BLD-Final | 5/15/2006 | 5/15/2006 | 5/15/2006 | P | PASS |
Mike Jordan
|
|
|
Internet Inspection Request from: Carey Allen
|
DOC - Permit Finaled | 5/15/2006 | 5/15/2006 | 5/15/2006 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 5/12/2006 | 5/12/2006 | 5/12/2006 | A | NR |
Mike Jordan
|
|
|
Internet Inspection Request from: Carey Allen
|
BLD-Energy code compliance | 2/22/2006 | 2/22/2006 | 2/22/2006 | P | PASS |
Mike Jordan
|
|
|
Internet Inspection Request from: Carey Allen. TBE installed.
|
BLD-Energy code compliance | 2/15/2006 | 2/21/2006 | 2/21/2006 | P | FAIL |
Mike Jordan
|
|
|
Internet Inspection Request from: Carey Allen. Needs to install TBE.
|
BLD-Framing/Rough-in | 2/15/2006 | 2/16/2006 | 2/16/2006 | P | FAIL |
Mike Jordan
|
|
|
Internet Inspection Request from: Carey Allen. Add tbe to two ply truss in garage, add straps to bearing walls by stairs and in garage at gas piping. ok to insulate. c/n posted.
|
Plan Reviewer's activity | | | 2/16/2006 | | PASS |
|
|
|
Elevation Certificate received and approved by Jim W. Framing inspection may be performed.
|
BLD-Footing | 12/8/2005 | 12/9/2005 | 12/9/2005 | A | PART |
Mike Jordan
|
|
|
lito ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. Footing placed yesterday. insp. stemwall
|
Issue PAID IN FULL permit | | | 11/18/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/31/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/31/2005 | | DONE |
|
|
|
|
Telephone call | | | 10/31/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Plan assigned to (SAM) | 7/18/2005 | 7/18/2005 | 10/28/2005 | | PASS |
|
|
|
10/28/2005 13:37:02 PEP - activity updated through activity BLDA022 from case BLD05-01945.
|
Routing - PLAN CHECK | 10/21/2005 | | 10/28/2005 | | PASS |
|
|
|
|
Plan assigned to (PEP) | 10/28/2005 | | 10/28/2005 | | PASS |
|
|
|
10/28/2005 13:37:02 PEP - activity updated through activity BLDA022 from case BLD05-01945.
|
Case Summary (BLD) | | | 10/28/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/28/2005 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 10/20/2005 | | 10/21/2005 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 10/18/2005 | | 10/20/2005 | | PASS |
|
|
|
Pepper Hills #12 was recorded on 6/10/2005.
|
Plan resubmittals received | | | 10/18/2005 | | |
|
|
|
Applicant submitted new plan submittal. Will re-route to Planning for sign off.
|
Routing - PLANNING | 10/18/2005 | | 10/18/2005 | | PASS |
|
|
|
R-1B but per CUP03-74 setbacks (reduced to R-1C standards)
|
Plan resubmittals received | | | 9/28/2005 | | |
|
|
|
Received Base Elevation Certificate. Routed to Public Works.
|
Plan Reviewer's activity | | | 8/25/2005 | | |
|
|
|
Applicant picked up Plans & Application to make revisions. Applicant will resubmit under same BLD number.
|
Routing - PUBLIC WORKS | 8/3/2005 | | 8/3/2005 | | FAIL |
|
|
|
Needs flood plain requirements Contact Jim Wyllie ###-####
|
Routing - PLANNING | 7/28/2005 | | 8/2/2005 | | PASS |
|
|
|
|
Application received | | | 7/18/2005 | | |
|
|
|
|