BLD-Final | 9/15/2006 | 9/15/2006 | 9/15/2006 | P | PASS |
Jim Storey
|
|
|
tom; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley floor elavated to meet c/n.
|
DOC - Permit Finaled | 9/15/2006 | 9/15/2006 | 9/15/2006 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 9/14/2006 | 9/14/2006 | 9/14/2006 | P | FAIL |
Jim Storey
|
|
|
tom ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie 44 '' max silheight bedroom window.
|
BLD-Final | 9/13/2006 | 9/13/2006 | 9/13/2006 | P | NR |
Jim Storey
|
|
|
tom ; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley need fireplace final.
|
BLD-Energy code compliance | 4/24/2006 | 4/24/2006 | 4/24/2006 | P | PASS |
Jim Storey
|
|
|
tom ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 4/18/2006 | 4/19/2006 | 4/19/2006 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/18/2006 at 2:13:14 PM. Contact: ###-####. ok to insulate
|
BLD-Energy code compliance | 4/6/2006 | 4/6/2006 | 4/6/2006 | A | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/6/2006 at 6:04:20 AM. Contact: ###-####. nr
|
BLD-Footing | 9/27/2005 | 9/27/2005 | 9/27/2005 | P | PASS |
Jim Storey
|
|
|
brent; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
Issue PAID IN FULL permit | | | 9/19/2005 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 7/28/2005 | 8/23/2005 | 9/16/2005 | | PASS |
|
|
|
9/16/2005 09:09:49 SAM - activity updated through activity BLDA022 from case BLD05-02068.
|
Routing - PLAN CHECK | 8/3/2005 | | 9/16/2005 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 9/16/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/16/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/16/2005 | | |
|
|
|
|
Permit Ready to Issue | | | 9/16/2005 | | DONE |
|
|
|
|
Telephone call | | | 9/16/2005 | | |
|
|
|
called ###-#### and left voicemessage for John that permit is ready and fees
|
Plan Reviewer's activity | | | 9/15/2005 | | DONE |
|
|
|
John Nine brought in roof framing plan and beam plan on 9/14/05. Roof truss profiles are for a different lot. I called John at 06:45 on 9/15/05 and let him know that I have the truss engineering for lot 7 block 1. Plans are still on hold.
|
Plan Reviewer's activity | | | 8/30/2005 | | DONE |
|
|
|
14:00 I recieved a call from Jon Nine. He informed me that the house will be changing and that he will need to re-submit new plans. Plan are on hold and two plan reviews will need to be assessed.
|
Plan Reviewer's activity | | | 8/24/2005 | | DONE |
|
|
|
08:20 I called and talked to Jon about needing more information before the plans can be issued. I need wall bracing to be shown for each floor and the 18' garage door header needs to be engineered with maybe the footings. Plans are on hold.
8/29/05 I received resubmittals from the builder EXCEPT for the truss engineering for the girder and trusses over the garage.
|
Routing - PLANNING | 7/29/2005 | | 8/3/2005 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/29/2005 | | 7/29/2005 | | PASS |
|
|
|
|
Application received | | | 7/28/2005 | | |
|
|
|
|