Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD05-01831
StatusFinaled
Name THOMAS HAMMER COFFEE
Site Address 298 N 8TH ST
Project NameIDAHO BLDG-1ST FLR
Customer Number 
ePlanReviewNo
Description
(THOMAS HAMMER COFFEE)(IDAHO BLDG-1ST FLR) This building is fully sprinklered under the 1994 UCBC to allow building to be over height and number of stories and for allowable area increase. Plan alternates are being used per architect. To remodel a 1,881 sq.ft. tenant space for a coffee shop per approved plans. Previously occupied by a copy and print tenant. Work includes selective interior demolition; construction of new walls, doors and soffits; upgrade of electrical, mechanical, plumbing & sprinkler system to meet tenant needs and comply with current adopted codes & ordinances. (drs)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD12/28/200512/28/20051/3/2006 DONE
First Notice has not been responded to.
First Notice 12/14/200512/28/2005 DONE
Permanent Occupancy 12/14/200512/14/2005 DONE
Details
Permanent occupancy UNPAID FEE  12/14/2005 DONE
Perm. Occ. Cert. # 10840 issued 12-14-05 to Thomas Hammer Coffee.
Temporary occupancy  12/6/2005 DONE
Temp. Occ. Cert. # 5335 issued 12-6-05 to Thomas Hammer Coffee.
BLD-Final12/1/200512/5/200512/5/2005PPASS
DetailsDave Hannah
joel; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ok for perm occ
FIRE-Final Inspection11/29/200511/29/200511/29/2005APASS
DetailsForrest France
Fire life safety passed inspection.
FIRE-Final Inspection11/23/200511/28/200511/28/2005AFAIL
DetailsForrest France
Fire life safety items appear satisfactory, however, the related fire sprinker permit work must be inspected and approved prior to life safety final.
BLD-Final11/16/200511/29/200511/28/2005PCANC
DetailsDave Hannah
joel brown ###-#### Disp set to [CANC] by a contractor via Hello! on Nov 28 2005 11:41AM.
FIRE-Final Inspection11/23/200511/23/200511/23/2005PCANC
DetailsForrest France
###-#### - joel No time available for this inspection today, to be rescheduled per conversation.
FIRE-Final Inspection11/22/200511/22/200511/22/2005PCANC
DetailsForrest France
BLD-Framing/Rough-in10/20/200510/21/200510/24/2005APASS
DetailsDave Hannah
jim stubbs; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok to cover walls
BLD-Conference10/4/200510/5/200510/5/2005APASS
DetailsDave Hannah
jim; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Conference10/5/200510/5/200510/5/2005PPASS
DetailsDave Hannah
jim; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Issue PAID IN FULL permit  9/1/2005 DONE
Routing - PUBLIC WORKS8/30/2005 8/30/2005 PASS
connie
CHANGE STATUS TO (REV)  8/30/2005 DONE
changing plumbing
CHANGE STATUS TO (RDY)  8/30/2005 DONE
Inspection Record Card- Bld  8/15/2005 DONE
Permit Ready to Issue  8/15/2005 DONE
Telephone call  8/15/2005  
called architect (john price) ###-#### left message on voicemail permit its ready and fees.
Routing - FIRE8/3/2005 8/12/2005 PASS
Approved with conditions; review faxed to architect.
Plan assigned to (DRS)7/28/2005 8/12/2005 PASS
8/12/2005 14:47:56 DRS - activity updated through activity BLDA022 from case BLD05-01831.
1st review completed  8/12/2005 FAIL
failed Plan check and Public Works
Routing - PUBLIC WORKS8/12/2005 8/12/2005 PASS
PLANS/APPL TAKEN TO FRONT DESK  8/12/2005 PASS
Inspection Record Card- Bld  8/12/2005 DONE
Print Occupancy Form  8/12/2005 DONE
Plan resubmittals received  8/8/2005  
Received (3) copies of sheet A2.0, A2.2 and E2.1. Routed to Dan S.
Telephone call  8/3/2005 DONE
Called John Price concerning the door proposed for upgrade at the men's restroom on the second floor. This door needs to be a 60 minute assembly rather than the 45 minute shown. I also ask him about the restroom layout which differs from 2000 building plan on file. He said he drew the layout as it exists. He will also check the 2-hour shaft integrity for the north & south stair enclosures which show sideleight by the 1-1/2 hour doors into the enclosure. These should not be as shown. There is also a question on permits for Expressions T.I. of 2004 (BLD04-01353) and new tenant space for at east end of expressions (BLD00-03214) that have not been finaled and tenants do not have certificate of occupancy. This problem needs to be corrected.
Routing - PLAN CHECK7/12/2005 8/3/2005 FAIL
Clarifications coming from architect.Routing to fire code analyst for review.
Telephone call  8/2/2005 DONE
Call to John Price for clarifications on alternates. He said the alternate would be the scope of project. He is checking on outside air requirements and make-up air requirements for new hood and tenant use. I ask him to correct the electrical plan for energy code compliance because he had used the wrong factors and exceeded code requirements based on information provided. He will provide new sheets.
Plan assigned to (JCB)7/7/2005 7/28/2005 DEFR
Reassigned to Dan Stuart
Routing - PLUMBING7/11/2005 7/12/2005 PASS
per plans and 2003 upc
Routing - PUBLIC WORKS7/7/2005 7/11/2005 FAIL
Failed by Connie Baumgartner - ###-####

Need a menu to determine sewer fees.
Plans ACCEPTED BY PLAN TECH  7/7/2005  
Application received  7/6/2005  
Recd Pcfee & Taken To Pln CK  7/6/2005 DONE
Routing - PLAN CHECK8/12/2005 8/12/2004 PASS
Routing to permit desk.
Fee Review-notes7/6/20057/6/2005