Second Notice BLD | 8/11/2008 | 8/11/2008 | 8/12/2008 | | DONE |
Darla L Downs
|
|
|
First Notice has not been responded to.
|
First Notice | | 7/29/2008 | 8/11/2008 | | DONE |
|
|
|
|
Telephone call | | | 7/29/2008 | | DONE |
Barbara Stitt
|
|
|
Per phone call with Carol Montgomery on 7-29-08 @ 11:20am this is ok to give perm occupancy as this project is complete///7/29/08 @ 11:24am BAS
|
Permanent Occupancy | | | 7/29/2008 | | DONE |
Barbara Stitt
|
|
|
Already recieved perm occupancy approval on 6-9-06 I just finished up the computer part///7-29-08 pdf
|
BLD-Conference | 2/19/2008 | 2/20/2008 | 2/20/2008 | A | PEND |
Jim Sly
|
|
|
Talked to ? @ ###-####......Will check later to verify permits picked up.
|
BLD-Aging Inspection | 2/18/2008 | 2/18/2008 | 2/19/2008 | | PEND |
Jim Sly
|
|
|
Called Nate......left V/M
|
PubWorks Occupancy Approval | 6/26/2006 | 6/26/2006 | 6/26/2006 | | DONE |
|
|
|
|
BLD-Final | 6/8/2006 | 6/9/2006 | 6/9/2006 | A | PASS |
Jim Sly
|
|
|
nate; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie OK for Perm Occ
|
Permanent Occupancy | | 6/9/2006 | 6/9/2006 | | DONE |
|
|
|
|
FIRE-Final Inspection | 6/5/2006 | 6/6/2006 | 6/6/2006 | A | PASS |
Troy Cobbley
|
|
|
nate ; Phone #: ###-#### Life safety passed.
|
BLD-Final | 6/2/2006 | 6/5/2006 | 6/5/2006 | A | NR |
Jim Sly
|
|
|
nate; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley Need fire
|
FIRE-Final Inspection | 5/18/2006 | 5/23/2006 | 5/24/2006 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
FIRE-Final Inspection | 5/17/2006 | 5/18/2006 | 5/18/2006 | A | CANC |
Troy Cobbley
|
|
|
Wrong inspection called in. See underground sprinkler permit for correct entry
|
FIRE-Final Inspection | 12/5/2005 | 12/6/2005 | 12/6/2005 | P | FAIL |
Troy Cobbley
|
|
|
I spoke to Nate about needing resubmittals for the fire alarm and first time submittals for the overhead sprinkler system. No items inspected.
|
Telephone call | | | 10/20/2005 | | DONE |
|
|
|
Talked w/Nate (superintendant) re: status of temp. occ. they are continuing to move forward
|
Plan resubmittals received | | | 9/22/2005 | | DONE |
|
|
|
Received 1 Transmittal ,1 United Water Flow Sheet dated 9/7/05 showing available flow of 3,000 gpm; doesn't inlcude static pressure which is required for sprinkler design.
|
FIRE-Final Inspection | 9/6/2005 | 9/6/2005 | 9/7/2005 | P | PART |
Forrest France
|
|
|
A temporary occupancy was granted with Dave Hanneman's permission. Life safety items remaining are to provide permanent curb painting for the fire lane, provide a letter indicating min. available flow for the fire sprinkler system, remove conflicting address numbers at the back of the building, final the fire alarm permit.
|
Temporary occupancy | | | 9/7/2005 | | DONE |
|
|
|
Temp. Occ. Cert. # 5267 issued 9-7-05 to Rolling Hlls Charter School.
|
Plan resubmittals received | | | 9/7/2005 | | DONE |
|
|
|
fire flow information from United Water resubmitted by architect, indicating 3,000 gpm available; adequate for fire flow. No static pressure was indicated for sprinkler calc purposes.
|
Case Summary (BLD) | | | 9/7/2005 | | |
|
|
|
|
Telephone call | | | 9/7/2005 | | DONE |
Bill Alexander
|
|
|
Contacted Scott Steed (superintendent) @ ###-#### (now at Kowalis and Mackay), indicating they need to get a fire permit for the overhead fire sprinkler system in this modular structure, through a licensed fire sprinkler contractor (immediately). His response after questioning why, was OK.
|
BLD-Final | 9/2/2005 | 9/6/2005 | 9/6/2005 | P | PART |
Jim Sly
|
|
|
nate; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles OK for Temp....Need Perm Occ from Fire and Structural with in 90 days.
|
Case Summary (BLD) | | | 9/6/2005 | | DONE |
|
|
|
|
BLD-Final | 9/2/2005 | 9/2/2005 | 9/2/2005 | P | NR |
Jim Sly
|
|
|
nate; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
FIRE-Final Inspection | 9/1/2005 | 9/2/2005 | 9/2/2005 | P | FAIL |
Forrest France
|
|
|
Numerous code deficiencies include door hardware, fire sprinkler system, hydrant flow, sprinkler flow, fire lane marking, non functional exit signs and emergency lights, and fire alarm permit final, need to be addressed prior to approval. A correction notice with a non-comprehensive list was left at the site with Nate Hosac.
|
BLD-Foundation | 8/31/2005 | 9/1/2005 | 9/2/2005 | A | PASS |
Jim Sly
|
|
|
christine; Phone #: ###-#### Internet Inspection Request from: Barbara Moore C/N posted for framing
|
BLD-Foundation | 8/29/2005 | 8/30/2005 | 8/30/2005 | A | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/29/2005 at 1:37:31 PM. Contact: ###-####. C/N Need address #s Need plans Arch to address wood/conc contact...... South of West YMCA
|
(F) Reprint permit | | | 8/19/2005 | | |
|
|
|
|
Override - Parcel Holds | | | 8/17/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/17/2005 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 7/27/2005 | | 8/9/2005 | | PASS |
|
|
|
8/9/2005 10:19:43 MLO - activity updated through activity BLDA022 from case BLD05-02034.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/9/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/9/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/9/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/9/2005 | | DONE |
|
|
|
|
Telephone call | | | 8/9/2005 | | DONE |
|
|
|
called wes steele ###-#### left voicemail permit is ready and fees
|
Routing - FIRE | 8/3/2005 | | 8/8/2005 | | PASS |
|
|
|
Approved with conditions. Review comments faxed to architect.
|
1st review completed | | | 8/8/2005 | | FAIL |
|
|
|
failed plumbing and Public works.
|
Routing - PLAN CHECK | 8/1/2005 | | 8/2/2005 | | PASS |
|
|
|
Mike O.
|
Routing - PLANNING | 7/29/2005 | | 8/1/2005 | | PASS |
|
|
|
CUP Pass (Angela Wood)
Okay per DRH05-00247. Site must include landscaping required by the design review approval. (Cody Riddle)
|
Routing - Erosion and Sediment | 7/28/2005 | | 7/29/2005 | | PASS |
|
|
|
ESC waiver request approved with attached conditions.
|
Routing - PLANNING Land Div | 7/29/2005 | | 7/29/2005 | | PASS |
|
|
|
Pass. Lot 5, Block 15 of Research Center No. 7
|
Plan resubmittals received | | | 7/29/2005 | | |
|
|
|
Received (7) copies of sheet A1 and (6) copies of sheet L1. Routed to Marleen S.
|
Routing - PUBLIC WORKS | 7/29/2005 | | 7/29/2005 | | PASS |
|
|
|
Rerouting to PW to review sewer line resubmittals.
|
Routing - PLUMBING | 7/29/2005 | | 7/29/2005 | | PASS |
|
|
|
Rerouting to Plumbing to review resubmittals received on this 7/29/05. per resubmitted plans dated 7/29/05 and 2003 upc
|
Routing - PUBLIC WORKS | 7/27/2005 | | 7/28/2005 | | FAIL |
|
|
|
Failed by Jim Pardy, contact number ###-####
Each building is required to separately connect to public sewer per Boise City code.
|
Routing - PLUMBING | 7/28/2005 | | 7/28/2005 | | FAIL |
|
|
|
united water and public works will require a service line or meter to each building. provide a plan showing separate sewer and water services to each building.
|
Plans ACCEPTED BY PLAN TECH | | | 7/27/2005 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 7/27/2005 | | |
|
|
|
|
Application received | | | 7/26/2005 | | |
|
|
|
|