Fee Review-notes | 7/21/2005 | 7/21/2005 | 2/13/2007 | | DONE |
|
|
|
|
Telephone call | | | 2/7/2007 | | |
|
|
|
lft vm with erin regarding the cofv for 2 permit on one - needs to be on 2 separate cofv - I called and left ms 1/29 and calling again 2/7 3:30 pm
|
Third Notice BLD | 1/8/2007 | 1/8/2007 | 1/29/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Telephone call | | | 1/25/2007 | | DONE |
|
|
|
lft vm with eric regarding the bld permits 2 on one sheet wont work - she will return my call Monday
|
Second Notice BLD | 12/27/2006 | 12/27/2006 | 1/8/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 10/10/2006 | 10/10/2006 | 12/27/2006 | | DONE |
Mike Jordan
|
|
|
|
BLD-Aging Inspection | 10/4/2006 | 10/4/2006 | 10/10/2006 | | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 10/10/2006 | 10/10/2006 | 10/10/2006 | P | PASS |
Mike Jordan
|
|
|
work is now completed and has all sign offs.
|
BLD-Aging Inspection | 8/4/2006 | 8/4/2006 | 8/7/2006 | | PASS |
Mike Jordan
|
|
|
wip
|
BLD-Aging Inspection | 5/16/2006 | 5/16/2006 | 5/16/2006 | | PASS |
Mike Jordan
|
|
|
wip, body shop is still under construction. Should be near completion by end of May.
|
Code Occupancy Approval Temp | | | 12/6/2005 | | FAIL |
|
|
|
NEEDS TO BOND FOR $30,000 INCOMPLETE LANDSCAPE, THIS IS TO ONLY UTILIZE A SMALL PART OF THE PARKING LOT WHILE THE BODY SHOP IS UNDER CONSTRUCTION.
|
BLD-Final | 10/25/2005 | 10/26/2005 | 10/25/2005 | P | CANC |
Jim Sly
|
|
|
storm drain insp -for parking lot -phil; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Inspection cancelled from web by: Marsha Smylie
|
Case Summary (BLD) | | | 10/6/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/6/2005 | | |
|
|
|
|
Plan assigned to (DLD) Darla | 7/25/2005 | 7/25/2005 | 9/2/2005 | | PASS |
|
|
|
9/2/2005 08:15:38 KMW - activity updated through activity BLDA022 from case BLD05-01994.
|
Routing - PLAN CHECK | 9/1/2005 | | 9/2/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/2/2005 | | |
|
|
|
|
Permit Ready to Issue | | | 9/2/2005 | | DONE |
|
|
|
|
Telephone call | | | 9/2/2005 | | DONE |
|
|
|
called ###-#### and told David permit is ready and fees
|
Routing - FIRE | 8/23/2005 | | 9/1/2005 | | PASS |
|
|
|
resubmittal acceptable.
|
Plan resubmittals received | | | 8/23/2005 | | |
|
|
|
Received (2) copies of sheet FD1.1. Routed with plans/application to Sam R.
|
1st review completed | | | 8/16/2005 | | FAIL |
|
|
|
failed fire.
|
Routing - FIRE | 8/5/2005 | | 8/16/2005 | | FAIL |
|
|
|
review comments faxed to architect.
|
Routing - PLANNING | 8/1/2005 | | 8/4/2005 | | PASS |
|
|
|
Approved grading and drainage only.
|
Routing - PLUMBING | 7/29/2005 | | 8/1/2005 | | PASS |
|
|
|
no plumbing
|
Routing - Erosion and Sediment | 7/28/2005 | | 7/29/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 7/25/2005 | | 7/28/2005 | | PASS |
|
|
|
|
Plan resubmittals received | | | 7/27/2005 | | |
|
|
|
Received (2) copies of O & M manual. Routed to Brian M.
|
Routing - PLANNING Land Div | 7/25/2005 | | 7/25/2005 | | PASS |
|
|
|
Approved. Site is over 5 acres in size.
|
Plans ACCEPTED BY PLAN TECH | | | 7/25/2005 | | |
|
|
|
|
Application received | | | 7/21/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/21/2005 | | |
|
|
|
|
Routing - PLAN CHECK | 8/16/2005 | | | | FAIL |
|
|
|
Failed Fire. Plans in hold bin.
|