Third Notice BLD | 8/18/2006 | 8/18/2006 | 3/1/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Telephone call | | | 2/13/2007 | | DONE |
|
|
|
lft ms with RA Shultz ###-#### to confirm the final values on the mechanical
|
Second Notice BLD | 8/2/2006 | 8/2/2006 | 8/18/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 7/17/2006 | 8/2/2006 | | DONE |
|
|
|
|
Permanent occupancy | | | 7/13/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11132 issued 7-13-06 to St. Mark's Church for the food bank addn.
|
BLD-Final | 6/28/2006 | 6/29/2006 | 6/29/2006 | A | PASS |
Jim Sly
|
|
|
diana - food bank; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley OK for Perm Occ. :)
|
Permanent Occupancy | | 6/29/2006 | 6/29/2006 | | DONE |
|
|
|
|
Code Occupancy Approval | | | 6/27/2006 | | PASS |
|
|
|
|
BLD-Final | 6/16/2006 | 6/19/2006 | 6/20/2006 | A | FAIL |
Jim Sly
|
|
|
dianna; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley See prev note
|
BLD-Final | 6/13/2006 | 6/14/2006 | 6/14/2006 | A | NR |
Jim Sly
|
|
|
diana - call prior to insp for access; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley OK for Perm....when Code enforce Perms
|
Code Occupancy Approval Temp | 2/28/2006 | 2/28/2006 | 2/28/2006 | P | FAIL |
Carol Montgomery
|
|
|
Signed temp. - very small portion of landscaping at the north and west side of the bldg. to be completed.
|
BLD-Final | 2/13/2006 | 2/14/2006 | 2/14/2006 | P | NR |
Jim Sly
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa Need ACHD to verify OK........CDHD same and Code Enforce to final for Perm.
|
FIRE-Final Inspection | 2/13/2006 | 2/14/2006 | 2/14/2006 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled.
|
Print Occupancy Form | | | 2/14/2006 | | |
|
|
|
Request for reprint per Jim Sly 2-14-06 eus
|
BLD-Final | 1/17/2006 | 1/18/2006 | 1/18/2006 | A | PART |
Jim Sly
|
|
|
matt ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie OK for Temp Occ. OK to Perm when Fire Perms.
|
FIRE-Final Inspection | 1/13/2006 | 1/17/2006 | 1/17/2006 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Dave Hannemans permission until the revised fire alarm plans are approved. Sprinkler permit needs finaled. Life safety will be ok to final when both fire permits are finaled and the new door has closer and seals.
|
BLD-Conference | 12/28/2005 | 12/29/2005 | 12/29/2005 | A | PASS |
Jim Sly
|
|
|
###-#### Jack
|
BLD-Framing/Rough-in | 12/15/2005 | 12/16/2005 | 12/16/2005 | A | PASS |
Jim Sly
|
|
|
ceiling grid matt; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Energy code compliance | 11/21/2005 | 11/21/2005 | 11/21/2005 | P | PASS |
Jim Sly
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 11/18/2005 | 11/18/2005 | 11/18/2005 | P | PART |
Jim Sly
|
|
|
jack ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie C/N....Need clarific from Arch for A35 clip location and how to extend 1hr wall to roof deck. Non rated electr panel in 1hr wall. No tag on door frame (not installed yet)
|
BLD-Framing/Rough-in | 11/17/2005 | 11/18/2005 | 11/18/2005 | A | NR |
Jim Sly
|
|
|
matt; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Foundation | 10/10/2005 | 10/10/2005 | 10/10/2005 | P | PART |
Jim Sly
|
|
|
corwin; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa OK Pending Special insp, tests and approvals (STRATA)
|
BLD-Footing | 10/5/2005 | 10/5/2005 | 10/5/2005 | P | PART |
Jim Sly
|
|
|
corwin; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa Footing..... OK pending special insp (STRATA) tests and approvals.
|
Issue PAID IN FULL permit | | | 9/28/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/16/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/16/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/16/2005 | | DONE |
|
|
|
|
Telephone call | | | 9/16/2005 | | DONE |
|
|
|
left mess for dave davies at ###-#### is ready & need achd, & r/p info & gc.
|
Routing - Erosion and Sediment | 9/14/2005 | | 9/15/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/15/2005 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 7/26/2005 | | 9/15/2005 | | PASS |
|
|
|
9/15/2005 14:48:56 MLO - activity updated through activity BLDA022 from case BLD05-02014.
|
Plan resubmittals received | | | 9/14/2005 | | DONE |
|
|
|
Received 2 Erosion and Sediment Control Narratives,1 Letter,1 Erosion and Sediment Control Permit Application & 2 Copys of sheet C1.0 Taken to Mike O.
|
Routing - Erosion and Sediment | 9/12/2005 | | 9/12/2005 | | FAIL |
|
|
|
ESC waiver request denied on 7-27-05. Still waiting on resubmittal. Contacted architect and left vm.
|
Routing - FIRE | 8/29/2005 | | 9/10/2005 | | PASS |
|
|
|
resubmittal acceptable subject to comments concerning discrepancy between United Water and Capitol Water flow reports. Revised review faxed to architect.
|
Plan resubmittals received | | | 8/30/2005 | | DONE |
|
|
|
Received 2 Response Letters & 2 Copys of sheet 2.00 Taken to Mike O.
|
Routing - PLAN CHECK | 8/26/2005 | | 8/29/2005 | | PASS |
|
|
|
|
1st review completed | | | 8/25/2005 | | FAIL |
|
|
|
failed plan check and fire.
|
Routing - FIRE | 8/16/2005 | | 8/25/2005 | | FAIL |
|
|
|
review comments faxed to architect.
|
Plan resubmittals received | | | 8/22/2005 | | |
|
|
|
Received (2) copies of sheet 1.00, 2.00, 3.10, 3.30, 5.00, 5.20 and 6.00. Also received (2) sets of structural calcs. Routed to Mike O.
|
Routing - PLAN CHECK | 8/9/2005 | | 8/16/2005 | | FAIL |
|
|
|
corrections sent to architect
|
Plan resubmittals requested | | | 8/16/2005 | | DONE |
|
|
|
IBC corrections
|
Routing - PLANNING | 7/28/2005 | | 8/9/2005 | | PASS |
|
|
|
Per all conditions of CUP02-38 Mod 1.
|
Routing - PLUMBING | 7/27/2005 | | 7/28/2005 | | PASS |
|
|
|
1/4" per foot grade on 2" waste. 120 deg. max hot water to public lavs.
|
Routing - PUBLIC WORKS | 7/26/2005 | | 7/27/2005 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 7/27/2005 | | 7/27/2005 | | FAIL |
|
|
|
ESC plan waiver request denied. Informed applicant via voice mail.
|
Plans ACCEPTED BY PLAN TECH | | | 7/26/2005 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 7/26/2005 | | |
|
|
|
|
Routing - PLANNING Land Div | 7/26/2005 | | 7/26/2005 | | PASS |
|
|
|
Approved, site is over 5 acres in size.
|
Application received | | | 7/22/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/22/2005 | | |
|
|
|
|
Fee Review-notes | 7/22/2005 | 7/22/2005 | | | |
|
|
|
|
Routing - PLAN CHECK | 9/12/2005 | | | | |
|
|
|
|