BLD-Conference | 3/31/2006 | 3/31/2006 | 3/31/2006 | P | PASS |
Dave Hannah
|
|
|
###-#### - ERIC nOTE: STAIRWAYS
|
BLD-Final | 3/7/2006 | 3/7/2006 | 3/7/2006 | P | PART |
Dave Hannah
|
|
|
eric Note: please call 1/2 hr prior to inspection; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles needs to get permit changed
|
BLD-Footing | 12/15/2005 | 12/16/2005 | 12/16/2005 | P | PART |
Dave Hannah
|
|
|
ROBERT; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles concrete lid ok to pour
|
BLD-Footing | 11/3/2005 | 11/3/2005 | 11/4/2005 | P | PART |
Dave Hannah
|
|
|
robert Note: rebar ins; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles this was afoundatipon wall on new part of addnion ok to place concrete
|
BLD-Conference | 10/10/2005 | 10/11/2005 | 10/11/2005 | A | PART |
Dave Hannah
|
|
|
please call 30min prior to meet you//robert shaw; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa dimpled drain covering installed backwards but still ok as damp proofing
|
BLD-Footing | 9/15/2005 | 9/15/2005 | 9/16/2005 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/15/2005 at 8:32:22 AM.
|
BLD-Footing | 9/6/2005 | 9/6/2005 | 9/6/2005 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 9/6/2005 at 9:08:22 AM. Contact: ###-####. section under old part of house ok to pour
|
Plan assigned to (SRZ) | 7/27/2005 | 7/27/2005 | 7/28/2005 | | PASS |
|
|
|
7/28/2005 16:16:57 SRZ - activity updated through activity BLDA022 from case BLD05-02044.
|
Case Summary (BLD) | | | 7/28/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/28/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/28/2005 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/28/2005 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 7/27/2005 | | PASS |
|
|
|
Pending Engineering. (SRZ)
|
Application received | | | 7/27/2005 | | |
|
|
|
|