd time 5/26/05
|