Case Summary (BLD) | | | 5/17/2010 | | DONE |
|
|
|
|
Second Notice BLD | 9/25/2006 | 9/25/2006 | 9/29/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 8/4/2006 | 8/4/2006 | 9/25/2006 | | DONE |
Jim Storey
|
|
|
|
PubWorks Occupancy Approval | 8/7/2006 | 8/7/2006 | 8/7/2006 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/4/2006 | 8/4/2006 | 8/4/2006 | P | PASS |
Forrest France
|
|
|
Required correction has been completed, inspection passed.
|
BLD-Final | 8/4/2006 | 8/4/2006 | 8/4/2006 | P | PASS |
Jim Storey
|
|
|
joe - call prior for access -late afternoon; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
DOC - Permit Finaled | 8/4/2006 | 8/4/2006 | 8/4/2006 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 8/4/2006 | 8/4/2006 | 8/4/2006 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 8/2/2006 | 8/2/2006 | 8/3/2006 | P | FAIL |
Forrest France
|
|
|
Fire dept. access lane marking does not meet requirements of current resubmitted approved plans, extend curb painting and hatched no parking stripes as discussed and indicated per plan.
|
Code Occupancy Approval | 8/2/2006 | 8/2/2006 | 8/2/2006 | P | PASS |
Wm. Michael Meloy
|
|
|
15:30 compliance met.
|
BLD-Final | 8/1/2006 | 8/2/2006 | 8/2/2006 | A | PART |
Jim Storey
|
|
|
joe - call prior for access; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley pending fir/pwk/zoning
|
BLD-Final | 7/17/2006 | 7/18/2006 | 7/18/2006 | A | FAIL |
Tony Young
|
|
|
joe; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley needs alarm signed off,, also conf on signage, plans, insulate king studs?
|
BLD-Other | 6/15/2006 | 6/16/2006 | 6/16/2006 | A | PASS |
Jim Storey
|
|
|
ceilling ok
|
BLD-Other | 6/15/2006 | 6/15/2006 | 6/15/2006 | P | DEFR |
Jim Storey
|
|
|
Joe, ceiling grid reinspection; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt to am fri
|
BLD-Framing/Rough-in | 6/13/2006 | 6/14/2006 | 6/14/2006 | A | FAIL |
Jim Storey
|
|
|
joe - ceiling grid insp; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
|
BLD-Aging Inspection | 6/12/2006 | 6/12/2006 | 6/12/2006 | | PASS |
Jim Storey
|
|
|
wip
|
Plan resubmittals received | | | 6/7/2006 | | |
|
|
|
Received 1 copy of faxed letter to John Menard, 1 copy main entry sketch, 1 copy of west entry sketch, 1 copy of east entry sketch and taken to John M.
|
BLD-Energy code compliance | 4/11/2006 | 4/12/2006 | 4/12/2006 | A | NR |
Jim Storey
|
|
|
Joe -- call 1st before insp; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
BLD-Framing/Rough-in | 4/12/2006 | 4/12/2006 | 4/12/2006 | A | PASS |
Jim Storey
|
|
|
Joe -- call 1st before insp; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
BLD-Aging Inspection | 3/8/2006 | 3/8/2006 | 3/8/2006 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Other | 1/3/2006 | 1/4/2006 | 1/4/2006 | A | PASS |
Tom Arcoraci
|
|
|
JOE nOTE; EXTERIOR SHEETING; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to side
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 1/3/2006 | | |
|
|
|
|
(F) Reprint permit | | | 1/3/2006 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 1/3/2006 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 12/21/2005 | 12/22/2005 | 12/22/2005 | A | PART |
Tom Arcoraci
|
|
|
wall sheathing to 8 foot//Joe ###-#### 8 ft ok and north side full ht ok
|
Override - Parcel Holds | | | 12/21/2005 | | |
|
|
|
|
Override - Parcel Holds | | | 12/16/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 12/16/2005 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 12/16/2005 | | |
|
|
|
|
Permit Ready to Issue | | | 12/16/2005 | | DONE |
|
|
|
|
Telephone call | | | 12/16/2005 | | DONE |
|
|
|
called ###-#### and told her that plan mod is ready to pick up and fees
|
Plan resubmittals received | | | 12/14/2005 | | DONE |
|
|
|
Received 1 transmittal & 2 copys of sheet C1.4 taken to John M.
|
Plan Reviewer's activity | | | 12/13/2005 | | PASS |
|
|
|
Reviewed plans for allowable area and modified the permit to delete the requirement for a sprinkler system. This permit was originally approved with a full fire sprinkler system. The sprinkler system was required as an alternate to a portion of the required fire access. The plans have been modified, with the approval of the fire department, to delete the requirement for a sprinkler system with the installation of an acceptable fire access lane. JCM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/13/2005 | | DEFR |
|
|
|
|
Plan assigned to (JCM) | 11/7/2005 | | 12/13/2005 | | PASS |
|
|
|
12/13/2005 15:53:35 JCM - activity updated through activity BLDA022 from case BLD05-02001.
|
Routing - FIRE | 12/6/2005 | | 12/13/2005 | | PASS |
|
|
|
|
BLD-Framing/Rough-in | 12/9/2005 | 12/12/2005 | 12/12/2005 | A | PART |
Jim Storey
|
|
|
joe taras ###-#### roof ok
|
Routing - PLAN CHECK | 12/13/2005 | | 12/12/2005 | | PASS |
|
|
|
Plan Modification.
|
Override - Parcel Holds | | | 12/9/2005 | | |
|
|
|
|
Routing - PLAN CHECK | 11/19/2005 | | 12/6/2005 | | |
|
|
|
|
Plan resubmittals received | | | 12/5/2005 | | DONE |
|
|
|
Received 1 transmittal, 1 letter to Sam R. & 2 copys of sheet A1.11 Taken to John M.
|
Routing - FIRE | 11/7/2005 | | 11/19/2005 | | FAIL |
|
|
|
proposed FD roadway modification is not code compliant. Revised review faxed to architect.
|
Plan Modification Accepted | | | 11/7/2005 | | |
|
|
|
Plan modification accepted for the elimination of the fire sprinkler system and the addition of a fire access lane on the west side of the building on sheet A0.01, A1.11 and A2.11. Routed to John M.
|
Routing - PLAN CHECK | 11/7/2005 | | 11/7/2005 | | |
|
|
|
|
CHANGE STATUS TO (REV) | | | 11/4/2005 | | DONE |
|
|
|
plan modification
|
BLD-Foundation | 10/14/2005 | 10/17/2005 | 10/17/2005 | A | PASS |
Jim Storey
|
|
|
after 10am please///jack ; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Footing | 10/11/2005 | 10/12/2005 | 10/12/2005 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/11/2005 at 11:30:47 AM. Contact: ###-####.
|
BLD-Footing | 10/11/2005 | 10/11/2005 | 10/11/2005 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/11/2005 at 11:19:03 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Oct 11 2005 11:29AM.
|
(F) Reprint permit | | | 9/22/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/21/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/19/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/19/2005 | | DONE |
|
|
|
|
Telephone call | | | 9/19/2005 | | DONE |
|
|
|
left mess for jessica at ###-#### that permit is ready & need achd
|
Routing - FIRE | 9/1/2005 | | 9/16/2005 | | PASS |
|
|
|
resubmittal acceptable. Revised reveiw comments faxed to architect.
|
Routing - PLAN CHECK | 9/16/2005 | | 9/16/2005 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 9/16/2005 | | PASS |
|
|
|
Reviewed and approved final resubmittal from the project structural engineer. JCM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/16/2005 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 7/26/2005 | | 9/16/2005 | | PASS |
|
|
|
9/16/2005 15:34:25 JCM - activity updated through activity BLDA022 from case BLD05-02001.
|
Plan resubmittals received | | | 9/12/2005 | | |
|
|
|
Received (2) copies of sheet A2.41, E1.0 and (2) sets of supplemental structural calcs. Routed to John M.
|
Routing Off Site - STRUCTURAL | 9/1/2005 | | 9/7/2005 | | FAIL |
|
|
|
Called PDQ for pick up - E-mailed the architect with a copy of the second review comment list from the consulting structural engineer. JCM
|
Plan resubmittals requested | | | 9/7/2005 | | DONE |
|
|
|
E-mailed the architect a copy of the second comment list from the consulting structural engineer requesting additional calculations. JCM
|
Plan Reviewer's activity | | | 9/1/2005 | | PASS |
|
|
|
Reviewed and approved resubmitted plan sheets. JCM
|
Routing - PLAN CHECK | 8/16/2005 | | 9/1/2005 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/31/2005 | | DONE |
|
|
|
Received Transmittal 2 Letters for Sam R., 1 Building Permit Fire Code Review,& 2 Copys of sheets A0.01,A2.11, A2.31,A3.11,A6.11 Taken to John M.
|
Plan resubmittals received | | | 8/31/2005 | | DONE |
|
|
|
Received Transmittal Letter, 1 Plan Review Division Fax Transmittal 1 Review Comments , 3 Supplemental Calcs, & 3 Copys of sheets S3.11,S4.11 Taken to John M.
|
Plan resubmittals requested | | | 8/25/2005 | | |
|
|
|
Sent following email to Jessica Rodriquez: Jessica, Dave Miller has agreed to your proposal to fully fire sprinkler the building as an alternate to providing additional roadways. Please resubmit plans revised to reflect this modification and I will be able to approve them from a Fire standpoint. Please note that it appears from the permit activity notes that John Minard is holding the plans, awaiting a resubmittal from you on his IBC building plan review.
|
1st review completed | | | 8/16/2005 | | FAIL |
|
|
|
failed structural, plan check and fire.
|
Routing - FIRE | 8/8/2005 | | 8/16/2005 | | FAIL |
|
|
|
review faxed to architect
|
Plan resubmittals received | | | 8/9/2005 | | DONE |
|
|
|
Received Transmittal & 2 Copys of sheet A3.21 Taken to John M.
|
Routing Off Site - STRUCTURAL | 7/26/2005 | | 8/8/2005 | | FAIL |
|
|
|
Called PDQ for pick up - Received e-mailed comment list from the consulting structural engineer requesting revisions. JCM
|
Plan resubmittals requested | | | 8/8/2005 | | DONE |
|
|
|
Faxed the architect a copy of the plan review comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - PLAN CHECK | 8/4/2005 | | 8/8/2005 | | FAIL |
|
|
|
John M.
|
Routing - PLANNING | 8/2/2005 | | 8/4/2005 | | PASS |
|
|
|
Sara S. DRH05-00061 Approved per DRH05-00061.
|
Routing - PLUMBING | 8/1/2005 | | 8/2/2005 | | PASS |
|
|
|
min. roof drainage piping grade for size is 1/4" per foot.
|
Routing - Erosion and Sediment | 7/29/2005 | | 8/1/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Plan resubmittals requested | | | 8/1/2005 | | DONE |
|
|
|
Mailed the architect a copy of the plan review requesting revisions.
|
Routing - PUBLIC WORKS | 7/26/2005 | | 7/29/2005 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 7/26/2005 | | 7/26/2005 | | PASS |
|
|
|
Approved as Unit 101 in Riverwalk Condos No. 5.
|
Plans ACCEPTED BY PLAN TECH | | | 7/26/2005 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 7/26/2005 | | |
|
|
|
|
Application received | | | 7/22/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/22/2005 | | |
|
|
|
|
Fee Review-notes | 7/22/2005 | 7/22/2005 | | | |
|
|
|
|
Routing - PLANNING | | | | | |
|
|
|
|