BLD-Final | 3/30/2006 | 3/31/2006 | 3/31/2006 | P | PASS |
Tom Arcoraci
|
|
|
Buster; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
DOC - Permit Finaled | 3/31/2006 | 3/31/2006 | 3/31/2006 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Grading Inspection | 3/31/2006 | 3/31/2006 | 3/31/2006 | | BOND |
|
|
|
The rough grading and drainage have been completed at the above mentioned address. However, revegetation and fine grading have not been completed. For this the engineer has recommended a bond of $1,000.00. Upon receipt of this bond the grading and drainage is conditionally approved.
|
BLD-Energy code compliance | 10/31/2005 | 11/2/2005 | 11/2/2005 | A | PASS |
Tony Young
|
|
|
buster; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 10/25/2005 | 10/25/2005 | 10/25/2005 | P | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 10/25/2005 at 11:17:04 AM. exterior shear ok also
|
BLD-Framing/Rough-in | 10/24/2005 | 10/25/2005 | 10/25/2005 | A | PASS |
Tony Young
|
|
|
buster; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Foundation | 8/24/2005 | 8/25/2005 | 8/25/2005 | A | PART |
Tony Young
|
|
|
jeremy; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Footing | 8/15/2005 | 8/16/2005 | 8/16/2005 | A | PASS |
Tony Young
|
|
|
buster; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
PubWorks Subgrade Approval | 7/13/2005 | 7/13/2005 | 8/15/2005 | | DONE |
|
|
|
Footing subgrade aproved by the geotechnical engineer. 8/15/05
A letter from the applicant's geotechnical engineer indicating that the footing subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Terry Records at ###-####.
|
Inspection Record Card- Bld | | | 8/15/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/15/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/15/2005 | | DONE |
|
|
|
|
Telephone call | | | 8/15/2005 | | DONE |
|
|
|
called told Patty permit is ready did not have chance to tell her fees
|
Issue PAID IN FULL permit | | | 8/15/2005 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 7/11/2005 | 8/10/2005 | 8/12/2005 | | PASS |
|
|
|
8/12/2005 16:29:43 SAM - activity updated through activity BLDA022 from case BLD05-01870.
|
Routing - PLAN CHECK | | | 8/12/2005 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 8/12/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/12/2005 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 8/11/2005 | | DONE |
|
|
|
10:20 I called and talked to the engineer. I let him know that I need a detail for the 3'-2" foundation wall and also engineering for the SIP's roof panels. Plans are on hold.
|
Routing - FIRE | 7/13/2005 | | 7/14/2005 | | PASS |
|
|
|
no fire sprinkler requirements for this address
|
Routing - PLANNING | 7/13/2005 | | 7/13/2005 | | PASS |
|
|
|
Construction must comply with original conditional use permit and CFH05-00023.
|
Routing - Erosion and Sediment | 7/13/2005 | | 7/13/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS GRADING | 7/11/2005 | | 7/12/2005 | | PASS |
|
|
|
Approved as Category 1 by CFH05-00023
|
Routing - PUBLIC WORKS | 7/12/2005 | | 7/12/2005 | | PASS |
|
|
|
|
Application received | | | 7/11/2005 | | |
|
|
|
|