Third Notice BLD | 12/6/2005 | 12/6/2005 | 1/11/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 10/10/2005 | 10/10/2005 | 12/6/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 9/23/2005 | 10/10/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 9/23/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10743 issued 9-23-05 to Bilyeu Properties.
|
BLD-Final | 9/21/2005 | 9/22/2005 | 9/22/2005 | P | PASS |
Jim Sly
|
|
|
terry; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa OK for Perm Occ. ():
|
FIRE-Final Inspection | 9/21/2005 | 9/22/2005 | 9/22/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled. Structural inspector please verify that approved hardware is installed on the east facing exit door per conversation.
|
Permanent Occupancy | | 9/22/2005 | 9/22/2005 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 8/4/2005 | 8/5/2005 | 8/5/2005 | A | PASS |
Jim Sly
|
|
|
terry; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Framing/Rough-in | 7/22/2005 | 7/25/2005 | 7/22/2005 | A | CANC |
Jim Sly
|
|
|
terry; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa Inspection cancelled from web by: Marsha Smylie
|
Issue PAID IN FULL permit | | | 7/5/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/21/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/21/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/21/2005 | | DONE |
|
|
|
|
Telephone call | | | 6/21/2005 | | DONE |
|
|
|
left mess for andrew davis at ###-#### is ready
|
Routing - PLAN CHECK | 6/10/2005 | | 6/20/2005 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
Routing - PUBLIC WORKS | 6/20/2005 | | 6/20/2005 | | PASS |
|
|
|
Sent back for sewer fee re-evaluation.
|
Routing - PLAN CHECK | 6/20/2005 | | 6/20/2005 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/20/2005 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 5/26/2005 | | 6/20/2005 | | PASS |
|
|
|
6/20/2005 13:35:53 CJW - activity updated through activity BLDA022 from case BLD05-01348.
|
Plan resubmittals received | | | 6/15/2005 | | |
|
|
|
Received (2) copies of sheet A-1.1, A-2.1 and A-3.1. Also received (2) copies of System Load Report and (1) copy structural calcs. Routed to Carl W.
|
Routing - FIRE | 6/6/2005 | | 6/10/2005 | | PASS |
|
|
|
|
1st review completed | | | 6/10/2005 | | FAIL |
|
|
|
failed plan check.
|
Routing - PLAN CHECK | 6/2/2005 | | 6/6/2005 | | FAIL |
|
|
|
The IBC plan review was started on June 3, 2005 and was finished on June 6, 2005. Revised drawings were required. See the plan review report.
|
Routing - Erosion and Sediment | 5/31/2005 | | 5/31/2005 | | PASS |
|
|
|
ESC plan waiver request approved with attached conditions.
|
Routing - PUBLIC WORKS | 5/26/2005 | | 5/31/2005 | | PASS |
|
|
|
|
Application received | | | 5/26/2005 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/23/2005 | | |
|
|
|
|
Application received | | | 5/20/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/20/2005 | | |
|
|
|
|
Fee Review-notes | 5/20/2005 | 5/20/2005 | | | |
|
|
|
|