BLD-Final | 10/18/2005 | 10/19/2005 | 10/19/2005 | A | PASS |
Jim Storey
|
|
|
todd; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
DOC - Permit Finaled | 10/19/2005 | 10/19/2005 | 10/19/2005 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 9/19/2005 | 9/19/2005 | 9/19/2005 | P | PASS |
Jim Storey
|
|
|
###-####
|
BLD-Framing/Rough-in | 9/16/2005 | 9/16/2005 | 9/16/2005 | P | PART |
Jim Storey
|
|
|
todd; Phone #: ###-#### Internet Inspection Request from: Barbara Moore frame ok ft missing. ok to insulate.
|
BLD-Framing/Rough-in | 9/15/2005 | 9/15/2005 | 9/15/2005 | P | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 9/15/2005 at 6:57:22 AM. Contact: ###-####.
|
BLD-Footing | 8/22/2005 | 8/24/2005 | 8/24/2005 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 8/22/2005 at 7:31:50 AM. Contact: ###-####.
|
BLD-Foundation | 8/22/2005 | 8/23/2005 | 8/23/2005 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/22/2005 at 7:32:33 AM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 8/1/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/27/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/27/2005 | | DONE |
|
|
|
|
Telephone call | | | 7/27/2005 | | DONE |
|
|
|
e-mailed michelle that permit is ready
|
Plan assigned to (SAM) | 6/29/2005 | 7/26/2005 | 7/26/2005 | | PASS |
|
|
|
7/26/2005 15:53:41 SAM - activity updated through activity BLDA022 from case BLD05-01758.
|
Routing - PLAN CHECK | 7/6/2005 | | 7/26/2005 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 7/26/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/26/2005 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 7/6/2005 | | 7/6/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 6/29/2005 | | 7/6/2005 | | PASS |
|
|
|
|
Application received | | | 6/29/2005 | | |
|
|
|
|