Second Notice BLD | 7/7/2006 | 7/7/2006 | 8/4/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 6/8/2006 | 7/7/2006 | | DONE |
|
|
|
|
Permanent Occupancy | | 6/8/2006 | 6/8/2006 | | DONE |
|
|
|
|
Temporary occupancy | | | 6/8/2006 | | DONE |
|
|
|
Temp. Occ. Cert. # 5410 issued 6-8-06 to Neighborhood Housing Services.
|
Permanent occupancy UNPAID FEE | | | 6/8/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11068 issued 6-8-06 to Neighborhood Housing Services (east side)
|
BLD-Final | 6/7/2006 | 6/7/2006 | 6/7/2006 | P | PASS |
Dave Hannah
|
|
|
paul; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok for perm occ
|
BLD-Final | 12/15/2005 | 12/16/2005 | 12/19/2005 | P | CANC |
Dave Hannah
|
|
|
PAUL; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Final | 12/19/2005 | 12/19/2005 | 12/19/2005 | P | PART |
Dave Hannah
|
|
|
paul; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok for temp occ need to finish ada lift and ramp in back
|
FIRE-Final Inspection | 12/15/2005 | 12/16/2005 | 12/16/2005 | A | PASS |
Forrest France
|
|
|
Fire life safety passed final inspection, NOTE: need to maintain 3' clearance around existing fire hydrant at main entrance off Shoreline Dr per requirements.
|
FIRE-Conference | 12/8/2005 | 12/9/2005 | 12/9/2005 | A | DONE |
Forrest France
|
|
|
On site discussion regarding life safety requirements and alarm related issues for the new manlift.
|
BLD-Framing/Rough-in | 12/8/2005 | 12/9/2005 | 12/9/2005 | A | PART |
Dave Hannah
|
|
|
paul///ceiling grid inspection please; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ok to drop in tiles
|
BLD-Framing/Rough-in | 12/7/2005 | 12/7/2005 | 12/8/2005 | P | FAIL |
Dave Hannah
|
|
|
t-bar inspection please////paul; Phone #: ###-#### Internet Inspection Request from: Barbara Moore needs to wire up lights
|
BLD-Concrete | 11/22/2005 | 11/22/2005 | 11/22/2005 | P | PART |
Dave Hannah
|
|
|
paul; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles cmu for ada lift crew is hand grouting every 4 ft ok for sec lift
|
BLD-Footing | 10/25/2005 | 10/25/2005 | 10/26/2005 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/25/2005 at 8:08:01 AM. Contact: ###-####. wheel chair lift ok to pour after they clean oout sluff and pick bar up for bottom clearance
|
BLD-Framing/Rough-in | 9/28/2005 | 9/29/2005 | 9/29/2005 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/28/2005 at 2:39:49 PM. Contact: ###-####. ok to cover after other trades sign off r/is
|
Issue PAID IN FULL permit | | | 8/15/2005 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 6/29/2005 | | 8/4/2005 | | PASS |
|
|
|
8/4/2005 13:51:49 RMH - activity updated through activity BLDA022 from case BLD05-01731.
|
Routing - PLAN CHECK | 7/28/2005 | | 8/4/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/4/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/4/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/4/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/4/2005 | | DONE |
|
|
|
|
Telephone call | | | 8/4/2005 | | DONE |
|
|
|
left mess for dave bliss at ###-#### permit is ready
|
Plan resubmittals received | | | 8/1/2005 | | |
|
|
|
Received (3) copies of structural calculations for Manlifts and Infills. Routed to Ron H.
|
Routing - FIRE | 7/19/2005 | | 7/28/2005 | | PASS |
|
|
|
review comments faxed to architect.
|
1st review completed | | | 7/28/2005 | | FAIL |
|
|
|
failed plan check
|
Routing - PLAN CHECK | 7/7/2005 | | 7/19/2005 | | FAIL |
|
|
|
Faxed and mailed requirements to the architect, routed plans to the fire department on 7/19/05
|
Routing - PLANNING | 7/6/2005 | | 7/7/2005 | | PASS |
|
|
|
Approved.
|
Routing - PUBLIC WORKS | 6/29/2005 | | 7/6/2005 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 7/6/2005 | | 7/6/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PARKS DEPARTME | 6/28/2005 | | 6/29/2005 | | PASS |
|
|
|
No requirements per Dave Selvage, Parks Dept.
|
Plans ACCEPTED BY PLAN TECH | | | 6/27/2005 | | |
|
|
|
|
Application received | | | 6/27/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/27/2005 | | DONE |
|
|
|
|
Fee Review-notes | 6/27/2005 | 6/27/2005 | | | |
|
|
|
|