Permit Information
Permit NumberBLD05-01690
StatusFinaled
Name BOISE CITY PUBLIC WORKS DEPT
Site Address 11818 W JOPLIN RD
Project NameWEST BOISE WWTP
Customer Number 
ePlanReviewNo
Description
West Boise Waste Water Treatment Plant (Filtrate Tank) - To construct two new 50' X 50' X 20' deep concrete filtrate storage tanks, extend a utility tunnel and construct a 20' X 9.5' CMU building for a motor control center on top of the utility tunnel. All construction per the approved plans. MJP CUP 04-00137-Mod #1 10-17-06 * PLAN MODIFICATION * To modify and relocate the existing fire department access road as shown on revised sheet FIG.-1 Dated 10/-17/2006 MJP
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  2/22/2008 DONE
Office Staff conference/action  3/16/2007 DONE
refund requesed by city. Did not grant one, because of 500.00 plan mod. waived.
Fee Review-notes6/23/20056/23/20053/9/2007 DONE
First Notice2/12/20072/12/20073/1/2007 DONE
DetailsJim Sly
BLD-Final2/9/20072/12/20072/12/2007APASS
DetailsJim Sly
rick; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
Final OK........C/C issued.
DOC - Permit Finaled2/12/20072/12/20072/12/2007PPASS
DetailsJim Sly
BLD-Final2/8/20072/8/20072/8/2007PCANC
DetailsJim Sly
BLD-Final2/7/20072/8/20072/8/2007ACANC
DetailsJim Sly
rick; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
BLD-Final2/8/20072/8/20072/8/2007PCANC
DetailsJim Sly
rick; Phone #: ###-#### Internet Inspection Request from: Victoria Beall
CHANGE STATUS TO (ISS)  2/7/2007 DONE
reissue never was finaled
BLD-Final11/21/200611/21/200611/21/2006PNR
DetailsJim Sly
Pat, late afternoon if possible = ); Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
Verify if P/W wants to final.
FIRE-Final Inspection11/21/200611/21/200611/21/2006PPASS
DetailsTroy Cobbley
life safety already finaled on the 16th
FIRE-Final Inspection11/16/200611/16/200611/16/2006PPASS
DetailsTroy Cobbley
Life safety finaled
BLD-Final10/31/200611/3/200611/2/2006PCANC
DetailsJim Sly
pat - ###-#### Inspection cancelled from web by: Cathy Weisshaupt
FIRE-Final Inspection10/31/200611/3/200611/2/2006PCANC
DetailsTroy Cobbley
pat - ###-#### Inspection cancelled from web by: Cathy Weisshaupt
(F) Reprint permit  11/2/2006 DONE
Override - Parcel Holds  10/31/2006  
Override - Parcel Holds  10/31/2006  
Inspection Record Card- Bld  10/31/2006  
Telephone call  10/31/2006 DONE
lft vm to lawrence bennett ###-#### that modification permit is ready to be picked up
CHANGE STATUS TO (ISS)  10/31/2006 DONE
Override - Parcel Holds  10/31/2006  
Plan assigned to (M_P)10/17/200610/17/200610/30/2006 PASS
10/30/2006 11:29:55 M_P - activity updated through activity BLDA022 from case BLD05-01690.
Routing - PLAN CHECK10/30/2006 10/30/2006 PASS
PLANS/APPL TAKEN TO FRONT DESK  10/30/2006 DONE
Override - Parcel Holds  10/30/2006  
Print Pending Permit.LaserJet4  10/30/2006 DONE
Case Summary (BLD)  10/30/2006 DONE
Routing - FIRE10/26/2006 10/30/2006 PASS
Attached updated review comments to plans.
Routing - PLAN CHECK10/20/2006 10/26/2006 PEND
PLAN MODIFICATION
Mike Phillips
Case Summary (BLD)  10/26/2006  
Routing - Erosion and Sediment10/19/2006 10/20/2006 PASS
No plan modification required or submitted.
Routing - PLANNING10/18/2006 10/19/2006 PASS
Routing - PUBLIC WORKS10/18/2006 10/18/2006 PASS
Plan Modification Accepted  10/17/2006  
Plan Modification accepted for the redesign of road on one sheet of one. No fees charged per Marlene S
FIRE-Final Inspection10/2/200610/3/200610/4/2006AFAIL
DetailsTroy Cobbley
The plans need to be resubmitted since the fire dept. access roadway has changed significantly. All other items appear ok.
BLD-Final9/28/20069/29/20069/29/2006ANR
DetailsJim Sly
pat; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
BLD-Framing/Rough-in8/1/20068/2/20068/2/2006APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 8/1/2006 at 3:36:56 PM.
CMU walls Special insp req
BLD-Other5/31/20066/1/20066/1/2006PPASS
DetailsJim Sly
tab Note: elevate roof slab; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Last pour.........OK pending special inspection.......reports and approvals, and approval by Structural Engineer of record.
BLD-Final4/27/20064/28/20064/28/2006APART
DetailsJim Sly
PAT; Phone #: ###-#### Internet Inspection Request from: Darla Downs
Last pour on large tank walls......OK pending special insp by Rick Cummings and MTI tests and approvals.
BLD-Concrete4/25/20064/25/20064/25/2006PPART
DetailsJim Sly
pat Note: reinforcement ; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Utilidor Slabs OK pend MTI special insp tests and approvals.
BLD-Foundation4/19/20064/20/20064/20/2006APART
DetailsJim Sly
Pat\\ will pour in the pm on 4-20-06; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
S. E. corner....Wall insp. OK Pending special insp by Rick Cummings and MTI inspection, tests and approvals.
BLD-Framing/Rough-in4/10/20064/11/20064/11/2006APART
DetailsJim Sly
Pat -- concrete walls; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
North wall and Remainder of E wall.....OK pending MTI special insp tests and approvals
BLD-Framing/Rough-in3/24/20063/27/20063/27/2006APART
DetailsJim Sly
Pat -- concrete wall inspection; pouring at 12:00; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
Tall wall at West Tank Completion of North wall ....and N. W. 1/2 of West wall. Pending special insp, tests and approvals.
BLD-Framing/Rough-in3/13/20063/15/20063/15/2006APART
DetailsJim Sly
Pat -- wall concrete placement for filtrate tanks; pouring concrete at noon; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
Center section of South wall includes "T" section measuring 15'x15'x15'. 4000lb psi concrete required. Test results on previously poured sections at 7 day coming in at around 5800psi.
BLD-Framing/Rough-in3/6/20063/8/20063/8/2006APART
DetailsJim Sly
Pat -- for filtrate tank first wall pore; pouring at 10 AM; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
partial section of 20' high wall.
BLD-Footing2/23/20062/24/20062/24/2006APART
DetailsJim Sly
Pat -- will be pouring at noon; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
Pouring footing at SW and SE section of Bldg..........Special inspection by Rick Cummings and MTI.
BLD-Aging Inspection2/13/20062/13/20062/21/2006 DONE
DetailsJim Sly
WIP
Issue PAID IN FULL permit  11/3/2005 DONE
Inspection Record Card- Bld  9/30/2005 DONE
Permit Ready to Issue  9/30/2005 DONE
Routing - PLAN CHECK8/17/2005 9/29/2005 PASS
PLANS/APPL TAKEN TO FRONT DESK  9/29/2005 DONE
Print Pending Permit.LaserJet4  9/29/2005 DONE
Case Summary (BLD)  9/29/2005 DONE
Telephone call  9/29/2005 DONE
Spoke with Bill Freeman and the contract for the GC & RP goes out to bid next week so will be at least a month before pick up////9/29/05 5:00pm BAS
Plan assigned to (M_P)6/23/2005 9/29/2005 PASS
9/29/2005 13:16:09 M_P - activity updated through activity BLDA022 from case BLD05-01690.
Routing Off Site - STRUCTURAL9/16/2005 9/21/2005 PASS
Called PDQ for pick up
Plan resubmittals received  9/14/2005 DONE
Received 3 Structural Calcs, 3 Project Start Up for Special Inspections,3 Miscellaneous Metal Work & 4 Copys of sheets W-MIS-ST-400,W-MIS-ST-404,W-MIS-ST-405,W-FLT-ST-401,W-FLT-ST-403,W-FLT-ST-406 Taken to Mike P.
Telephone call  9/6/2005 DONE
The following email was sent in reply to inquiry by Bill Freeman about requirements for temporary FD access roadway. "Roads, at least of an approved temporary nature must be in place prior to storage of combustibles on site or construction using combustible materials. The FD may approve temporary use of unpaved roadways which are constructed of compacted gravel which has sufficient load-bearing capability and will be usable during adverse weather conditions. Contact the Fire Marshal, Dave Hanneman for further details on such a temporary roadway."
Routing - FIRE8/12/2005 8/17/2005 PASS
resubmittal acceptable. Review comments faxed to architect.
Plan resubmittals received  8/12/2005  
revied site plan received
Meeting  8/9/2005 DONE
*:15 am met with Bill Freeman reviewed plans which are indiscernable as to fire related features. He will bring back additional plans to supplement to verify FD access roadways(new and existing), hydrants, correct designation of construction which is actually part of this project and that which is future, etc.
1st review completed  8/8/2005 FAIL
failed plan check and fire.
Routing - FIRE7/26/2005 8/8/2005 FAIL
cannot determine FD access or haz mat's exposures. Emailed Bill Freeman to discuss further. Holding plans until I can discuss with Bill.
Routing - PLAN CHECK6/28/2005 7/26/2005 FAIL
Plan review complete, sent correction report to Bill Freeman requesting additional information be submitted for further review prior to issuing permit.
Case Summary (BLD)  7/26/2005  
Routing Off Site - STRUCTURAL6/23/2005 7/13/2005 FAIL
E-mailed comment to Bill Freeman. Additional information requried for further review by our outside engineering firm.
Routing - PLANNING6/28/2005 6/28/2005 PASS
Subject to compliance w/ CUP modification.
Routing - PLUMBING6/27/2005 6/28/2005 PASS
permit any potable water or sanitary sewer waste and vent piping.
Routing - Erosion and Sediment6/24/2005 6/27/2005 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS6/23/2005 6/24/2005 PASS
Routing - PLANNING Land Div6/23/2005 6/23/2005 PASS
Site is over 5 acres in size.
Plans ACCEPTED BY PLAN TECH  6/23/2005  
Ok per Mike P. to take in ///dld
Plan routing begun/NEW & ADDTN  6/23/2005  
Application received  6/23/2005