Second Notice BLD | 12/5/2005 | 12/5/2005 | 12/19/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 11/25/2005 | 12/5/2005 | | DONE |
|
|
|
|
BLD-Final | 11/18/2005 | 11/23/2005 | 11/23/2005 | P | PASS |
Tom Arcoraci
|
|
|
ryan ; Phone #: ###-####//please check if mechanical permit needed for this project// Internet Inspection Request from: Marsha mech permit not required non done
|
FIRE-Final Inspection | 11/22/2005 | 11/23/2005 | 11/23/2005 | A | PASS |
Forrest France
|
|
|
c/n items have been completed, life safety passed.
|
Permanent Occupancy | | 11/23/2005 | 11/23/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 11/23/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10810 issued 11-23-05 to Pacific Subs.
|
FIRE-Final Inspection | 11/22/2005 | 11/22/2005 | 11/22/2005 | P | NR |
Forrest France
|
|
|
c/n not 100% completed yet per contractor.
|
FIRE-Final Inspection | 11/18/2005 | 11/22/2005 | 11/22/2005 | A | NR |
Forrest France
|
|
|
Per contractor phone call, not all items on the correction notice have been completed.
|
FIRE-Final Inspection | 11/17/2005 | 11/18/2005 | 11/18/2005 | A | FAIL |
Forrest France
|
|
|
Remove surface bolts and door stopper at back double doors, lower the provided fire ext. to 48" max AFF,one bulb at emergency light is out, provide visual indicator at main entry/exit door, post max occupant sign, no storage allowed in the break room, duct smoke detectors may be required at AHU's.
|
BLD-Final | 11/17/2005 | 11/18/2005 | 11/18/2005 | P | CANC |
Dave Hannah
|
|
|
ryan; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Inspection cancelled from web by: Marsha Smylie
|
BLD-Framing/Rough-in | 11/8/2005 | 11/9/2005 | 11/9/2005 | A | PART |
Dave Hannah
|
|
|
lloyd; Phone #: ###-#### Note: please call 1/2 hr prior to inpspection Internet Inspection Request from: Cathy Chiles 2hr wall sep in attic ok to install ceiling
|
BLD-Framing/Rough-in | 10/24/2005 | 10/25/2005 | 10/25/2005 | A | FAIL |
Jim Storey
|
|
|
lloyd; Phone #: ###-#### Note: please call 1/2 hr prior to inspection Internet Inspection Request from: Cathy Chiles
|
Routing - FIRE | 9/26/2005 | | 10/13/2005 | | PASS |
|
|
|
resubmittal acceptable. Review faxed to architect.
|
Routing - PLAN CHECK | 10/13/2005 | | 10/13/2005 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/13/2005 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 10/13/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/13/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/13/2005 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/13/2005 | | |
|
|
|
|
Plan assigned to (JCB) | 7/20/2005 | | 10/13/2005 | | PASS |
|
|
|
10/13/2005 13:19:47 JCB - activity updated through activity BLDA022 from case BLD05-01956.
|
Routing - PLUMBING | 9/16/2005 | | 9/26/2005 | | PASS |
|
|
|
Then route to Fire Dept. provide full size cleanouts at the ends of waste lines. floor drain required in the kitchen
|
Plan Reviewer's activity | | | 9/19/2005 | | DONE |
|
|
|
Alternate Approval request approved by the Building Official.
|
Routing - PLAN CHECK | 9/13/2005 | | 9/16/2005 | | PEND |
|
|
|
Alternate Approval Letter still needs approval by the Building Official. Plumbing Division and Fire Department still need to approve plans. Plans to route to these divisions.
|
Plan resubmittals received | | | 9/16/2005 | | |
|
|
|
Received (3) copies of sheet A1, A2 and A3. Routed to Jason B.
|
Telephone call | | | 9/13/2005 | | DONE |
|
|
|
Called architect representative, Josh Axthelm, to discuss some items that still need to be addressed concerning this project. He acknowledged and said the corrections will be made on the sheets and resubmittals provided within the next day.
|
Routing - PLAN CHECK | 8/24/2005 | | 9/13/2005 | | FAIL |
|
|
|
Called architect representative, Josh Axthelm, to discuss some items that still need to be addressed concerning this project. He acknowledged and said the corrections will be made on the sheets and resubmittals provided within the next day.
|
Plan resubmittals received | | | 9/9/2005 | | DONE |
|
|
|
Received 1 Response & 3 Copys of sheets A1,A2,A3 Taken to Jason B.
|
Meeting | | | 8/24/2005 | | DONE |
|
|
|
Met with architect representative and tenant representatives to discuss all issues to address in the plan review report. Issues will be addressed and new redesigned plans will be submitted.
|
1st review completed | | | 8/24/2005 | | FAIL |
|
|
|
failed public works, plumbing, plan check and fire.
|
Routing - FIRE | 8/19/2005 | | 8/24/2005 | | FAIL |
|
|
|
No review conducted. Failed due to extensive building changes which need to be made prior to plan check approval
|
Routing - PLAN CHECK | 8/16/2005 | | 8/19/2005 | | FAIL |
|
|
|
Plan review e-mailed and faxed to architect and tenant representative. Numerous issues to address. Plan resubmittals and a written response is required for further review. Plans to route to the Fire Dept.
|
Plan resubmittals requested | | | 8/19/2005 | | DONE |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - PUBLIC WORKS | 8/15/2005 | | 8/16/2005 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 8/16/2005 | | 8/16/2005 | | PASS |
|
|
|
ESC plan waiver request approved with attached conditions.
|
Routing - PLAN CHECK | 7/22/2005 | | 8/15/2005 | | FAIL |
|
|
|
Plans not reviewed yet. Plans requested to be routed back to Public Works with new layout/resubmittals.
|
Plan resubmittals received | | | 8/2/2005 | | |
|
|
|
Received (3) copies of sheet A-1, A-2 and A-3. Routed to Jason B.
|
Routing - PUBLIC WORKS | 7/20/2005 | | 7/22/2005 | | FAIL |
|
|
|
please route to Public Works for re-review
|
Routing - PLUMBING | 7/22/2005 | | 7/22/2005 | | FAIL |
|
|
|
please provide a plumbing plan showing the items listed above.
|
Application received | | | 7/19/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/19/2005 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/19/2005 | | |
|
|
|
|
Fee Review-notes | 7/19/2005 | 7/19/2005 | | | |
|
|
|
|