Case Summary (BLD) | | | 7/2/2013 | | DONE |
|
|
|
|
Third Notice BLD | 12/7/2005 | 12/7/2005 | 3/15/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice | | 9/19/2005 | 12/7/2005 | | DONE |
|
|
|
|
First Notice | | 9/9/2005 | 9/19/2005 | | DONE |
|
|
|
|
BLD-Final | 9/8/2005 | 9/9/2005 | 9/9/2005 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/8/2005 at 2:57:11 PM. Contact: ###-####. ok for perm occ
|
FIRE-Final Inspection | 9/8/2005 | 9/9/2005 | 9/9/2005 | A | PASS |
Forrest France
|
|
|
Fire extinguisher has been installed as discussed. Fire life safety finaled.
|
Permanent Occupancy | | 9/9/2005 | 9/9/2005 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 9/9/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10716 issued 9-9-05 to Laruen Meispa on the 6th floor of the U.S. Bank Bldg.
|
BLD-Framing/Rough-in | 9/6/2005 | 9/7/2005 | 9/7/2005 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/6/2005 at 3:33:45 PM. Contact: ###-####. ceiling grid ok to cover grid
|
BLD-Framing/Rough-in | 9/6/2005 | 9/6/2005 | 9/7/2005 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/6/2005 at 9:47:48 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/17/2005 | 8/17/2005 | 8/18/2005 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/17/2005 at 10:10:22 AM. Contact: ###-####. all plumbing pens in floor fire protected
|
BLD-Framing/Rough-in | 8/16/2005 | 8/16/2005 | 8/17/2005 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 8/16/2005 at 7:52:45 AM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 8/8/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/29/2005 | | 8/4/2005 | | PASS |
|
|
|
Drawings approved after resubmittal reveiw.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/4/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/4/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/4/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/4/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/4/2005 | | DONE |
|
|
|
|
Telephone call | | | 8/4/2005 | | DONE |
|
|
|
lft ms with cory nelson that permit and fees are ready to be picked up
|
Plan assigned to (CJW) | 7/7/2005 | | 8/4/2005 | | PASS |
|
|
|
8/4/2005 12:33:18 CJW - activity updated through activity BLDA022 from case BLD05-01821.
|
Routing - FIRE | 7/21/2005 | | 7/29/2005 | | PASS |
|
|
|
Faxed comments to architect
|
Plan resubmittals received | | | 7/29/2005 | | DONE |
|
|
|
Received Transmittal Letter, 1 Plan Review Response & 2 Copys of sheets A2.0,A3.0,A5.0 Taken to Carl W.
|
1st review completed | | | 7/29/2005 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - PLAN CHECK | 7/8/2005 | | 7/21/2005 | | FAIL |
|
|
|
The IBC plan review was started on July 20, 2005 and was finished the next day. Revised drawings were required. See the plan review report.
|
Routing - PUBLIC WORKS | 7/7/2005 | | 7/8/2005 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/6/2005 | | |
|
|
|
|
Application received | | | 7/5/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/5/2005 | | |
|
|
|
|
Fee Review-notes | 7/5/2005 | 7/5/2005 | | | |
|
|
|
|