Third Notice BLD | 1/8/2007 | 1/8/2007 | 1/31/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 9/25/2006 | 9/25/2006 | 1/8/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 9/5/2006 | 9/25/2006 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/5/2006 | 9/5/2006 | 9/5/2006 | P | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
Permanent occupancy UNPAID FEE | | | 9/5/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11199 issued 9-5-06 to Johnstone Supply.
|
BLD-Final | 8/31/2006 | 9/1/2006 | 9/1/2006 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Internet Inspection Request from: Mike Walling. Temp occ given. Will be ok for perm occ once lise/safety and fire sprinkler has been finaled.
|
FIRE-Final Inspection | 9/1/2006 | 9/1/2006 | 9/1/2006 | P | PART |
Forrest France
|
|
|
Final pending provision for correct sprinkler coverage at the level of exit discharge at two stairways.
|
Permanent Occupancy | | 9/1/2006 | 9/1/2006 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/24/2006 | 8/25/2006 | 8/25/2006 | A | FAIL |
Troy Cobbley
|
|
|
Life safety ok to final when fire alarm and fire sprinkler permits are finaled.
|
PubWorks Occupancy Approval | 8/17/2006 | 8/17/2006 | 8/17/2006 | | DONE |
|
|
|
|
BLD-Other | 8/15/2006 | 8/16/2006 | 8/16/2006 | A | PASS |
Tom Arcoraci
|
|
|
High-Piled storage rack mounting inspection; Phone #: ###-#### Internet Inspection Request from: Mike Walling bolts ok
|
FIRE-Conference | 7/21/2006 | 7/24/2006 | 7/24/2006 | A | DONE |
Troy Cobbley
|
|
|
I went over the life safety items with Mike.
|
BLD-Energy code compliance | 7/17/2006 | 7/18/2006 | 7/18/2006 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 7/17/2006 at 11:49:48 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 7/7/2006 | 7/11/2006 | 7/11/2006 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Internet Inspection Request from: Mike Walling. Interior framing.
|
BLD-Conference | 6/22/2006 | 6/23/2006 | 6/23/2006 | A | PART |
Mike Jordan
|
|
|
Framing/Structural Inspection; Phone #: ###-#### Internet Inspection Request from: Mike Walling. Reviewed special insp. reports, and inspected partial framing at future elev. shaft.
|
BLD-Other | 5/17/2006 | 5/18/2006 | 5/18/2006 | P | DEFR |
Mike Jordan
|
|
|
###-#### - mike Note: welding
|
BLD-Aging Inspection | 5/17/2006 | 5/17/2006 | 5/17/2006 | | PASS |
Mike Jordan
|
|
|
wip
|
BLD-Concrete | 3/10/2006 | 3/13/2006 | 3/13/2006 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/10/2006 at 8:14:13 AM. Contact: ###-####. Reinforcement for tilt panels. Also verified that missing bar from last inspection was installed per special inspection report.
|
BLD-Concrete | 2/20/2006 | 2/21/2006 | 2/21/2006 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/20/2006 at 3:26:52 PM. Contact: ###-####. Tilt panels. Noted missing rebar on t hree panels. Special inspector to verify install of missing bar.
|
BLD-Footing | 1/27/2006 | 1/30/2006 | 1/30/2006 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/27/2006 at 3:23:37 PM. Contact: ###-####. east and south footings.
|
BLD-Footing | 1/25/2006 | 1/26/2006 | 1/26/2006 | A | PASS |
Mike Jordan
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. Interior column pad footings. Contractor is getting special inspections.
|
Permit Ready to Issue | | | 1/19/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/19/2006 | | DONE |
|
|
|
|
Telephone call | | | 1/19/2006 | | |
|
|
|
lft ms with secretary that plan review is ready to be picked up ###-####
|
CHANGE STATUS TO (ISS) | | | 1/19/2006 | | DONE |
|
|
|
|
(F) Reprint permit | | | 1/19/2006 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 1/3/2006 | | 1/12/2006 | | PASS |
|
|
|
1/12/2006 10:46:07 JCM - activity updated through activity BLDA022 from case BLD05-02089.
|
Routing - PLAN CHECK | 1/11/2006 | | 1/12/2006 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 1/12/2006 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/12/2006 | | DONE |
|
|
|
|
Routing - FIRE | 1/5/2006 | | 1/11/2006 | | PASS |
|
|
|
Plan mod approved to provide ESFR sprinklers in lieu of smoke and heat vents in warehouse.
|
Routing - PLAN CHECK | 1/3/2006 | | 1/5/2006 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 1/5/2006 | | PASS |
|
|
|
The plans were reviewed and approved for structural and nonstructural modifications. The approved, issued plans have been modified by revising some some of the concrete tilt-up wall for easier erection, the roofing material was modified, the shaft fire-resistive construction was deleted and the proposed sprinkler system type was changed to ESFR sprinklers to allow the deletion of the proposed smoke and heat vents. JCM
|
Plan resubmittals received | | | 12/29/2005 | | DONE |
|
|
|
PLAN MODIFICATION PLANS RECEIVED and forwarded to John Menard to determine routing. Three (3) copies of the revised structural calculations, and (3) copies of the following plan sheets: A-1, A-1.1, A-2, A-3, A-4, A-4.1, A-5, A-6, A-7, A-8, A-9, A-15, S-1, S-2, S-3, S-4, S-5.1, S-6, S-7, S-8, S-9, S-10, S-11 and S-12.
|
(F) Reprint permit | | | 12/6/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 12/5/2005 | | DONE |
|
|
|
|
Telephone call | | | 9/30/2005 | | DONE |
|
|
|
called ###-#### and told Lisa w/ Russell Corp. that permit is ready and fees and need ACHD reciept
|
Plan assigned to (JCM) | 8/4/2005 | 8/4/2005 | 9/28/2005 | | PASS |
|
|
|
9/28/2005 09:15:24 JCM - activity updated through activity BLDA022 from case BLD05-02089.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/28/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/28/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/28/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/28/2005 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 9/23/2005 | | 9/28/2005 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/28/2005 | | 9/28/2005 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 8/30/2005 | | 9/23/2005 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 9/14/2005 | | 9/15/2005 | | PASS |
|
|
|
Reviewed and approved final structural resubmittals. JCM
|
Plan resubmittals received | | | 9/14/2005 | | DONE |
|
|
|
Received 1 Letter, 3 Response to Structural, & 3 Copys of sheets S-4.1,S-7,S-8,S-9,S-10 Taken to John M.
|
Plan Reviewer's activity | | | 9/8/2005 | | PASS |
|
|
|
Reviewed and approved resubmitted plans. JCM
|
Routing Off Site - STRUCTURAL | 8/30/2005 | | 9/7/2005 | | FAIL |
|
|
|
Received an e-mailed comment list from the consulting structural engineer requesting additional revisions. JCM
|
Plan resubmittals requested | | | 9/7/2005 | | DONE |
|
|
|
E-mailed the architect a copy of the second structural review requesting additional clarification. JCM
|
Plan resubmittals received | | | 9/6/2005 | | |
|
|
|
Received (3) copies of sheet A-1, A-1.1, A-4, A-4.1, A-6, A-7, A-12, A-14, EN-1 adn E2.2L. Routed to John M.
|
1st review completed | | | 8/30/2005 | | FAIL |
|
|
|
failed public works, structural, plan review.
|
Routing - FIRE | 8/18/2005 | | 8/30/2005 | | PASS |
|
|
|
Approved subject to plan review comments, faxed to architect; called architect to discuss.
|
Plan resubmittals received | | | 8/29/2005 | | |
|
|
|
Received (4) copies of sheet S-1, S-2, S-3, S-4, S-4.1, S-5, S-5.1, S-6, S-8, S-9 and S-10. Also received (3) sets of structural calcs. Routed to John M.
|
Routing - PLAN CHECK | 8/18/2005 | | 8/18/2005 | | FAIL |
|
|
|
John M.
|
Routing Off Site - STRUCTURAL | 8/15/2005 | | 8/18/2005 | | |
|
|
|
Routed soils report and structural calsc to Stapley Eng.
|
Plan resubmittals requested | | | 8/18/2005 | | DONE |
|
|
|
E-mailed the architect with a copy of the structural and nonstructural plan review comment lists requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 8/4/2005 | | 8/18/2005 | | FAIL |
|
|
|
Routed to Stapley Engineering - Received e-mailed comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - PLANNING | 8/16/2005 | | 8/17/2005 | | PAS |
|
|
|
Sarah S.
|
Routing - PLUMBING | 8/12/2005 | | 8/16/2005 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 8/11/2005 | | 8/12/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 8/8/2005 | | 8/11/2005 | | FAIL |
|
|
|
Drainage plan shows inadequate clearance between high ground water & bottom of seepage beds. Variance request is pending. Contact Jim Wyllie ###-####
|
Plan resubmittals received | | | 8/11/2005 | | DONE |
|
|
|
Received 1 Transmittal , & 2 Hazardous Materials Inventory Statement Taken to John M.
|
Routing - PLANNING Land Div | 8/4/2005 | | 8/8/2005 | | PASS |
|
|
|
Lot 23, Block 3, West Boise Industrial Park #6
|
Plans ACCEPTED BY PLAN TECH | | | 8/4/2005 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 8/4/2005 | | |
|
|
|
|
Application received | | | 8/1/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/1/2005 | | |
|
|
|
|
Fee Review-notes | 8/1/2005 | 8/1/2005 | | | |
|
|
|
|