Second Notice BLD | 2/2/2007 | 2/2/2007 | 2/2/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 12/18/2006 | 2/2/2007 | | DONE |
|
|
|
|
BLD-Final | 12/4/2006 | 12/4/2006 | 12/4/2006 | P | PASS |
Tom Arcoraci
|
|
|
jay ; Phone #: ###-#### - please call 1/2 hr prior to inspection Internet Inspection Request from: Patricia Smith
|
Permanent occupancy | | | 12/4/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11340 issued 12-4-06 to the North St. Apts.
|
Code Occupancy Approval Temp | 11/16/2006 | 11/27/2006 | 11/27/2006 | A | CANC |
Michael Garner
|
|
|
find out if bldr. has come to an agreement about landscape screening for street-side swales and planners - officer has spoken with the planner - Sarah Schafer - who confirmed that she and the bldr have an agreed upon plan - case closed
|
Code Occupancy Approval | 11/27/2006 | 11/27/2006 | 11/27/2006 | P | PASS |
Michael Garner
|
|
|
|
BLD-Final | 11/21/2006 | 11/22/2006 | 11/22/2006 | A | PART |
Tony Young
|
|
|
jay ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith ok for temp occ.. c/n posted
|
Temporary occupancy | | | 11/22/2006 | | DONE |
|
|
|
Temp. Occ. Cert. # 5478 issued 11-22-06 to the North Street Apartments.
|
BLD-Final | 11/20/2006 | 11/21/2006 | 11/21/2006 | A | NR |
Tony Young
|
|
|
jay - note: - please call 1/2 hr prior to inspection ; Phone #: ###-#### Internet Inspection Request from: Patricia Smith
|
FIRE-Final Inspection | 11/20/2006 | 11/21/2006 | 11/21/2006 | A | PASS |
Troy Cobbley
|
|
|
life safety finaled
|
Code Occupancy Approval | 11/16/2006 | 11/16/2006 | 11/16/2006 | P | FAIL |
Michael Garner
|
|
|
officer mistakenly finaled this case on the COD side - officer did sign the TempOccupancy card on-site - officer thinks that the DRH condition requiring landscape screening for swales adjacent to the street has not been completed by the builder
|
BLD-Energy code compliance | 9/11/2006 | 9/11/2006 | 9/11/2006 | P | PASS |
Tony Young
|
|
|
jay; Phone #: ###-#### Note: please first to meet with jay Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 9/1/2006 | 9/1/2006 | 9/1/2006 | P | PART |
Dave Hannah
|
|
|
ok to insulate c/n on site
|
BLD-Framing/Rough-in | 5/3/2006 | 5/4/2006 | 5/4/2006 | A | PART |
Tony Young
|
|
|
jay; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles exterior shear ok
|
BLD-Foundation | 2/21/2006 | 2/21/2006 | 2/21/2006 | P | PART |
Tony Young
|
|
|
foundation wall insp//jay; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Footing | 2/16/2006 | 2/17/2006 | 2/17/2006 | A | PART |
Tony Young
|
|
|
pouring at 10am///jay; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
Issue PAID IN FULL permit | | | 2/8/2006 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 9/13/2005 | | 1/24/2006 | | PASS |
|
|
|
1/24/2006 08:21:12 M_P - activity updated through activity BLDA022 from case BLD05-02326.
|
Routing - PLAN CHECK | 1/23/2006 | | 1/24/2006 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/24/2006 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 1/24/2006 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 1/24/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/24/2006 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/24/2006 | | DONE |
|
|
|
|
Telephone call | | | 1/24/2006 | | DONE |
|
|
|
tlk to gary ###-#### that permit and fees are ready to be picked up
|
Routing - FIRE | 1/19/2006 | | 1/23/2006 | | PASS |
|
|
|
No comments.
|
Routing - PLAN CHECK | 1/4/2006 | | 1/19/2006 | | |
|
|
|
Routing to fire.
|
Plan resubmittals received | | | 1/19/2006 | | DONE |
|
|
|
Received 2 copies of sheet A1.0 reflecting new fire hydrant location.
|
Plan resubmittals received | | | 1/17/2006 | | DONE |
|
|
|
Received 1 transmittal, & 2 copys of sheets A1.0,A3.0,A5.0 taken to Mike P.
|
Routing - PLAN CHECK | 12/19/2005 | | 1/4/2006 | | PEND |
|
|
|
Waiting for others to approve prior to issuing permit.
Plans are in fire department for review on Buildings 2 & 3.
|
Plan resubmittals received | | | 12/20/2005 | | DONE |
|
|
|
2 copies of plan sheets A1.0, A2.0, A2.1, A3.0, A4.1, A4.2, A5.0, A8.0, A9.0 received and inserted in other plan sets by architect.
|
Routing - PLAN CHECK | 12/8/2005 | | 12/19/2005 | | FAIL |
|
|
|
Second review failed, sent correction report to architect requesting additional information be submitted for further review prior to issuing permit.
|
Routing - PLUMBING | 12/2/2005 | | 12/6/2005 | | PASS |
|
|
|
approved per resubmittall,notes, plan and 2003 UPC
|
Routing - PLAN CHECK | 11/29/2005 | | 12/2/2005 | | |
|
|
|
Routing to plumbing.
|
1st review completed | | | 11/29/2005 | | FAIL |
|
|
|
FAILED PLUMBING PLANNING AND PLAN CHECK
|
Routing - FIRE | 11/21/2005 | | 11/27/2005 | | PASS |
|
|
|
routed to FV 11/23
|
Plan resubmittals received | | | 11/22/2005 | | |
|
|
|
Received (2) copies of sheet A1.0. Routed to Mike P.
|
Routing - PLAN CHECK | 10/31/2005 | | 11/21/2005 | | FAIL |
|
|
|
Plan review complete, sent correction report requesting additional information be submitted for further review prior to issuing permit.
|
Print permit w/o conditions | | | 11/21/2005 | | |
|
|
|
|
Routing - PLANNING | 10/14/2005 | | 10/31/2005 | | PASS |
|
|
|
Taffic plan approved and passes. Units moved -- permit needs modification. Modification appeal ended, permit passed.
|
Plan resubmittals received | | | 10/19/2005 | | DONE |
|
|
|
Received 1 transmittal & 2 copys of sheet P2.0 Taken to Mike P.
|
Routing - PLAN CHECK | 9/30/2005 | | 10/14/2005 | | |
|
|
|
Routing to Planning Angela Wood for traffic study review.
|
Plan resubmittals received | | | 10/11/2005 | | |
|
|
|
Received (1) copy of sheet A1.0. Routed to Mike P.
|
Routing - PLANNING | 9/30/2005 | | 9/30/2005 | | FAIL |
|
|
|
Need proof of "Traffic Safety Plan" prior to issuance of blg. permits as outlined in CUP04-104 staff report, condition number 4. Document attached to permit.
|
Routing - PLANNING | 9/23/2005 | | 9/29/2005 | | |
|
|
|
DRH 04-0-00215 Sara S. Approved per DR. I didn't get these plans passed on to Angie until 9/28/05.
|
Routing - PLUMBING | 9/19/2005 | | 9/23/2005 | | FAIL |
|
|
|
CHANGE PLUMBING PLAN. DCVA'S NOT ALLOWED UNDERGROUND UNLESS INSTALLED IN AN OSHA APPROVED VAULT.
|
Routing - Erosion and Sediment | 9/19/2005 | | 9/19/2005 | | PASS |
|
|
|
ESC approved with attached conditions.
|
Routing - PUBLIC WORKS | 9/15/2005 | | 9/19/2005 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 9/13/2005 | | 9/15/2005 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/13/2005 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 9/13/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/13/2005 | | |
|
|
|
|
Application received | | | 8/23/2005 | | |
|
|
|
|
Fee Review-notes | 9/13/2005 | 9/13/2005 | | | |
|
|
|
|