Third Notice BLD | 8/18/2006 | 8/18/2006 | 9/15/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 7/7/2006 | 7/7/2006 | 8/18/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 5/17/2006 | 5/17/2006 | 7/7/2006 | | DONE |
Mike Jordan
|
|
|
|
BLD-Aging Inspection | 5/17/2006 | 5/17/2006 | 5/17/2006 | | PASS |
Troy Cobbley
|
|
|
Fire alarm permit has been finaled. This permit ok for perm occupancy
|
DOC - Permit Finaled | 5/17/2006 | 5/17/2006 | 5/17/2006 | A | PASS |
Mike Jordan
|
|
|
Fire alarm has been finaled off on the MIS permit. C/O has been issued for the vanilla finish.
|
FIRE-Final Inspection | 3/15/2006 | 3/16/2006 | 3/16/2006 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the fire alarm plans have been approved and inspected. Also a MIS permit will be required for the new tenant.
|
FIRE-Final Inspection | 1/25/2006 | 1/26/2006 | 1/26/2006 | A | FAIL |
Troy Cobbley
|
|
|
Fire alarm modifications are required as per review comment #18, need to test exit lights and emergency lights
|
BLD-Other | 11/29/2005 | 11/30/2005 | 11/30/2005 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/29/2005 at 2:01:31 PM. Contact: ###-####. ceiling grid.
|
BLD-Conference | 11/29/2005 | 11/30/2005 | 11/30/2005 | A | DONE |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/29/2005 at 2:00:53 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 9/29/2005 | 9/30/2005 | 9/30/2005 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 9/29/2005 at 4:01:12 PM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 8/19/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/18/2005 | | DONE |
|
|
|
|
Telephone call | | | 8/18/2005 | | DONE |
|
|
|
called Cornell Larson ###-#### told him permit is ready and fees
|
1st review completed | | | 8/17/2005 | | FAIL |
|
|
|
Failed plan check
|
Routing - PLAN CHECK | 8/17/2005 | | 8/17/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/17/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/17/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/17/2005 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 8/2/2005 | | 8/17/2005 | | PASS |
|
|
|
8/17/2005 15:54:13 RMH - activity updated through activity BLDA022 from case BLD05-02069.
|
Routing - FIRE | 8/8/2005 | | 8/17/2005 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/11/2005 | | |
|
|
|
Received (3) copies of sheet A-2. Routed to Ron H.
|
Routing - PLAN CHECK | 8/3/2005 | | 8/8/2005 | | FAIL |
|
|
|
Faxed requirements to the architect on 8/8/05 / Routed plans to fire on same day.
|
Case Summary (BLD) | | | 8/5/2005 | | |
|
|
|
|
Case Summary (BLD) | | | 8/5/2005 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 8/2/2005 | | 8/3/2005 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/29/2005 | | |
|
|
|
|
Application received | | | 7/28/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/28/2005 | | |
|
|
|
|
Fee Review-notes | 7/28/2005 | 7/28/2005 | | | |
|
|
|
|