BLD-Final | 3/9/2006 | 3/10/2006 | 3/10/2006 | A | PASS |
Tony Young
|
|
|
Bob,###-####
|
DOC - Permit Finaled | 3/10/2006 | 3/10/2006 | 3/10/2006 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 3/9/2006 | 3/9/2006 | 3/9/2006 | P | CANC |
Tony Young
|
|
|
Bob; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
BLD-Final | 3/9/2006 | 3/10/2006 | 3/9/2006 | A | PART |
Tony Young
|
|
|
Bob; Phone #: ###-#### all ok except need f/place finals
|
BLD-Grading Inspection | 3/9/2006 | 3/9/2006 | 3/9/2006 | | BOND |
|
|
|
Rough grading is complete. However, fine grading and revegetation of the disturbed hillside must still be done. For this a $1,000.00 bond is required. Upon receipt of this bond the grading and drainage is conditionally approved.
|
BLD-Conference | 3/3/2006 | 3/3/2006 | 3/3/2006 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 3/3/2006 at 10:18:04 AM. Contact: ###-####. ?s on steps
|
BLD-Wall cover | 11/23/2005 | 11/28/2005 | 11/28/2005 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 11/23/2005 at 2:01:24 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 11/18/2005 | 11/21/2005 | 11/21/2005 | A | FAIL |
Tony Young
|
|
|
shearnailing. need to do as per plans,, or letter from engineer as ok
|
BLD-Framing/Rough-in | 11/18/2005 | 11/18/2005 | 11/18/2005 | P | CANC |
Tom Arcoraci
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 11/18/2005 | 11/18/2005 | 11/18/2005 | P | FAIL |
Mike Jordan
|
|
|
Needs to complete lateral bracing. Minimum 3 8d nails for attic truss connection. Need solid blocking underneath floor at bearing points. engineer to review install of drag strut at stairway.
|
BLD-Foundation | 8/16/2005 | 8/16/2005 | 8/16/2005 | P | PART |
Tony Young
|
|
|
dave ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Footing | 8/9/2005 | 8/9/2005 | 8/9/2005 | P | PART |
Mike Jordan
|
|
|
dave; Phone #: ###-#### Note: please inspect before 3:00 - concrete on the way Internet Inspection Request from: Cathy Chiles. All reinforcement not in place at time of inspection. contractor was notified of deficiencies and will correct.
|
Issue PAID IN FULL permit | | | 7/26/2005 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 7/7/2005 | 7/7/2005 | 7/13/2005 | | PASS |
|
|
|
7/13/2005 07:52:17 SRZ - activity updated through activity BLDA022 from case BLD05-01503.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/13/2005 | | DONE |
|
|
|
ONE SET RED-LINED
|
Inspection Record Card- Bld | | | 7/13/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/13/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/13/2005 | | DONE |
|
|
|
|
Telephone call | | | 7/13/2005 | | DONE |
|
|
|
tlk to gabrielli ###-#### that permit and fees are ready to be picked up
|
Routing - PLAN CHECK | 6/17/2005 | | 7/13/2005 | | PASS |
|
|
|
|
PubWorks Subgrade Approval | 6/6/2005 | 6/6/2005 | 7/12/2005 | | DONE |
|
|
|
footing subgrade approved by the geotechnical engineer
|
Case Summary (BLD) | | | 7/12/2005 | | |
|
|
|
|
Plan Reviewer's activity | | | 7/8/2005 | | PASS |
|
|
|
Pending feedback from Engineer concerning beams. (SRZ)
|
Plan assigned to (SAM) | 6/6/2005 | 6/6/2005 | 7/7/2005 | | DONE |
|
|
|
|
Routing - FIRE | 6/15/2005 | | 6/17/2005 | | PASS |
|
|
|
No fire sprinklers required (Highlands Hackberry #5)
|
Routing - Erosion and Sediment | 6/14/2005 | | 6/15/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLANNING | 6/6/2005 | | 6/14/2005 | | PASS |
|
|
|
Routed and passed by Angela Wood per CFH05-00017. *computer file indicates plans were routed to AW last week -- incorrect record.
|
Application received | | | 6/6/2005 | | |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 6/6/2005 | | 6/6/2005 | | PASS |
|
|
|
Approved as Category 1 by CFH05-00017
|
Routing - PUBLIC WORKS | 6/6/2005 | | 6/6/2005 | | PASS |
|
|
|
|