BLD-Final | 11/10/2005 | 11/10/2005 | 11/10/2005 | P | PASS |
Jim Sly
|
|
|
MIKE; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa c/c issued
|
DOC - Permit Finaled | 11/10/2005 | 11/10/2005 | 11/10/2005 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 9/30/2005 | 9/30/2005 | 9/30/2005 | P | PASS |
Jim Sly
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 9/28/2005 | 9/28/2005 | 9/28/2005 | P | PART |
Mike Jordan
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. See posted c/n.
|
BLD-Foundation | 8/29/2005 | 8/29/2005 | 8/29/2005 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/29/2005 at 10:09:11 AM. Contact: ###-####.
|
BLD-Foundation | 8/26/2005 | 8/29/2005 | 8/29/2005 | A | FAIL |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/26/2005 at 6:59:28 AM. Contact: ###-####. no one on site. Forms not constructed.
|
BLD-Footing | 8/26/2005 | 8/26/2005 | 8/26/2005 | A | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/26/2005 at 6:59:16 AM. Contact: ###-####.
|
Telephone call | | | 8/23/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Issue PAID IN FULL permit | | | 8/23/2005 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 6/2/2005 | 6/2/2005 | 8/22/2005 | | PASS |
|
|
|
8/22/2005 11:36:37 PEP - activity updated through activity BLDA022 from case BLD05-01465.
|
Routing - PLAN CHECK | 8/3/2005 | | 8/22/2005 | | PASS |
|
|
|
|
Plan assigned to (PEP) | 8/22/2005 | | 8/22/2005 | | PASS |
|
|
|
8/22/2005 11:36:37 PEP - activity updated through activity BLDA022 from case BLD05-01465.
|
Case Summary (BLD) | | | 8/22/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/22/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/22/2005 | | |
|
|
|
|
Routing - PUBLIC WORKS | 8/3/2005 | | 8/3/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 7/28/2005 | | 8/2/2005 | | PASS |
|
|
|
full revised plan set submitted - site plan approved as noted. eeg.
|
Application received | | | 6/2/2005 | | |
|
|
|
|
Routing - PLANNING | 6/2/2005 | | | | FAIL |
|
|
|
common drive setback requirements not met. Revised site plan needed
|