Permit Information
Permit NumberBLD05-02310
StatusFinaled
Name STEVE YOUNGERMAN
Site Address 404 E PARKCENTER BLVD
Project NameRIVER QUARRY BLD A
Customer Number 
ePlanReviewNo
Description
(HARRY'S PARKCENTER)(RIVER QUARRY BLDG A-STE #140) To construct a 2,986 sq.ft. restaurant in existing 1 story building per approved plans. Work to include, construction of interior partitions, to construct two accessible restrooms, kitchen area and related appliances, installation of a new type-one hood system, grease duct and one hour grease duct wrap, installation of new sinks, miscelaneous related interior finishes. This building is NOT fire sprinklered. The existing one hour tenant demising wall is being upgraded to a Two hour fire barrier to limit the fire area to under 5000 sq ft in lieu of sprinklers. Rmh
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Telephone call  4/5/2007 DONE
call to steve youngerman no ans. call to bob john, he stated this is youngerman's job, he doesn't know why he is on the permit, and he will once again try to get his brother in law steve youngerman to comply with the final cert of value requirement.
Third Notice BLD6/14/20066/14/20063/1/2007 DONE
Second Notice has not been responded to.
Telephone call  2/13/2007  
spoke w/ bob john. John stated that his brother in law is responsible for the permit and he will get ahold of him and have him call us, as his brother in law's phone # is unlisted ahnd John can not give it out. I told him that since he allowed his brother in law to use his name on the permit he is ultimately responsible for all of the permit requirements including final certificate of value. He stated he would contact us later this day w/ the brother in law's phone #.
Telephone call  2/13/2007  
call from bob john, his brother in law's name is steve youngerman and his address is 5415 s caper pla, boise, idaho cell # ###-####. third and final notice sent to steve youngerman.
Telephone call  2/6/2007 DONE
tlk to bob concerning the return copy of final notice - he will contact steve youngblood and have him call me - If i dont hear from him by friday I will call bob back
Second Notice BLD4/14/20064/14/20066/14/2006 DONE
First Notice has not been responded to.
First Notice 3/20/20064/14/2006 DONE
BLD-Final3/16/20063/20/20063/20/2006APASS
DetailsJim Storey
Permanent Occupancy 3/20/20063/20/2006 DONE
Details
Permanent occupancy UNPAID FEE  3/20/2006 DONE
Perm. Occ. Cert. # 10940 issued 3-20-06 to Harry's Parkcenter.
BLD-Final3/15/20063/16/20063/16/2006ANR
DetailsJim Storey
resch. for mon am
BLD-Final3/14/20063/15/20063/15/2006AFAIL
DetailsJim Storey
Scheduled by a contractor via Hello! on 3/14/2006 at 4:30:52 PM. Contact: ###-####.smoke seal door stop health dept
FIRE-Final Inspection3/14/20063/15/20063/15/2006APASS
DetailsForrest France
Fire life safety is satisfactory, inspection passed.
BLD-Framing/Rough-in3/1/20063/1/20063/1/2006PPASS
DetailsJim Storey
ceiling grid inspection//john; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
BLD-Framing/Rough-in12/30/200512/30/200512/30/2005PPASS
DetailsTom Arcoraci
Issue PAID IN FULL permit  11/8/2005 DONE
Print Occupancy Form  10/26/2005 DONE
Permit Ready to Issue  10/26/2005 DONE
Telephone call  10/26/2005 DONE
called ###-#### and told Pete Rockwell that permit is ready and fees
Plan assigned to (R_H)8/23/2005 10/25/2005 PASS
10/25/2005 15:30:29 RMH - activity updated through activity BLDA022 from case BLD05-02310.
Routing - FIRE10/14/2005 10/25/2005 PASS
Resubmittal review / Acceptable. They installed a fire barrier wall.
Routing - PLAN CHECK10/25/2005 10/25/2005 PASS
PLANS/APPL TAKEN TO FRONT DESK  10/25/2005 DONE
Case Summary (BLD)  10/14/2005 DONE
Routing - PLAN CHECK10/6/2005 10/14/2005 PEND
Permit pending fire department review and approval, no corrections required by the building review
Plan resubmittals received  10/13/2005 DONE
Received 1 Transmittal Letter, 1 Letter to Ron H. & 3 Copys of sheets A-1.1,A-2.1,A-2.2 Taken to Ron H.
Routing - FIRE9/15/2005 10/6/2005 FAIL
faxed review to architect.
1st review completed  10/6/2005 FAIL
failed plan check and fire
Case Summary (BLD)  9/15/2005 DONE
Routing - PLAN CHECK9/6/2005 9/15/2005 FAIL
Routing - PLUMBING9/2/2005 9/6/2005 PASS
Approved per plan and 2005 UPC
Routing - PLANNING8/29/2005 9/2/2005 PASS
Marty Santoyo. Verify use of a new restaurant space in the building. (L-OD zone)
The restaurant use is allowed in the zone and the seats proposed meet the parking allowed under CUP02-00140.
Routing - PUBLIC WORKS8/23/2005 8/29/2005 PASS
Plans ACCEPTED BY PLAN TECH  8/22/2005  
Application received  8/19/2005  
Recd Pcfee & Taken To Pln CK  8/19/2005  
Fee Review-notes8/19/20058/19/2005