Unit C - To install a 440 sq. ft. one story modular office building with a new pier foundation with holdowns and new ramps and stairs. Other work includes all site improvements and landscaping per approved plans and attachments, DRH05-00247, CUP05-00061. SEE ESC05-01261 & PWK05-03770 Idaho State Tag # 8341CC
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD7/7/20067/7/20068/18/2006 DONE
First Notice has not been responded to.
First Notice 6/19/20067/7/2006 DONE
Permanent occupancy  6/19/2006 DONE
Perm. Occ. Cert. # 11087 issued 6-19-06 to the Rolling Hills Charter School, Bldg. # C.
Permanent Occupancy 6/16/20066/16/2006 DONE
Details
BLD-Final6/8/20066/9/20066/9/2006APASS
DetailsJim Sly
nate; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
OK for Perm Occ.
FIRE-Final Inspection6/5/20066/6/20066/6/2006APASS
DetailsTroy Cobbley
Life safety passed.
BLD-Final6/2/20066/5/20066/5/2006ANR
DetailsJim Sly
nate; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley
Need fire
FIRE-Final Inspection12/5/200512/6/200512/6/2005PFAIL
DetailsTroy Cobbley
I spoke to Nate about needing resubmittals for the fire alarm and first time submittals for the overhead sprinkler system. No items inspected.
Plan resubmittals received  9/22/2005 DONE
Received 1 Transmittal ,1 United Water Flow Sheet dated 9/7/05 showing available flow of 3,000 gpm; doesn't inlcude static pressure which is required for sprinkler design.
FIRE-Final Inspection9/6/20059/6/20059/7/2005PDONE
DetailsForrest France
Duplicate inspection already scheduled by the contractor.
FIRE-Final Inspection9/6/20059/6/20059/7/2005PPART
DetailsForrest France
Need to remove manual thumbturns at the main entry/exit doors. A temporary occupancy was granted with Dave Hanneman's permission.
Temporary occupancy  9/7/2005 DONE
Temp. Occ. Cert. # 5269 issued 9-7-05 to the Rolling Hills Charter School.
BLD-Final9/2/20059/6/20059/6/2005PPART
DetailsJim Sly
nate; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
OK for Temp Occ. Need Fire and Struct Perm Occ. within 90 days
Case Summary (BLD)  9/6/2005 DONE
BLD-Final9/2/20059/2/20059/2/2005PNR
DetailsJim Sly
nate; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
FIRE-Final Inspection9/1/20059/2/20059/2/2005PFAIL
DetailsForrest France
Manual thumbturns are not allowed on the main entry /exit doors, provide a fire ext., repair emergency light.
BLD-Foundation8/31/20059/1/20059/1/2005APASS
DetailsJim Sly
christine; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
Note: C/N for framing
BLD-Foundation8/29/20058/30/20058/30/2005ANR
DetailsJim Sly
Scheduled by a contractor via Hello! on 8/29/2005 at 1:38:49 PM. Contact: ###-####.
C/N Need appr plan address #'s Architect to address wood/concrete contact...
(F) Reprint permit  8/19/2005  
Override - Parcel Holds  8/17/2005  
Issue PAID IN FULL permit  8/17/2005 DONE
Plan assigned to (MLO)7/27/2005 8/9/2005 PASS
8/9/2005 10:21:02 MLO - activity updated through activity BLDA022 from case BLD05-02037.
PLANS/APPL TAKEN TO FRONT DESK  8/9/2005 DONE
Inspection Record Card- Bld  8/9/2005 DONE
Print Occupancy Form  8/9/2005 DONE
Permit Ready to Issue  8/9/2005 DONE
Telephone call  8/9/2005 DONE
called wes steele ###-#### left voicemail permit is ready and fees
Routing - FIRE8/3/2005 8/8/2005 PASS
review comments faxed to architect.
1st review completed  8/8/2005 FAIL
failed plumbing and public works.
Routing - PLAN CHECK8/1/2005 8/3/2005 PASS
Routing - PLANNING7/29/2005 8/1/2005 PASS
CUP Pass (Angela Wood)

Okay per DRH05-00247. Site must include landscaping required by the design review approval. (Cody Riddle)
Plan resubmittals received  7/29/2005  
Received (7) copies of sheet A1 and (6) copies of sheet L1. Routed to Marleen S.
Routing - PUBLIC WORKS7/29/2005 7/29/2005 PASS
Rerouting to PW to review sewer line resubmittals.
Routing - PLUMBING7/29/2005 7/29/2005 PASS
Rerouting to Plumbing to review resubmittals received on this 7/29/05.per resubmitted plans and 2003 upc
Routing - Erosion and Sediment7/28/2005 7/29/2005 PASS
ESC waiver request approved with attached conditions.
Routing - PLANNING Land Div7/29/2005 7/29/2005 PASS
Lot 5, Block 15 Research Center No. 7
Routing - PUBLIC WORKS7/27/2005 7/28/2005 FAIL
Failed by Jim Pardy, contact number ###-####.

Each building is required to be separately connected to public sewer per Boise City code.
Routing - PLUMBING7/28/2005 7/28/2005 FAIL
see bld05-02034 for review comments.
Plan routing begun/NEW & ADDTN  7/27/2005  
Plans ACCEPTED BY PLAN TECH  7/27/2005  
Application received  7/26/2005  
Third Notice BLD8/18/20068/18/2006   
Second Notice has not been responded to.