Second Notice | | 7/22/2009 | 9/8/2009 | | DONE |
|
|
|
Value done by CMC in 2006
|
First Notice | 6/5/2009 | 6/5/2009 | 7/22/2009 | | DONE |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 6/5/2009 | 6/5/2009 | 6/5/2009 | | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 6/5/2009 | 6/5/2009 | 6/5/2009 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 3/24/2009 | 3/24/2009 | 3/24/2009 | | DONE |
Forrest France
|
|
|
Okay for final-fire sprinkler work completed.
|
BLD-Aging Inspection | 3/7/2008 | 3/7/2008 | 3/7/2008 | P | PART |
Forrest France
|
|
|
Project related fire sprinkler work is complete, will need scheduled fire life safety inspection for BLD final.
|
BLD-Aging Inspection | 3/7/2008 | 3/7/2008 | 3/7/2008 | | DEFR |
Dave Hannah
|
|
|
sent to 410 outstanding fire sprinkle issues
|
BLD-Final | 11/9/2005 | 11/10/2005 | 11/10/2005 | A | CANC |
Jim Storey
|
|
|
ron; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie fire failed
|
FIRE-Final Inspection | 11/9/2005 | 11/9/2005 | 11/9/2005 | P | FAIL |
Forrest France
|
|
|
Project will require fire sprinkler modifications as the newly installed duct is over 4' and significantly blocks coverage of the sprinklers from above, a fire sprinkler permit will be needed to perform this work.
|
BLD-Framing/Rough-in | 10/17/2005 | 10/17/2005 | 10/18/2005 | P | PASS |
Dave Hannah
|
|
|
wall cover insp//please call 10 min prior to meet you//ron; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa shaft on ground floor ok ot cover
|
Issue & PRINT to be Invoiced | | | 7/21/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/14/2005 | | 7/18/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/18/2005 | | PASS |
|
|
|
To permit desk for issuing process
|
Inspection Record Card- Bld | | | 7/18/2005 | | |
|
|
|
|
Permit Ready to Issue | | | 7/18/2005 | | |
|
|
|
|
Telephone call | | | 7/18/2005 | | DONE |
|
|
|
talked to curtis to verify plan is ready
|
Plan assigned to (DRS) | 6/30/2005 | | 7/18/2005 | | PASS |
|
|
|
7/18/2005 07:01:42 DRS - activity updated through activity BLDA022 from case BLD05-01733.
|
Routing - FIRE | 7/11/2005 | | 7/14/2005 | | PASS |
|
|
|
Approved subject to satisfactory field inspection. No written review required.
|
1st review completed | | | 7/14/2005 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 7/5/2005 | | 7/11/2005 | | PEND |
|
|
|
No resubmittals required. Routing to fire code analyst for review.
|
Routing - PUBLIC WORKS | 6/30/2005 | | 7/5/2005 | | PASS |
|
|
|
|
Routing - PLUMBING | 7/5/2005 | | 7/5/2005 | | PASS |
|
|
|
additional cross connection protection may be required.
|
Application received | | | 6/27/2005 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/27/2005 | | |
|
|
|
|
Fee Review-notes | 6/27/2005 | 6/27/2005 | | | |
|
|
|
|