Third Notice BLD | 2/12/2007 | 2/12/2007 | 12/10/2014 | | DONE |
Cathy Chiles
|
|
|
This permit finaled on the web by Jakie Phelps
|
Telephone call | | | 2/13/2007 | | DONE |
|
|
|
lft vm with jackie ###-#### regarding the final differences in the plum value - should give me a call back
|
Second Notice BLD | 2/2/2007 | 2/2/2007 | 2/12/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 1/4/2007 | 2/2/2007 | | DONE |
|
|
|
|
Permanent occupancy | | | 12/18/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11362 issued 12-18-06 to Healthwise.
|
BLD-Final | 11/29/2006 | 12/1/2006 | 12/1/2006 | A | PASS |
Tony Young
|
|
|
ross ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok for perm c of o
|
PubWorks Occupancy Approval | 10/18/2006 | 10/18/2006 | 10/18/2006 | | DONE |
|
|
|
|
Temporary occupancy | | | 10/16/2006 | | DONE |
|
|
|
Temp. Occ. Cert. #5462 issued 10-16-06 to Healthwise.
|
BLD-Final | 10/12/2006 | 10/13/2006 | 10/13/2006 | P | PART |
Tony Young
|
|
|
ross - note: structrual and code enforcement ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok for temp. occ. pending code enforcement
|
FIRE-Final Inspection | 10/12/2006 | 10/13/2006 | 10/13/2006 | A | PASS |
Forrest France
|
|
|
Corrections have been verified, fire life safety inspection passed. Note, one section of curb missing fire lane paint marking to be completed per contractor, will verify next week for compliance.
|
BLD-Grading Inspection | 10/13/2006 | 10/13/2006 | 10/13/2006 | | DONE |
|
|
|
final Grading and drainage approved
|
FIRE-Final Inspection | 10/11/2006 | 10/12/2006 | 10/12/2006 | P | NR |
Forrest France
|
|
|
Still need alarm and sprinkler trade permits signed off before life safety final.
|
FIRE-Final Inspection | 10/10/2006 | 10/11/2006 | 10/11/2006 | P | CANC |
Troy Cobbley
|
|
|
No time for inspection due to time constraints and micron plan review
|
FIRE-Final Inspection | 10/9/2006 | 10/10/2006 | 10/10/2006 | A | FAIL |
Troy Cobbley
|
|
|
No fire life safety inspection was performed since the fire sprinklers and the fire alarm permit are not finaled yet.
|
BLD-Final | 10/6/2006 | 10/9/2006 | 10/9/2006 | P | NR |
Tony Young
|
|
|
ross; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
FIRE-Final Inspection | 10/6/2006 | 10/9/2006 | 10/9/2006 | P | FAIL |
Forrest France
|
|
|
The project related alarm and sprinkler permit work must be approved and finaled prior to BLD life safety final. Note: two alarm permits are attatched to this project.
|
FIRE-Final Inspection | 10/4/2006 | 10/6/2006 | 10/6/2006 | P | CANC |
Troy Cobbley
|
|
|
No time left in day for inspection
|
BLD-Final | 10/5/2006 | 10/6/2006 | 10/6/2006 | P | NR |
Tony Young
|
|
|
ross - note: after 3:30 pm ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
BLD-Conference | 9/29/2006 | 10/4/2006 | 10/4/2006 | A | DONE |
Dave Hannah
|
|
|
ross; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Concrete | 9/19/2006 | 9/20/2006 | 9/20/2006 | A | PART |
Tony Young
|
|
|
ross; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles pending s. i. report
|
BLD-Other | 8/15/2006 | 8/16/2006 | 8/16/2006 | A | PART |
Dave Hannah
|
|
|
russ Note: grid ceiling 3rd floor; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to cover 3rd floor ceiling after elec oks
|
BLD-Framing/Rough-in | 8/11/2006 | 8/11/2006 | 8/11/2006 | P | PART |
Tony Young
|
|
|
ross - rebar insp (placement at 10:30); Phone #: ###-#### Internet Inspection Request from: Barbara Buckley area #2 and #6 ok
|
BLD-Framing/Rough-in | 8/8/2006 | 8/9/2006 | 8/9/2006 | A | PART |
Tony Young
|
|
|
above the ceiling insp - lisa or cell ###-#### ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok pending trades
|
PubWorks Subgrade Approval | 7/17/2006 | 7/17/2006 | 7/17/2006 | | PART |
|
|
|
Subgrade for footings for the upper most level of the patio/deck have been approved by the geotechnical engineer.
|
BLD-Framing/Rough-in | 6/22/2006 | 6/23/2006 | 6/23/2006 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/22/2006 at 1:36:52 PM. Contact: ###-####. remainder of 3rd floor ok
|
BLD-Framing/Rough-in | 6/7/2006 | 6/7/2006 | 6/7/2006 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/7/2006 at 6:50:27 AM. Contact: ###-####. north side of 3rd floor ok pending
|
BLD-Framing/Rough-in | 6/1/2006 | 6/2/2006 | 6/2/2006 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 6/1/2006 at 2:23:09 PM. Contact: ###-####. main level walls ok pending trades
|
BLD-Framing/Rough-in | 5/26/2006 | 5/26/2006 | 5/26/2006 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 5/26/2006 at 9:25:04 AM. Contact: ###-####. 2nd floor walls ok to cover
|
BLD-Wall cover | 4/28/2006 | 5/1/2006 | 5/1/2006 | A | PASS |
Tony Young
|
|
|
drywall on exterior; Phone #: ###-####
|
BLD-Wall cover | 4/27/2006 | 4/28/2006 | 4/28/2006 | A | CANC |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 4/27/2006 at 11:26:50 AM. Contact: ###-####. rescheduled for monday am
|
BLD-Conference | 4/21/2006 | 4/21/2006 | 4/21/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 4/21/2006 at 7:32:31 AM. Contact: ###-####. Need tech data on Hilti fire rated foam for application used on the 1 hr. floor ceiling assembly.
|
BLD-Framing/Rough-in | 4/11/2006 | 4/12/2006 | 4/12/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 4/11/2006 at 1:05:31 PM. Contact: ###-####. Performed walk thru with general contractor and discussed general items regarding the floor ceiling assemblies, egress stairway. wip. Noted that steel beams are being wrapped with double layer 1/2'' rock and being capped with 5/8 type X as per details. Also reveiwed UL listing requirements for rated penetrations.
|
Plan resubmittals received | | | 3/3/2006 | | |
|
|
|
|
(F) Reprint permit | | | 2/28/2006 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 2/28/2006 | | |
|
|
|
|
OVERRIDE | | | 2/17/2006 | | |
|
|
|
|
Print Occupancy Form | | | 2/17/2006 | | DONE |
|
|
|
|
Telephone call | | | 2/17/2006 | | DONE |
|
|
|
Left message with Dennis Robinson (CM Company) ###-#### to pick up permit2-17-06 eus
|
Print Occupancy Form | | | 2/17/2006 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 2/17/2006 | | |
|
|
|
|
Override - Parcel Holds | | | 2/17/2006 | | |
|
|
|
|
Permit Ready to Issue | | | 2/17/2006 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 2/7/2006 | 2/7/2006 | 2/15/2006 | | PASS |
|
|
|
2/15/2006 14:37:52 MLO - activity updated through activity BLDA022 from case BLD05-02015.
|
Routing - PLAN CHECK | 2/8/2006 | | 2/15/2006 | | PASS |
|
|
|
Ok w/o further fire reviews per S. Rogers 2/15/2006. MLO
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/15/2006 | | |
|
|
|
|
Plan Modification Accepted | | | 2/7/2006 | | |
|
|
|
Plan modification excepted for Bld05-02015 for the redeisgn of the first floor individual office to a open work area, Corridor relocated between East hall of locker room, mech, electrical and the open office area on sheets A2.11, A2.21, A2.31, A2.51, M2.11, P2.11, E2.11f, E2.11l, E2.11p, E2.11s. Routed to Mike Otto.
|
BLD-Concrete | 1/18/2006 | 1/19/2006 | 1/19/2006 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 1/18/2006 at 7:32:21 AM. Contact: ###-####. upper ftg,, s.i . will be on site
|
BLD-Concrete | 1/18/2006 | 1/18/2006 | 1/18/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/18/2006 at 7:31:27 AM. Contact: ###-####. Welded wire mesh for interior slab on grade. wip.
|
BLD-Concrete | 1/5/2006 | 1/6/2006 | 1/6/2006 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 1/5/2006 at 2:28:07 PM. Contact: ###-####. wip,, s. i. on site
|
BLD-Concrete | 12/29/2005 | 12/29/2005 | 12/29/2005 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 12/29/2005 at 9:26:26 AM. Contact: ###-####. NW wall. Only one mat tied. Special inspector to inspect when complete.
|
BLD-Footing | 12/16/2005 | 12/19/2005 | 12/19/2005 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/16/2005 at 9:46:22 AM. Contact: ###-####. ok pending s. i. report
|
PubWorks Subgrade Approval | 12/16/2005 | 12/16/2005 | 12/16/2005 | | PART |
|
|
|
footing subgrade approved for Line B from line 4 to 10; Line C from line 8 to 10; and isolated column footings at the intersection of Lines A from 4 to 5 and at 6,7 and 8
|
BLD-Concrete | 12/6/2005 | 12/7/2005 | 12/7/2005 | A | PART |
Tony Young
|
|
|
ross; Phone #: ###-#### Internet Inspection Request from: Barbara Moore pending s. i. report
|
BLD-Footing | 11/30/2005 | 12/1/2005 | 12/1/2005 | A | CANC |
Tony Young
|
|
|
ross tucker; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa canc. due to snow
|
PubWorks Subgrade Approval | 11/23/2005 | 11/23/2005 | 11/23/2005 | | PART |
|
|
|
SUBGRADE OKAY FROM I LINE FROM GRID LINES 2 AND 11 AND LINES 10 AND 11 FROM I TO E
|
BLD-Footing | 11/21/2005 | 11/22/2005 | 11/22/2005 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 11/21/2005 at 4:36:25 PM. Contact: ###-####. stair area ok,, from steet/parking lot area
|
BLD-Footing | 11/18/2005 | 11/21/2005 | 11/21/2005 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 11/18/2005 at 1:35:38 PM. Contact: ###-####. retaining wall ftgs,, 5ftw 12"deep,, pending s. i. report
|
PubWorks Subgrade Approval | 11/7/2005 | 11/7/2005 | 11/7/2005 | | PART |
|
|
|
Footing subgrade approved for K line, the upper footing, from grid lines 1 and 10.
|
Issue PAID IN FULL permit | | | 10/7/2005 | | DONE |
|
|
|
|
CHANGE ISSUED DATE | | | 10/7/2005 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 7/26/2005 | | 10/6/2005 | | PASS |
|
|
|
10/6/2005 10:46:05 MLO - activity updated through activity BLDA022 from case BLD05-02015.
|
Case Summary (BLD) | | | 10/6/2005 | | |
|
|
|
|
Routing - PLAN CHECK | 10/6/2005 | | 10/6/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/6/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/6/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/6/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/6/2005 | | DONE |
|
|
|
|
Telephone call | | | 10/6/2005 | | DONE |
|
|
|
###-#### called and left message for Andy w/Caroline that permit is ready and fees
|
Routing - FIRE | 9/19/2005 | | 10/5/2005 | | PASS |
|
|
|
resubmittal acceptable. Revised review emailed to architect.
|
Routing Off Site - STRUCTURAL | 10/3/2005 | | 10/4/2005 | | PASS |
|
|
|
Called PDQ for pick up
|
Plan resubmittals received | | | 9/30/2005 | | |
|
|
|
Received (3) copies of supplemental structural calcs. Routed to Mike O.
|
Routing Off Site - STRUCTURAL | 9/26/2005 | | 9/29/2005 | | FAIL |
|
|
|
Called PDQ for pick up
|
Plan resubmittals requested | | | 9/29/2005 | | DONE |
|
|
|
structural corrections
|
Plan resubmittals received | | | 9/22/2005 | | DONE |
|
|
|
Received Transmittal, 3 Memorandums, & 3 Copys of sheets S2.2,S5.2,S7.2,S7.3,S7.4 Taken to Mike O.
|
Plan resubmittals requested | | | 9/19/2005 | | DONE |
|
|
|
additional structural comments
|
Routing - PLAN CHECK | 9/16/2005 | | 9/19/2005 | | PEND |
|
|
|
Pending structural approval
|
Routing Off Site - STRUCTURAL | 9/8/2005 | | 9/19/2005 | | FAIL |
|
|
|
Called PDQ for pick up corrections sent to architect. MLO
|
Plan resubmittals received | | | 9/15/2005 | | DONE |
|
|
|
Received 3 Copys of letter to Mike Otto, & 3 Copys of sheets P2.11,P2.12,P2.13 Taken to Mike O.
|
1st review completed | | | 9/8/2005 | | FAIL |
|
|
|
failed structural, plan check and fire.
|
Routing - PLAN CHECK | 9/8/2005 | | 9/8/2005 | | PEND |
|
|
|
|
Routing - FIRE | 8/24/2005 | | 9/8/2005 | | FAIL |
|
|
|
review faxed to architect.
|
Plan resubmittals received | | | 8/31/2005 | | DONE |
|
|
|
Received Transmittal, 3 Memorandums, & 3 Copys of sheets S0.1,S1.1,S2.1,S2.2,S2.3,S3.1,S5.1S5.2,S7.1,S7.3S7.4 Taken to Mike O.
|
Routing - PLAN CHECK | 8/10/2005 | | 8/24/2005 | | FAIL |
|
|
|
corrections sent to architect -unable to fax-errors.
|
Routing Off Site - STRUCTURAL | 8/3/2005 | | 8/24/2005 | | FAIL |
|
|
|
Called PDQ for pick up
|
Plan resubmittals requested | | | 8/24/2005 | | DONE |
|
|
|
IBC corrections
|
Routing - PLANNING | 8/2/2005 | | 8/9/2005 | | PASS |
|
|
|
Approved for Design Review (completed on 8/04/05); pending review by Angela Wood (routed to her office on 8/04/05) for compliance with conditional use. Pass AW.
|
Routing - PLUMBING | | | 8/2/2005 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - PUBLIC WORKS | 7/26/2005 | | 8/1/2005 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 7/28/2005 | | 7/29/2005 | | PASS |
|
|
|
Terry R.
|
Plans ACCEPTED BY PLAN TECH | | | 7/26/2005 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 7/26/2005 | | |
|
|
|
|
Routing - PLANNING Land Div | 7/26/2005 | | 7/26/2005 | | PASS |
|
|
|
Approved, legal parcel.
|
Application received | | | 7/22/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/22/2005 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 7/26/2005 | | 8/24/2004 | | FAIL |
|
|
|
corrections sent to architect
|
Fee Review-notes | 7/22/2005 | 7/22/2005 | | | |
|
|
|
|
Routing - Erosion and Sediment | 8/1/2005 | | | | |
|
|
|
|