Permit Information
Permit NumberBLD05-02200
StatusFinaled
Name BOISE VALLEY HABITAT FOR HUMANITY
Site Address 2007 N CRIBBENS ST
Project Name 
Customer Number 
ePlanReviewNo
Description
"THE PERMIT HOLDER is responsible to comply with current wall bracing requirements as adopted by Boise City." To construct a three bedroom, one and three quarter bathroom 1056 sq. ft. single story single family dwelling with a 400 sq. ft. concrete parking pad. Per approved plans and requirement list. (SAM)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Conference6/1/20066/1/20066/1/2006PPASS
DetailsJim Sly
Requesting final inspection. ; Phone #: ###-#### Internet Inspection Request from: Dean McKellip

FINAL OK
DOC - Permit Finaled6/1/20066/1/20066/1/2006PPASS
DetailsJim Sly
BLD-Conference12/8/200512/8/200512/8/2005PPASS
DetailsJim Sly
Requesting permission to cover, start sheet rocking.; Phone #: ###-#### Internet Inspection Request from: Dean McKellip
Energy Code OK
BLD-Conference12/7/200512/7/200512/7/2005PCANC
DetailsJim Sly
Requesting authorization to cover insulation and start sheet rocking.; Phone #: ###-#### Internet Inspection Request from: Dean McKellip
BLD-Conference11/28/200511/29/200511/29/2005APASS
DetailsJim Sly
Requesting permision to insulate exterior walls Internet Inspection Request from: Dean McKellip
Frame PASS
BLD-Conference9/28/20059/28/20059/28/2005PNR
DetailsMike Jordan
requesting authorization to pour concrete stem walls. Would appreciate inspect right after lunch. Concrete punping scheduled for 3 PM; Phone #: ###-#### Internet Inspection Request from: Dean McKellip
BLD-Conference9/19/20059/20/20059/20/2005PPASS
DetailsJim Sly
Requesting stem wall inspection first thing after lunch if possible.; Phone #: ###-#### Internet Inspection Request from: Dean McKellip
Wall OK
BLD-Footing9/16/20059/19/20059/19/2005APASS
DetailsJim Sly
Requesting footing inspection as early as possible appreciated.; Phone #: ###-#### Internet Inspection Request from: Dean McKellip
BLD-Conference9/19/20059/19/20059/19/2005PPASS
DetailsJim Sly
Requesting footing inspection for early afternoon.; Phone #: ###-####
Footing PASS
Permit Ready to Issue  9/7/2005  
Telephone call  9/7/2005 DONE
left mess that permit is ready
Issue PAID IN FULL permit  9/7/2005  
Plan assigned to (SAM)8/9/20059/6/20059/6/2005 PASS
9/6/2005 09:45:09 SAM - activity updated through activity BLDA022 from case BLD05-02200.
Routing - PLAN CHECK8/17/2005 9/6/2005 PASS
Print Pending Permit.LaserJet4  9/6/2005  
PLANS/APPL TAKEN TO FRONT DESK  9/6/2005 DONE
Inspection Record Card- Bld  9/6/2005 DONE
Routing - PUBLIC WORKS8/16/2005 8/17/2005 PASS
Routing - PLANNING8/12/2005 8/16/2005 PASS
Application received  8/9/2005