Permit Information
Permit NumberBLD05-01962
StatusFinaled
Name MICRON TECHNOLOGY INC
Site Address 8000 S FEDERAL WAY
Project NameMIC-NITROGEN TUBE TRAILER
Customer NumberC8394
ePlanReviewNo
Description
Micron Structural Concrete Slab - To construct a new 25' x 31' x 12" deep (775 sq. ft.) reinforced concrete support pad for two Nitrogen Trifluoride tube trailers. This concrete pad will be enclosed by a new 6'-0" chain-link fence and gate. This new concrete slab will be located east of Building #15 with its northwest corner beginning at the southeast corner of an existing roof covered concrete slab. This permit also includes the installation of associated connection piping and electrical for two new exterior lights to be located at the west end of the new pad. All construction per the approved plans.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD2/3/20062/3/20063/1/2006 DONE
First Notice has not been responded to.
First Notice1/17/20061/17/20062/3/2006 DONE
DetailsJim Storey
BLD-Final1/13/20061/17/20061/17/2006PFAIL
DetailsJim Storey
ernie; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
DOC - Permit Finaled1/17/20061/17/20061/17/2006PPASS
DetailsJim Storey
FIRE-Final Inspection1/11/20061/12/20061/12/2006PPASS
DetailsForrest France
Construction meets specifications, however the Nitrogen Triflouride trailers have not been installed on the pad at this time.
BLD-Aging Inspection12/29/200512/29/200512/29/2005 PASS
DetailsJim Storey
wip
BLD-Final10/19/200510/20/200510/20/2005ANR
DetailsJim Storey
ernie; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Issue & PRINT to be Invoiced  10/18/2005 DONE
Permit Ready to Issue  9/28/2005 DONE
Inspection Record Card- Bld  9/28/2005 DONE
Telephone call  9/28/2005 DONE
E-mailed Paul that permit is ready & fees///9/28/05 11:15am BAS
Routing - FIRE9/27/2005 9/27/2005 PASS
resubmittal acceptable
Routing - PLAN CHECK9/27/2005 9/27/2005 PASS
PLANS/APPL TAKEN TO FRONT DESK  9/27/2005 DONE
Plan assigned to (JCM)7/20/2005 9/27/2005 PASS
9/27/2005 16:17:13 JCM - activity updated through activity BLDA022 from case BLD05-01962.
Plan resubmittals received  9/8/2005 DONE
routed to fire
Telephone call  8/19/2005 DONE
Telcon with Bobbie Rice and Paul Marcolina. Bobbie claims material is NFPA health haz 2 per their evaluation of MSDS data. I requested a written response explaining their evaluation with MSDS included. She will do.
Routing - FIRE8/5/2005 8/18/2005 FAIL
Response from Micron indicates NF3 is not a health hazard 3 material, which contradicts our HMEX data. Called Paul, left voice mail to call me to discuss. Also called a Haz Mat consultant to get a 3rd party opinion; left message. Holding at my desk for additional information to conclude review.
Routing - PLAN CHECK8/1/2005 8/5/2005  
Received resubmittals and routed to Fire.
Plan resubmittals received  8/5/2005  
Received (3) copies of sheet P2.0. Routed to John M.
Routing - FIRE7/21/2005 8/1/2005 FAIL
review comments faxed to architect.
1st review completed  8/1/2005 FAIL
failed fire.
Plan Reviewer's activity  7/21/2005 PASS
Plans reviewed and approved as submitted. JCM
Routing - PLAN CHECK7/21/2005 7/21/2005 PASS
Pending Assignment by MYS7/19/2005 7/20/2005 DONE
7/20/2005 10:30:05 JCM - activity updated through activity BLDA166 from case BLD05-01962.
Plans ACCEPTED BY PLAN TECH  7/20/2005  
Application received  7/19/2005  
Third Notice BLD3/1/20063/1/2006   
Second Notice has not been responded to.
Fee Review-notes7/19/20057/19/2005