Letter of compliance | | | 12/6/2006 | | DONE |
|
|
|
Letter of Compliance issued 12-6-06.
|
FIRE-Final Inspection | 11/29/2006 | 11/30/2006 | 11/30/2006 | A | PASS |
Troy Cobbley
|
|
|
Life safety finaled. See entry from Sam Rogers pertaining to the battery capacity. All other items ok.
|
Additional plans submitted | | | 11/30/2006 | | DONE |
|
|
|
Received letter from battery manufacturer indicating battery capacity is 51.3 gals and batteries are VRLA and re-absorb "99% of the gases generated" (hydrogen) and "No special battery room or ventilation is required". Dave Hanneman agreed to treat as nominally 50 gals and not apply requirements of IFC 609 for smoke detection system and special room ventilation. Advised Troy C. to re-inspect on this basis.
|
Case Summary (BLD) | | | 11/28/2006 | | |
|
|
|
|
Case Summary (BLD) | | | 11/28/2006 | | DONE |
|
|
|
|
FIRE-Final Inspection | 11/13/2006 | 11/14/2006 | 11/14/2006 | P | CANC |
Troy Cobbley
|
|
|
Contractor is going to set up meeting with Sam Rogers to go over the inspectors comments that he disagrees with.
|
BLD-Final | 10/4/2006 | 10/4/2006 | 10/4/2006 | P | PEND |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/4/2006 at 7:54:23 AM. Contact: ###-####. Will be ok for final once life/safety finals.
|
Code Occupancy Approval | 10/4/2006 | 10/4/2006 | 10/4/2006 | P | PASS |
Scott M.Brown
|
|
|
FINAL SIGNED OFF
|
FIRE-Final Inspection | 10/2/2006 | 10/3/2006 | 10/3/2006 | A | FAIL |
Troy Cobbley
|
|
|
Provide ventilation per IFC 609.1 and review comment #2, provide fire alarm permti per review comment #3, tag fire extinguisher per comment #17 and provide address per comment #16
|
BLD-Final | 10/2/2006 | 10/3/2006 | 10/3/2006 | A | NR |
Mike Jordan
|
|
|
call for access; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Needs code enforcement and life safety finals. Need copy of special insp. letter and needs to provide step and enterance.
|
BLD-Foundation | 8/21/2006 | 8/21/2006 | 8/21/2006 | P | PASS |
Tom Arcoraci
|
|
|
roger; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Other | 8/14/2006 | 8/15/2006 | 8/15/2006 | A | PART |
Jim Sly
|
|
|
rick Note: r-bar ; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Rebar for tower only.......OK
|
(F) Reprint permit | | | 7/28/2006 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/27/2006 | | DONE |
|
|
|
|
Telephone call | | | 7/25/2006 | | DONE |
|
|
|
tlk to tony wilson ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 7/25/2006 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 7/24/2006 | | PASS |
|
|
|
7/24/06 - Notified by engineering board that license had been renewed. Okay to issue permit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/24/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/24/2006 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/12/2006 | | 7/14/2006 | | PASS |
|
|
|
Okay to take to permit desk. Do not issue until contractor registration form is provided and the engineer of record has a current state license. (see Marlene for questions)
|
Plan Reviewer's activity | | | 7/14/2006 | | HOLD |
|
|
|
7/14/2006 - Presently on HOLD and cannot issue until the engineer renews his state license. Contacted Tony Wilson (applicant) to inform him. As soon as license is renewed the permit can be issued.
|
Plan assigned to (MLO) | 8/9/2005 | | 7/14/2006 | | PASS |
|
|
|
|
Routing - FIRE | 7/10/2006 | | 7/12/2006 | | PASS |
|
|
|
Attached review comments to plans.
|
Routing - PLANNING Land Div | 7/12/2006 | | 7/12/2006 | | PASS |
|
|
|
Plat has been recorded.
|
Routing - PLAN CHECK | 7/6/2006 | | 7/7/2006 | | PEND |
|
|
|
needs state tag number for modular
|
Routing - PLANNING Land Div | 7/7/2006 | | 7/7/2006 | | FAIL |
|
|
|
Need to record Final Plat prior to issuing building permit.
|
Plan resubmittals received | | | 7/3/2006 | | |
|
|
|
Recieved 3 copies of the following: T01, C01, A01, A02, A03, A04, A05, A06, E01, E02, E03, E04, E05, E06, L01, C01-site survey; taken to Mike Otto
|
Plan resubmittals received | | | 6/29/2006 | | |
|
|
|
received "3" sets of plans including 3 sheets of T01, C01, A01, A02, A03, A04, A05, A06, E01, E02, E03, E04, E05, E06, L01 & Co1--plans taken to mike otto-plans didn't met size requirements will need to be re-submitted--will call tim wilson
|
Telephone call | | | 6/29/2006 | | DONE |
|
|
|
left mess for tim wilson that the correct size plans need to be submitted
|
Routing - FIRE | 4/13/2006 | | 4/17/2006 | | FAIL |
|
|
|
Faxed resubmittal requirement to architect. Attached review comments to plans.
|
Routing - PLANNING | 4/4/2006 | | 4/6/2006 | | PASS |
|
|
|
Approved per DRH05-00116.
|
Routing - PLANNING Land Div | 3/30/2006 | | 4/4/2006 | | FAIL |
|
|
|
Korte's Only Sub has not recorded as of 4/4/06.
|
Plan resubmittals received | | | 3/27/2006 | | DONE |
|
|
|
Received 5 copys of sheet C01 & 1 copy of 11 x 17 ( C01 ) taken to Mike O.
|
Routing - PLAN CHECK | 3/8/2006 | | 3/9/2006 | | FAIL |
|
|
|
corrections of 8/16/2005 not complete.
|
Routing - PLANNING Land Div | 3/7/2006 | | 3/7/2006 | | PEND |
|
|
|
Final Plat of Korte's Only Subdivision signed by Boise City Engineer on March 7, 2006. Do not issue building permit until Final Plat is recorded.
|
Routing - FIRE | 8/16/2005 | | 8/24/2005 | | FAIL |
|
|
|
review faxed to architect.
|
Plan resubmittals received | | | 8/24/2005 | | |
|
|
|
Received Project Start-up for Special Inspections. Routed to Mike O.
|
1st review completed | | | 8/24/2005 | | FAIL |
|
|
|
failed planning land div, plan check and fire.
|
Plan resubmittals received | | | 8/24/2005 | | |
|
|
|
Received (1) copy of State plan approval for equipment shelter. Routed to Mike O.
|
Plan resubmittals received | | | 8/23/2005 | | |
|
|
|
Received (1) copy of Anchor spec sheets and 1hr fire rating for shelter. Routed to Mike O.
|
Plan resubmittals requested | | | 8/16/2005 | | DONE |
|
|
|
IBC , State tag and plans
|
Routing - PLAN CHECK | 8/15/2005 | | 8/16/2005 | | FAIL |
|
|
|
corrections sent to Tony Wilson
|
Routing - Erosion and Sediment | 8/14/2005 | | 8/15/2005 | | PASS |
|
|
|
ESC plan waiver request approved with attached conditions.
|
Routing - PLANNING | 8/11/2005 | | 8/14/2005 | | FAIL |
|
|
|
Sara S. DRH05-00116
Applicant has not provided a landscape plan to show compliance with the conditions of approval. Applicant has been contacted.
|
Routing - PLANNING Land Div | 8/10/2005 | | 8/10/2005 | | FAIL |
|
|
|
Site plan doesn't match Assessor's map.
|
Plan routing begun/NEW & ADDTN | | | 8/9/2005 | | |
|
|
|
|
Application received | | | 8/5/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/5/2005 | | |
|
|
|
|
Fee Review-notes | 8/5/2005 | 8/5/2005 | | | |
|
|
|
|