Information based on query as of Saturday, August 17, 2024.
Permit Information
Permit NumberBLD05-01602
StatusFinaled
Name WRIGHT BROTHERS THE BLDG CO
Site Address 6352 N ROE ST
Project NameThe Cottages of Boise #2
Customer Number 
ePlanReviewNo
Description
To construct a new 9,606 square feet, two story, maximum 16 residence, 14 bedroom, assisted living facility, licensed by the State of Idaho, Facility Standards. NOTE: Per signed and approved alternate letter dated 1/20/06, a maximum of 5 people will be permitted to reside in this facility which will require assistance from the staff to evacuate the building in an emergency situation and there shall always be at least one employee of the owner in this building at all times. The following items are required throughout. The installation of a NFPA 13 fire sprinkler system with quick response heads, a manual and automatic fire alarm system, a fire detection system in all areas other than the patient sleeping rooms, smoke alarms shall be installed in all sleeping rooms, incidental use separation as required by Section 302.1.1.1, an one-hour fire barrier is required between the garage and the residence and a one-hour horizontal fire assembly is required between the first and second floor . The first floor is 8,198 sq.ft with an attached 525 sq.ft. garage. The second floor is 903 sq.ft and is used for staff offices. All construction per the approved plans and attached comment list. MJP CUP04-00100 CAR 04-00036
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/14/20056/14/20059/18/2008 DONE
DetailsCathy Brown
Second Notice BLD8/11/20088/11/20089/4/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice 7/21/20088/11/2008 DONE
Permanent Occupancy  7/21/2008  
per Tony Young ok to have perm occ-7-21-08 mls
BLD-Final6/30/20087/1/20087/2/2008PPASS
DetailsTony Young
Jeremy Phone #: ###-####
ok for perm c of o
Temporary Occupancy7/2/20089/30/20087/2/2008 DONE
DetailsBarbara Stitt
BLD-Final6/16/20086/17/20086/17/2008APART
DetailsTony Young
Dan Phone #: ###-####
temp occ ok,, conf only
BLD-Final6/16/20086/16/20086/16/2008PCANC
DetailsTony Young
Dan ###-#### Inspection cancelled from web by: Alexandra Rahn
BLD-Final6/10/20086/11/20086/11/2008APART
DetailsMike Jordan
Dan Phone #: ###-####. Needs to provide sloping surface at elevation change on sog from garage to mech. room at doorway. Install remainder of smoke seals on rated doors. Noted on approved plans and plan review notes for fairhousing act for kitchen counter heights and sink depth for kitchen sink is non compliant as in installed. Plans call for 34 inch counter heights with knee clearance underneath kitchen sink and 6.5 inch max depth on portion of kitchen sink. Noted to contractor that this needs to be repaired or rebsubmit for drawings from archtiect for approval. Ok for temp occ.
FIRE-Final Inspection6/10/20086/10/20086/10/2008PPASS
DetailsTroy Cobbley
Fire life safety passed.
BLD-Aging Inspection6/5/20086/5/20086/6/2008 PASS
DetailsTony Young
BLD-Foundation3/31/20083/31/20083/31/2008PPART
DetailsTony Young
dan Phone #: ###-####
2 light pole ftgs
BLD-Footing3/27/20083/28/20083/31/2008PCANC
DetailsTony Young
dan Phone #: ###-####
BLD-Footing3/27/20083/27/20083/27/2008PFAIL
DetailsTony Young
dan Phone #: ###-####
2 light pole ftgs,, not per plan, need ok as built or redo
BLD-Other3/11/20083/12/20083/12/2008APASS
DetailsTony Young
dan Note: shear nail Phone #: ###-####
interior ok
BLD-Other3/6/20083/7/20083/7/2008APASS
DetailsTony Young
Scheduled by a contractor via Hello! on 3/6/2008 at 6:33:35 PM. Contact: ###-####.
1st layer of rock ok
BLD-Wall cover2/28/20082/29/20082/29/2008APASS
DetailsTony Young
jeremy Phone #: ###-####
BLD-Framing/Rough-in2/25/20082/26/20082/26/2008PPASS
DetailsJim Storey
dan Phone #: ###-#### c/n ok meed foire chakling/ ok to insulate.
BLD-Framing/Rough-in2/21/20082/22/20082/22/2008PPASS
DetailsTony Young
dan Phone #: ###-####
BLD-Framing/Rough-in2/21/20082/22/20082/22/2008ANR
DetailsTony Young
dan Phone #: ###-####
need trades 1st
BLD-Aging Inspection2/18/20082/18/20082/21/2008 PASS
DetailsTony Young
Meeting  1/29/2008 DONE
Walk-in meting requested by architect Dave Davies to discuss a request for approval to install mag locks on three 80" exit doors, which would obstruct the opening height by 3 inches; no alternative was proposed for obstructing the required opening height. I indicated that would not be an acceptable obstruction and he agreed to use another model which mounts of the exterior and does not obstruct the existing 80" clear opening. We reviewed IBC 1008.1.8.6 I requirements. I also advised him to promptly advise the FA Engineer, who is about to approve the alarm shop drawings. Ihe PE will need to modify his FA design, resubmit it to the FA vendor who will change the shop drawings, then route them back to the PE for approval and then resubmit them to us, before we issue the fire alarm plans. Dave agreed to do so.
BLD-Framing/Rough-in12/13/200712/13/200712/13/2007PPART
DetailsTony Young
dan Phone #: ###-####
ok to rock walls where furnace is
BLD-Framing/Rough-in12/5/200712/6/200712/6/2007APART
DetailsJim Sly
dan Phone #: ###-####
OK to cover select walls in Mech Rm.
(F) Reprint permit  11/28/2007 DONE
(F) Reprint permit  11/26/2007 8888
Telephone call  11/26/2007  
Cheynne Weston was in and asked for copies of the permit and asked if any Park fees had been collected. Reprinted permit and told Cheynne that we have not collected fees at this ponit. He informed me that he has a meeting with legal regarding this project and will get more information back to us when a decision is made///11/26/07 3:30pm BAS
BLD-Other9/27/20079/28/20079/28/2007APASS
DetailsTony Young
jeremy Note: shear Phone #: ###-####
all ext shear ok
BLD-Footing8/22/20078/22/20078/22/2007PPART
DetailsJim Sly
bill Note: stem walls Phone #: ###-####
Stem walls OK pending MTI special inspection, tests, and approvals. Note: will provide special insp report for footing......next inspection.
BLD-Footing8/20/20078/20/20078/20/2007PPART
DetailsTony Young
Bill Phone #: ###-####-9006
pending eng/s. i. report
(F) Reprint permit  8/1/2007  
Issue PAID IN FULL permit  7/31/2007 DONE
Ready Permit EXTENDED  7/25/2007 DONE
Per Jenifer void permits, if not picked up on or before Aug.3,2007
Telephone call  6/26/2007 DONE
left vm for dave davies at ###-#### - permit ready and fees given - also need receipt for ACHD fees and RP needed
Telephone call  5/3/2007 DONE
left vm for dave davies at ###-#### - permit ready and fees given - also need receipt for ACHD fees and RP needed
Permit Ready to Issue  5/3/2007 DONE
Plan assigned to (M_P)6/15/20056/15/20055/2/2007 PASS
5/2/2007 08:34:43 M_P - activity updated through activity BLDA022 from case BLD05-01602.
Routing - PLAN CHECK5/1/2007 5/2/2007 PASS
PLANS/APPL TAKEN TO FRONT DESK  5/2/2007 DONE
Print Pending Permit.LaserJet4  5/2/2007 DONE
Case Summary (BLD)  5/2/2007 DONE
Print Occupancy Form  5/2/2007 DONE
Routing - PUBLIC WORKS4/30/2007 5/1/2007 PASS
Plan resubmittals received  4/30/2007  
Received 1 cover transmittal, 1 copy of sheets C-6, C-7, C-8 and taken to Mike Phillips
Routing - PLAN CHECK4/6/2006 4/30/2007  
Routing to P.W.
Plan Reviewer's activity  1/19/2007  
Expire permit on March 28th, 2007, per Jenifers e-mail dated 1/19/2007.
Plan Reviewer's activity  11/1/2006  
Sent letter to architect and owner expressing my intention to expire permit on November 20th, 2006.
Routing - PUBLIC WORKS4/4/2006 4/6/2006 FAIL
Waiting for DEQ approval. Contact Jim Pardy ###-####
Routing - PLAN CHECK3/20/2006 4/4/2006 PEND
Waiting for others to approve prior to issuing permit.
Routing - PLAN CHECK4/4/2006 4/4/2006  
Routing to P.W.
Routing - PLAN CHECK2/2/2006 3/20/2006 FAIL
Sent second e-mail requesting letter from architect to specify which occupancy I should review this project to?
Plan resubmittals received  3/9/2006  
Received 3 copies of Addendum 04, 3 copies of G15.62, G15.61, G3.32, G3.30, 5.11 and taken to Mike P.
Plan resubmittals received  2/10/2006 DONE
Received 2 letters, & 2 copys of sheets 1.00,3.30,3.35,g3.30,g3.32,g15.60,g15.61 taken to Mike P.
Routing - PLAN CHECK9/27/2005 2/2/2006 FAIL
3rd review failed, sent correction report to architect requesting additional information be submitted for further review prior to issuing permit.
Plan resubmittals received  1/23/2006 DONE
Received 2 Addendum sheets, & 2 copys of sheets 1.10,G3.32 taken to Mike P.
Plan Reviewer's activity  10/18/2005 FAIL
Requested copy of application to Facility Standards to verify level of care.
Plan resubmittals received  10/17/2005 DONE
Received 1 response,1 letter,1 res check 8 1/ 2 x 11 1 heating load calc, 1 cooling calc,& 2 Copys of sheets 1.11,1.13,G3.32,G3.30,5.12,G15.12,G15.22 Taken to Mike P.
Routing - PLUMBING  9/27/2005 PASS
plans approved per resubmittals dated 9/9/05. excluding any changes made for public works after this date.
Routing - PUBLIC WORKS9/19/2005 9/20/2005 FAIL
Routing - PLAN CHECK9/16/2005 9/19/2005  
Routing to P. W.
Routing - FIRE9/1/2005 9/16/2005 PASS
resubmittal approved with conditions. Revised comments faxed to architect.
Plan resubmittals received  9/12/2005  
Received (2) copies of sheet 15.04, 15.05, 15.10, 15.11, G15.10 and G15.11. Routed to Mike P.
Routing - PLAN CHECK8/18/2005 9/1/2005  
Routing to fire.
Plan resubmittals received  8/30/2005 DONE
Received 2 Response Letters, 2 United water sheets & 2 Copys of sheets C-0,C-6 Taken to Mike P.
Routing - PLAN CHECK7/27/2005 8/18/2005 FAIL
Second review failed, sent correction report to architect requesting additional informaiton be submitted for further review prior to issuing permit.
Plan Reviewer's activity  8/10/2005 DONE
E-mail the architect requesting if public works, plumbing and fire comments were included in this resubmittals.
Plan resubmittals received  8/9/2005  
Received (2) copies of sheet 1.0, 1.11, 3.10, G3.10, 3.30, G3.30, 3.31, G3.31, 3.50, G3.50, 5.12, 5.21, 7.00, 7.10, 7.11, 7.12, 15.04, 15.55, G15.62, G16.30 and 16.31. Routed to Mike P.
1st review completed  7/27/2005 FAIL
failed public works, plumbing, plan check and fire.
Routing - FIRE7/15/2005 7/27/2005 FAIL
review comments faxed to archtitect
Routing - PLAN CHECK6/27/2005 7/15/2005 FAIL
Plan review completed, sent correction report to architect requesting additional information be submitted for further review prior to issuing permit.
Routing - PLANNING6/27/2005 6/27/2005 PASS
Carl M. CUP04-00100
Routing - PLUMBING6/23/2005 6/27/2005 FAIL
verify compatibility of plastic drip pan with gas fired water heaters.
complete public works review requirements prior to plumbing plan review.
Routing - Erosion and Sediment6/22/2005 6/23/2005 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS6/17/2005 6/22/2005 FAIL
Pretreatment: Need to engineer the installation of a grease interceptor for all project building kitchens grease/grey water drainages. Contact Mke Hunter ###-####
Routing - PLANNING Land Div6/15/2005 6/17/2005 PASS
Legal parcel in Ada County prior to annexation.
Plans ACCEPTED BY PLAN TECH  6/15/2005  
Plan routing begun/NEW & ADDTN  6/15/2005  
Application received  6/14/2005  
Recd Pcfee & Taken To Pln CK  6/14/2005