Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD05-01608
StatusFinaled
Name WEST VALLEY CONSTRUCTION
Site Address 8119 W USTICK RD
Project Name 
Customer Number 
ePlanReviewNo
Description
*(Jamison R. Spencer D.M.C)* To remodel an existing 3128 sq ft dentist office for new health care office space. The first floor has an area of 3128 sq ft first floor and a 1464 sq ft basement. Work to include, remodeling one restroom for accessiblility requirements for unisex restroom, infill portions in existing partitions, construction of interior partitions to create waiting room, remove partition in basement to enlarge breakroom. Miscelaneous related interior fiinishes. (Rmh)
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD1/20/20061/20/200610/16/2006 DONE
Second Notice has not been responded to.
Telephone call  10/12/2006 DONE
tlk roger regarding the difference in ele and will be faxing the final bills to clear the difference
Telephone call  3/31/2006 DONE
tlk west valley construciton regarding I need their final values since 2/28 - he said that is on his desk in a pile that he would fax me the values next week for sure 2:20 pm cmc
Second Notice BLD12/22/200512/22/20051/20/2006 DONE
First Notice has not been responded to.
First Notice 12/6/200512/22/2005 DONE
Permanent occupancy  12/6/2005 DONE
Perm. Occ. Cert. # 10827 issued 12-6-05 to Jamison R. Spencer D.M.C.
BLD-Final12/2/200512/2/200512/2/2005PPASS
DetailsMike Jordan

Door hardware downstairs ok. All others finaled. Ok for perm occ.
Permanent Occupancy 12/2/200512/2/2005 DONE
Details
BLD-Final11/1/200511/2/200511/2/2005PPART
DetailsMike Jordan
pat; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. Ok for temp occ at upstairs only. Door hardware to be changed out in basement. Elec. and plumbing finals still need completed, temps only.
FIRE-Final Inspection11/1/200511/2/200511/2/2005APASS
DetailsTroy Cobbley
life safety finaled
BLD-Final10/31/200511/1/200511/1/2005PNR
DetailsJim Sly
pat; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
FIRE-Final Inspection10/31/200511/1/200511/1/2005AFAIL
DetailsTroy Cobbley
The duct smoke detector on the left side as you enter the room operated correctly but the duct detector on the right side did not operate correctly. Still need the hardware for doors in the basement.
BLD-Final10/28/200510/31/200510/31/2005PNR
DetailsJim Sly
pat; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
Need fire
FIRE-Final Inspection10/28/200510/31/200510/31/2005AFAIL
DetailsTroy Cobbley
Duct detectors still need connected and tested. Also need the door hardware in the basement installed.
FIRE-Final Inspection10/27/200510/28/200510/28/2005PCANC
DetailsTroy Cobbley
Not ready
BLD-Final10/25/200510/26/200510/26/2005PNR
DetailsJim Sly
pat; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
FIRE-Final Inspection10/25/200510/26/200510/26/2005AFAIL
DetailsTroy Cobbley
Project not ready for inspection. Duct detectors not wired up yet, exit signs not working, extinguishers not mounted.
FIRE-Final Inspection10/7/200510/10/200510/10/2005PFAIL
DetailsTroy Cobbley
Inspection was actually for a conference. I went over life safety items with the contractor. This included providing an additional exit sign at the bottom of the stairs with approved door hardware on the second exit to the exterior stairway. Also needs automatic flush bolts on the main entry exit. The two interior doors that lead into the main exit lobby require approved door hardware unless plan review is ok with the thumbturn deadbolts. Fire extinguishers will be required on both levels as well.
BLD-Conference10/6/200510/7/200510/7/2005PDONE
DetailsJim Sly
chris; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Framing/Rough-in9/15/20059/16/20059/16/2005APASS
DetailsMike Jordan
###-#### - chris
BLD-Framing/Rough-in9/1/20059/6/20059/6/2005APASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 9/1/2005 at 10:56:05 AM. Contact: ###-####.
Ustick and milwalkee.....Parking lot just East of Regies Vegies
Issue PAID IN FULL permit  7/26/2005 DONE
Plan assigned to (R_H)6/15/2005 6/16/2005 PASS
6/16/2005 11:20:57 RMH - activity updated through activity BLDA022 from case BLD05-01608.
Routing - PLAN CHECK6/15/2005 6/16/2005 PEND
pending public works review.
Case Summary (BLD)  6/16/2005 DONE
Routing - PUBLIC WORKS6/16/2005 6/16/2005 PASS
PLANS/APPL TAKEN TO FRONT DESK  6/16/2005 DONE
Routing - FIRE6/16/2005 6/16/2005 PASS
Inspector to field verify
Permit Ready to Issue  6/16/2005 DONE
Inspection Record Card- Bld  6/16/2005 DONE
Print Occupancy Form  6/16/2005 DONE
Telephone call  6/16/2005 DONE
Spoke with Tony and told him that permit is ready & fees///6/16/05 2:21pm BAS
1st review completed  6/16/2005 PASS
Plans ACCEPTED BY PLAN TECH  6/15/2005  
Application received  6/15/2005  
Recd Pcfee & Taken To Pln CK  6/15/2005 DONE
Fee Review-notes6/15/20056/15/2005   
Routing - PLAN CHECK6/16/2005