Case Summary (BLD) | | | 4/11/2008 | | DONE |
|
|
|
|
Third Notice BLD | 5/25/2007 | 5/25/2007 | 6/21/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Fee Review-notes | 8/11/2005 | 8/11/2005 | 6/21/2007 | | DONE |
|
|
|
|
Second Notice BLD | 5/9/2007 | 5/9/2007 | 5/25/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 4/26/2007 | 5/9/2007 | | DONE |
|
|
|
|
Permanent occupancy | | | 4/26/2007 | | DONE |
|
|
|
Perm. Occ. Cert. # 11557 issued 4-26-07 The Orchards Clubhouse.
|
Code Occupancy Approval | 4/24/2007 | 4/25/2007 | 4/25/2007 | A | PASS |
Scott M.Brown
|
|
|
steve; Phone #: ###-#### Note: please call 1/2 hr prior to inspection Internet Inspection Request from: Cathy Chiles
|
Permanent Occupancy | | 4/25/2007 | 4/25/2007 | | DONE |
|
|
|
|
BLD-Final | 2/27/2007 | 2/28/2007 | 2/28/2007 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 2/27/2007 at 3:17:36 PM. Contact: ###-####.
|
FIRE-Final Inspection | 2/27/2007 | 2/27/2007 | 2/27/2007 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled
|
BLD-Aging Inspection | 1/31/2007 | 1/31/2007 | 1/31/2007 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 12/1/2006 | 12/1/2006 | 12/7/2006 | | NR |
Troy Cobbley
|
|
|
Work is in progress
|
FIRE-Final Inspection | 9/22/2006 | 9/22/2006 | 9/22/2006 | P | FAIL |
Troy Cobbley
|
|
|
Still need the exiting hardware through the pool area addressed. Duct detectors have been removed.
|
BLD-Aging Inspection | 9/15/2006 | 9/15/2006 | 9/15/2006 | | NR |
Troy Cobbley
|
|
|
work is in progress
|
FIRE-Final Inspection | 6/29/2006 | 6/30/2006 | 6/30/2006 | A | FAIL |
Troy Cobbley
|
|
|
See fire dept. review comments for items marked that need addressing. Items include signage at property entrances, removing the manual flush bolts on two interior doors, providing address, providing occupant load sign, relocate and test duct smoke detectors (or remove if allowed) and install fencing and gate hardware around the pool. Per review comments a separate permit is required for the swimming pool.
|
BLD-Final | 6/28/2006 | 6/29/2006 | 6/29/2006 | P | NR |
Jim Sly
|
|
|
carl; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley Need all req sigs
|
(F) Reprint permit | | | 6/23/2006 | | DONE |
|
|
|
|
(F) Reprint permit | | | 6/20/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 6/1/2006 | | |
|
|
|
Received 1 copy of cover letter to Mike Phillips, 1 copy of Letter from Stapley Engineering to Jeff Likes, 1 copy of the following pages- Chateau roof framing plan, Sheet # SK-1, SK-2, 1 copy of Letter from Stapley Engineering to Jeff Likes, 1 copy of the following pages- Canterbury roof framing plan, SK-3, Chateau roof framing plan, SK-4, SK-5, 1 page letter from Boise Wood Solutions, SK-6 and taken to Dave Hannah per MIke Phillips request///6/1/06 @ 9:40am BAS
|
BLD-Aging Inspection | 3/24/2006 | 3/24/2006 | 3/24/2006 | | NR |
Tom Arcoraci
|
|
|
|
BLD-Energy code compliance | 1/19/2006 | 1/20/2006 | 1/20/2006 | A | PASS |
Jim Sly
|
|
|
carl; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 1/17/2006 | 1/18/2006 | 1/18/2006 | P | PASS |
Tom Arcoraci
|
|
|
karl--for cover insp ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Framing/Rough-in | 12/27/2005 | 12/28/2005 | 12/28/2005 | A | PART |
Tom Arcoraci
|
|
|
shear nail insp///carl ; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Other | 11/17/2005 | 11/18/2005 | 11/18/2005 | A | PASS |
Tom Arcoraci
|
|
|
stem wall insp//carl; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ground rod installed at this time
|
BLD-Footing | 11/15/2005 | 11/16/2005 | 11/16/2005 | A | PASS |
Tom Arcoraci
|
|
|
carl; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
(F) Reprint permit | | | 10/18/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/17/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/14/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/14/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/14/2005 | | DONE |
|
|
|
|
Telephone call | | | 10/14/2005 | | DONE |
|
|
|
called ###-#### and left message for Billy Strite (arch) that permit is ready and fees
|
Routing - PLAN CHECK | 10/6/2005 | | 10/13/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/13/2005 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 8/11/2005 | | 10/13/2005 | | PASS |
|
|
|
10/13/2005 15:21:07 M_P - activity updated through activity BLDA022 from case BLD05-02192.
|
Routing - PLAN CHECK | 10/4/2005 | | 10/6/2005 | | FAIL |
|
|
|
Second review failed, called and left message for Bill Strite requesting additional information, missing structural responces.
|
Routing - PLAN CHECK | 9/23/2005 | | 10/4/2005 | | |
|
|
|
Routing to ESC.
|
Plan resubmittals received | | | 10/4/2005 | | |
|
|
|
Received (2) copies of the ESC plan and narrative. Routed to Mike P.
|
Routing - Erosion and Sediment | 10/4/2005 | | 10/4/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Plan resubmittals received | | | 9/23/2005 | | |
|
|
|
Received (1) copy of the pool chemical report and special inspection start-up form. Received (2) copies of sheet 3.1EC, 5.2EC, 6.1EC, 6.2EC, 12.1, C-1.4, C-3.1 and C-3.2. Routed to Mike P.
|
1st review completed | | | 9/23/2005 | | FAIL |
|
|
|
failed ESC and plan check.
|
Routing - FIRE | 9/7/2005 | | 9/23/2005 | | PASS |
|
|
|
reveiw faxed to architect
|
Routing - PLAN CHECK | 8/30/2005 | | 9/7/2005 | | FAIL |
|
|
|
Plan review complete, e-mailed and mailed comments to the architect requesting additional information be submitted for further review prior to issuing permit.
|
Case Summary (BLD) | | | 9/7/2005 | | |
|
|
|
|
Routing - PLANNING | 8/16/2005 | | 8/30/2005 | | PASS |
|
|
|
DRH05-00191 Sara S. Approved per DRH05-00191. passed on to Angela W on 8/22/05. She is out sick 8/22 and I will check tomorrow. Passed 8/30 per CUP05-30 Mod.
CUP05-00030 Angela W.
|
Routing - PLUMBING | 8/16/2005 | | 8/16/2005 | | PASS |
|
|
|
per plans and 2003 upc
|
Routing - Erosion and Sediment | | | 8/16/2005 | | FAIL |
|
|
|
ESC plan not provided, narrative not per BMC 8-17, esc application not for this project, rp listed not rp but pd. Checklist prepared and faxed to PD.
|
Routing - PUBLIC WORKS | 8/11/2005 | | 8/15/2005 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 8/11/2005 | | 8/11/2005 | | PASS |
|
|
|
Approved, site is over 5 acres in size.
|
Recd Pcfee & Taken To Pln CK | | | 8/11/2005 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/11/2005 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 8/11/2005 | | |
|
|
|
|
Application received | | | 8/9/2005 | | |
|
|
|
|
PubWorks Occupancy Approval | 5/19/2009 | 5/19/2009 | | | |
|
|
|
Terry Records signed off project except for 2 buildings
|