Permit Information
Permit NumberBLD05-01687
StatusFinaled
Name LEBOIS PARTNERS - TENANT EXPANSION
Site Address 121 N 9TH ST Unit: 304
Project NamePLAZA 121
Customer Number 
ePlanReviewNo
Description
(LEBOIS PARTNERS - PLAZA 121 - STE 304) This building is fire sprinklered. To expand an existing tenant into an adjacent 1,890 square foot tenant space located on the 3rd floor of an existing 76,680 square foot, 6 story building. Work is to include interior nonbearing walls, interior doors, interior windows, and finishes. The work shall comply with the approved drawings, the plan review report, and all applicable codes. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 9/2/20069/2/2006 DONE
Details
Second Notice BLD5/25/20065/25/20066/12/2006 DONE
First Notice has not been responded to.
First Notice 4/6/20065/25/2006 DONE
Permanent occupancy  4/6/2006 DONE
Perm. Occ. Cert. # 10972 issued 4-6-06 to LeBois Partners.
Case Summary (BLD)  1/31/2006  
BLD-Final9/1/20059/2/20059/2/2005APASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 9/1/2005 at 10:09:20 AM. Contact: ###-####. ok for prem occ
FIRE-Final Inspection9/2/20059/2/20059/2/2005PPASS
DetailsForrest France
Fire life safety finaled.
BLD-Final8/31/20059/1/20059/1/2005ANR
DetailsDave Hannah
Scheduled by a contractor via Hello! on 8/31/2005 at 12:42:04 PM. Contact: ###-####.
FIRE-Final Inspection8/30/20058/31/20058/31/2005AFAIL
DetailsForrest France
Need to install fire extinguishers as discussed.
BLD-Final8/30/20058/31/20058/31/2005ANR
DetailsDave Hannah
Scheduled by a contractor via Hello! on 8/30/2005 at 12:09:47 PM. Contact: ###-####.needs fire sign offs
BLD-Other8/25/20058/26/20058/26/2005APART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 8/25/2005 at 11:54:14 AM. Contact: ###-####.ceiling grid ok to cover
(F) Reprint permit  8/24/2005 DONE
Override - Parcel Holds  7/26/2005  
Issue PAID IN FULL permit  7/26/2005 DONE
Routing - PLAN CHECK7/22/2005 7/25/2005 DONE
PLANS/APPL TAKEN TO FRONT DESK  7/25/2005 DONE
Override - Parcel Holds  7/25/2005  
Inspection Record Card- Bld  7/25/2005 DONE
Override - Parcel Holds  7/25/2005  
Permit Ready to Issue  7/25/2005 DONE
Telephone call  7/25/2005 DONE
called told cory permit is ready and fees
Plan assigned to (CJW)6/24/2005 7/25/2005 PASS
7/25/2005 11:03:08 CJW - activity updated through activity BLDA022 from case BLD05-01687.
Routing - FIRE7/18/2005 7/22/2005 PASS
1st review completed  7/22/2005 PASS
Routing - PLAN CHECK6/28/2005 7/18/2005 PASS
The IBC plan review was started on July 18, 2005 and was finished the same day. The drawings were approved with "red lines". See the plan review report.
Routing - PUBLIC WORKS6/24/2005 6/28/2005 PASS
Plans ACCEPTED BY PLAN TECH  6/23/2005  
Application received  6/22/2005  
Recd Pcfee & Taken To Pln CK  6/22/2005 DONE
Fee Review-notes6/22/20056/22/2005