Third Notice BLD | 12/6/2005 | 12/6/2005 | 1/17/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 10/31/2005 | 10/31/2005 | 12/6/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 10/20/2005 | 10/31/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 10/20/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10774 issued 10-20-05 to Countrywide Mortgage.
|
BLD-Final | 10/14/2005 | 10/14/2005 | 10/14/2005 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 10/14/2005 at 6:00:52 AM. Contact: ###-####. ok for perm occ. ():
|
FIRE-Final Inspection | 10/14/2005 | 10/14/2005 | 10/14/2005 | A | PASS |
Forrest France
|
|
|
Door hardware and emergency lights have been repaired as required, fire life safety finaled.
|
Permanent Occupancy | | 10/14/2005 | 10/14/2005 | | DONE |
|
|
|
|
BLD-Final | 10/11/2005 | 10/12/2005 | 10/12/2005 | A | NR |
Jim Sly
|
|
|
dave; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Need all signatures.
|
FIRE-Final Inspection | 10/11/2005 | 10/11/2005 | 10/11/2005 | P | FAIL |
Troy Cobbley
|
|
|
Provide additional emergency lighting in the new open office space, replace burnt out bulbs in the lights in the existing space and provide approved door hardware for the secondary exterior exit door.
|
BLD-Framing/Rough-in | 9/21/2005 | 9/21/2005 | 9/21/2005 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/21/2005 at 10:14:28 AM. Contact: ###-####. ok to cover after ele. ri insp.
|
Issue PAID IN FULL permit | | | 9/21/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/19/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/19/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/19/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/19/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/19/2005 | | DONE |
|
|
|
|
Telephone call | | | 9/19/2005 | | DONE |
|
|
|
left mess for john price at ###-#### permit is ready
|
1st review completed | | | 9/16/2005 | | FAIL |
|
|
|
failed plan check
|
Routing - PLAN CHECK | 9/16/2005 | | 9/16/2005 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/16/2005 | | PASS |
|
|
|
|
Plan assigned to (JCB) | 8/11/2005 | | 9/16/2005 | | PASS |
|
|
|
9/16/2005 09:03:09 JCB - activity updated through activity BLDA022 from case BLD05-02157.
|
Routing - FIRE | 8/31/2005 | | 9/16/2005 | | PASS |
|
|
|
review faxed to architect.
|
Routing - PLAN CHECK | 9/9/2005 | | 9/9/2005 | | PEND |
|
|
|
When approved by Fire Dept. permit can be issued.
|
Plan resubmittals received | | | 9/8/2005 | | DONE |
|
|
|
Received 1 Response Letter, & 2 Copys of sheet A7.0 Taken to Jason B.
|
Plan resubmittals received | | | 9/7/2005 | | |
|
|
|
Received (2) copies of sheet A0.0 and A9.3 along with a copy of the Regisered Design Professional of Responsible Charge form and a Certificate of Value. Routed to Jason B.
|
Plan resubmittals requested | | | 8/31/2005 | | DONE |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - PLAN CHECK | 8/11/2005 | | 8/31/2005 | | FAIL |
|
|
|
Plan review report e-mailed and faxed to architect. Plan resubmittals and written response required for further review. Plans to route to Fire Dept. for review.
|
Plans ACCEPTED BY PLAN CHECK | | | 8/10/2005 | | |
|
|
|
|
Application received | | | 8/5/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/5/2005 | | |
|
|
|
|
Fee Review-notes | 8/5/2005 | 8/5/2005 | | | |
|
|
|
|