Third Notice BLD | 3/15/2006 | 3/15/2006 | 8/28/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 3/1/2006 | 3/1/2006 | 3/15/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 2/9/2006 | 2/9/2006 | 3/1/2006 | | DONE |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 2/9/2006 | 2/9/2006 | 2/9/2006 | | PASS |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 2/9/2006 | 2/9/2006 | 2/9/2006 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 12/6/2005 | 12/7/2005 | 12/7/2005 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/6/2005 at 4:06:25 PM. Contact: ###-####.
|
BLD-Aging Inspection | 10/27/2005 | 10/27/2005 | 10/27/2005 | | FAIL |
Jim Storey
|
|
|
pending mech and fire.
|
BLD-Wall cover | 8/22/2005 | 8/23/2005 | 8/23/2005 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 8/22/2005 at 2:37:50 PM. Contact: ###-####.
|
BLD-Footing | 6/30/2005 | 7/1/2005 | 7/1/2005 | A | PASS |
Mike Jordan
|
|
|
brian; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
(F) Reprint permit | | | 7/1/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/30/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/27/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/27/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/27/2005 | | DONE |
|
|
|
|
Telephone call | | | 6/27/2005 | | DONE |
|
|
|
Left voice message for Larry Knopp that permit is ready & fees///6/27/05 4:02pm BAS
|
Plan assigned to (MLO) | 6/7/2005 | 6/7/2005 | 6/24/2005 | | PASS |
|
|
|
6/24/2005 10:48:15 MLO - activity updated through activity BLDA022 from case BLD05-01485.
|
Routing - PLAN CHECK | 6/23/2005 | | 6/24/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/24/2005 | | DONE |
|
|
|
|
Routing - FIRE | 6/16/2005 | | 6/22/2005 | | PASS |
|
|
|
Acceptable FD access using the existing non-standard FD lane extension, which was provided and accepted for the existing Rec building. Water supply 2500 gpm, UW 4/25/2005. No review comments required.
|
1st review completed | | | 6/22/2005 | | FAIL |
|
|
|
failed plan check.
|
Plan resubmittals received | | | 6/21/2005 | | |
|
|
|
Received (2) copies of sheet A2.0 and A3.0 along with (2) copies of the Project Start Up for Special Inspections check list. Routed to Mike O.
|
Routing - PLAN CHECK | 6/14/2005 | | 6/16/2005 | | FAIL |
|
|
|
corrections sent to architect
|
Plan resubmittals requested | | | 6/16/2005 | | DONE |
|
|
|
IBC corrections
|
Application received | | | 6/15/2005 | | |
|
|
|
|
Routing - PLANNING | 6/14/2005 | | 6/14/2005 | | PASS |
|
|
|
Must comply with conditions of approval from CUP05-00045. CER
|
Routing - PLUMBING | 6/14/2005 | | 6/14/2005 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - Erosion and Sediment | 6/10/2005 | | 6/14/2005 | | PASS |
|
|
|
ESC approved with attached conditions.
|
Routing - PUBLIC WORKS | 6/10/2005 | | 6/10/2005 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 6/7/2005 | | 6/9/2005 | | PASS |
|
|
|
Lot 25, Block 8, Columbia Village #1
|
Plans ACCEPTED BY PLAN TECH | | | 6/7/2005 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 6/7/2005 | | |
|
|
|
|
Fee Review-notes | 6/7/2005 | 6/7/2005 | | | |
|
|
|
|