Third Notice BLD | 6/14/2006 | 6/14/2006 | 9/14/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Telephone call | | | 9/14/2006 | | DONE |
|
|
|
tlk to ashley heating to verify if a permit was issued or not 12:15 pm - he wil call me back concerning this mech permit
|
Telephone call | | | 9/14/2006 | | |
|
|
|
tlk to steffin ashley heating - did not issue permit for mech 12:20 9/14/06
|
Second Notice BLD | 4/14/2006 | 4/14/2006 | 6/14/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 4/4/2006 | 4/14/2006 | | DONE |
|
|
|
|
Permanent occupancy | | | 4/4/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 10963 issued 4-4-06 to Arrowrock Classical School.
|
BLD-Final | 11/21/2005 | 11/22/2005 | 11/22/2005 | P | PASS |
Dave Hannah
|
|
|
robie ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok for prem occ
|
FIRE-Final Inspection | 11/21/2005 | 11/22/2005 | 11/22/2005 | A | PASS |
Forrest France
|
|
|
The related fire alarm permit has been finaled. Fire life safety is acceptable for permanent occupancy.
|
Permanent Occupancy | | 11/22/2005 | 11/22/2005 | | DONE |
|
|
|
|
Temporary occupancy | | | 10/5/2005 | | DONE |
|
|
|
Temp. Occ. Cert. # 5284 issued 10-5-05 to the Arrowrock Classical School.
|
FIRE-Conference | 9/15/2005 | 9/15/2005 | 9/15/2005 | P | DONE |
Forrest France
|
|
|
On site discussion with contractor regarding the proper location for duct smoke detectors.
|
BLD-Final | 9/2/2005 | 9/6/2005 | 9/8/2005 | P | DONE |
Dave Hannah
|
|
|
robbie; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Final | 9/1/2005 | 9/2/2005 | 9/8/2005 | P | PART |
Dave Hannah
|
|
|
robbie; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok for temp occ ok for perm occ after fire alm gos perm
|
FIRE-Final Inspection | 9/7/2005 | 9/7/2005 | 9/7/2005 | P | PART |
Forrest France
|
|
|
A temporary occupancy was granted with Sam Rogers permission pending final of the fire alarm permit, all other life safety issues are acceptable.
|
PRINT Activities | | | 9/6/2005 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 9/6/2005 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/1/2005 | 9/2/2005 | 9/2/2005 | A | PART |
Forrest France
|
|
|
Fire alarm permit must be finaled prior to BLD fire/life safety final. All other life safety issues have been inspected and are satisfactory.
|
FIRE-Alarm Testing | 8/31/2005 | 9/1/2005 | 9/1/2005 | P | FAIL |
Forrest France
|
|
|
This inspection was for the fire alarm which was not completed yet.
|
FIRE-Final Inspection | 8/31/2005 | 9/1/2005 | 9/1/2005 | P | FAIL |
Forrest France
|
|
|
Provide signage for fire lane, provide directional arrows on exit signs in hall, test and final fire alarm prior to life safety sign off.
|
FIRE-Final Inspection | 8/31/2005 | 8/31/2005 | 8/31/2005 | P | FAIL |
Forrest France
|
|
|
Fire alarm must be completed and inspected prior to fire life safety sign off.
|
BLD-Energy code compliance | 7/6/2005 | 7/7/2005 | 7/8/2005 | A | PASS |
Dave Hannah
|
|
|
glen; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa plumbing has been inspected ok to cover
|
BLD-Framing/Rough-in | 7/1/2005 | 7/5/2005 | 7/5/2005 | P | PASS |
Tom Arcoraci
|
|
|
###-#### ok to insulate pending plumbing ok ( no sticker)
|
BLD-Concrete | 6/14/2005 | 6/15/2005 | 6/15/2005 | A | PART |
Dave Hannah
|
|
|
GLEN; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Issue PAID IN FULL permit | | | 6/9/2005 | | |
|
|
|
|
Routing - PLAN CHECK | 6/7/2005 | | 6/8/2005 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/8/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/8/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/8/2005 | | DONE |
|
|
|
|
Telephone call | | | 6/8/2005 | | DONE |
|
|
|
lft mes for traves burrows ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 6/8/2005 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 5/25/2005 | | 6/8/2005 | | PASS |
|
|
|
6/8/2005 12:45:21 CJW - activity updated through activity BLDA022 from case BLD05-01345.
|
Routing - FIRE | 6/1/2005 | | 6/7/2005 | | PASS |
|
|
|
review faxed to architect.
|
1st review completed | | | 6/7/2005 | | FAIL |
|
|
|
failed planning and plan check.
|
Plan resubmittals received | | | 6/3/2005 | | |
|
|
|
Received (2) copies of sheet 2, 3 and SN. Routed to Carl W.
|
Routing - PLAN CHECK | 5/27/2005 | | 6/1/2005 | | FAIL |
|
|
|
The IBC plan review was started on May 31, 2005 and was finished the next day. Revised drawings were required. See the plan review report.
|
Routing - PLUMBING | 5/26/2005 | | 5/27/2005 | | PASS |
|
|
|
per plans and 2003 upc.
|
Routing - PLANNING | 5/26/2005 | | 5/26/2005 | | PASS |
|
|
|
PASS for conditional use: Angela Wood CUP05-00022
Appeal period has not lapsed for Design Review. Appeal period ends May 27, 2005 at 5:00 p.m. Should be able to sign off on plans by May 31. Routed to Plumbing.
No appeals rcvd. 6/ 8/ 2005
|
Routing - PUBLIC WORKS | 5/26/2005 | | 5/26/2005 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/26/2005 | | |
|
|
|
Travis returned plans with CDH approval. Routed back to Marlene.
|
Routing Off Site - C.D.H | 5/26/2005 | | 5/26/2005 | | PASS |
|
|
|
Travis Burrows (contractor) hand carried plans to CDH for review an approval on this date. Beth Norberg, CDH approved them.
|
Telephone call | | | 5/25/2005 | | DONE |
|
|
|
5:30 p.m. - Talked to Wes Steele (architect) via phone and left a message for Travis (contractor) that the plans needed to be reviewed by Central District Health. Wes said he or Travis would be in to hand carry the plans to CDH for review and return them to the PDS Dept. to continue processing.
|
Plans ACCEPTED BY PLAN TECH | | | 5/23/2005 | | |
|
|
|
|
Application received | | | 5/20/2005 | | |
|
|
|
|
Override - Parcel Holds | | | 5/20/2005 | | |
|
|
|
|
Override - Parcel Holds | | | 5/20/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/20/2005 | | DONE |
|
|
|
|
Fee Review-notes | 5/20/2005 | 5/20/2005 | | | |
|
|
|
|