Permit Information
Permit NumberBLD05-02426
StatusFinaled
Name WFS FINANCIAL
Site Address 9465 W EMERALD ST Unit: 220
Project Name 
Customer Number 
ePlanReviewNo
Description
(WFS FINANCIAL - 2ND STORY) This building is fire sprinklered to allow all exit stairways from the 2nd floor to be open and to allow nonrated corridors. To create a 3,986 square foot office tenant space on the 2nd floor of an existing 2 story building. Work is to include interior nonbearing walls, suspended ceilings, interior doors, interior windows, and finishes. The work shall comply with the approved drawings, the plan review report, and all applicable codes. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD8/18/20068/18/200612/22/2006 DONE
Second Notice has not been responded to.
Second Notice BLD8/2/20068/2/20068/18/2006 DONE
First Notice has not been responded to.
First Notice 7/19/20068/2/2006 DONE
Permanent occupancy  7/19/2006 DONE
Perm. Occ. Cert. # 11139 issued 7-19-06 to WFS Financial.
BLD-Final7/10/20067/11/20067/11/2006APASS
DetailsMike Jordan
MATT; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles. Was finaled by Jim Sly, noted ok for perm occ.
Permanent Occupancy 7/11/20067/11/2006 DONE
Details
FIRE-Final Inspection7/3/20067/5/20067/5/2006APASS
DetailsTroy Cobbley
Life safety finaled
FIRE-Conference5/22/20065/22/20065/22/2006PDONE
DetailsTroy Cobbley
I left a correction notice with Tim Waterman giving him until June 23, 2006 to have all permits for WFS finales or the temporary occupancy would be revoked and utilities turned off.
Meeting  5/22/2006 DONE
90-day TOC period has expired. Approval by Dave Hanneman and Jenifer Gilliland to allow a 30-day extension if owner posts a bond. In subsequent telcon 5/19/06 4:00 pm, with FA vendor, Lynde Jones, Mountain Alarm, Lynde indicated they have approval to resume work and she will have a person on site Monday to begin work and she committed to have it done within 30 days, absolutely "drop dead date" and possibly sooner. With that assurance, JG agreed to defer posting bond at this time but will have Troy Cobbley issue a Correction Notice to building owner, Tim Waterman indicating that the TOC will be extended until 6/23 at which time if the alarm system has not been installed and satisfactorily inspected and tested, the building may be red tagged, possibly utilities terminated and occupants expected to vacate. I called building owner, Tim Waterman, Video Eye, 5/22/06, 9:00 am to advise of City course of action; not available, left voice message to call me.
BLD-Final2/23/20062/23/20062/23/2006PDONE
DetailsTom Arcoraci
matt; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Temporary occupancy  2/13/2006 DONE
Temp. Occ. Cert. # 5368 issued 2-13-06 to WFS Financial.
BLD-Final12/6/200512/6/200512/6/2005PPART
DetailsJim Sly
matt; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
OK for Temp Occ. OK for Perm Occ. when Fire Perms. ():
FIRE-Final Inspection12/5/200512/6/200512/6/2005APART
DetailsTroy Cobbley
A temporary occupancy was given with Steve Kueter's permission until the fire alarm permit has been finaled.
FIRE-Final Inspection11/30/200512/1/200512/1/2005APART
DetailsForrest France
Life safety issues are acceptable pending fire alarm upgrade now required for the entire building.
BLD-Framing/Rough-in11/14/200511/15/200511/15/2005APASS
DetailsMike Jordan
ceiling grid inspection please///matt; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Framing/Rough-in10/26/200510/27/200510/27/2005PPASS
DetailsJim Sly
matt; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Issue PAID IN FULL permit  10/18/2005 DONE
Permit Ready to Issue  10/13/2005  
Inspection Record Card- Bld  10/13/2005 DONE
Print Occupancy Form  10/13/2005 DONE
Telephone call  10/13/2005 DONE
called Matt Rhees (arch.) and told him that permit is ready and fees
Routing - PLAN CHECK10/7/2005 10/12/2005 PASS
Drawings approved after resubmittal review.
PLANS/APPL TAKEN TO FRONT DESK  10/12/2005 DONE
Plan assigned to (CJW)9/9/2005 10/12/2005 PASS
10/12/2005 11:19:52 CJW - activity updated through activity BLDA022 from case BLD05-02426.
Plan resubmittals received  10/11/2005 DONE
Received 1 Transmittal & 2 Copys of sheets A4.0,M4.0 Taken to Carl W.
1st review completed  10/7/2005 FAIL
Failed plan check
Routing - FIRE9/19/2005 10/7/2005 PASS
Comments faxed to the architect.
Plan resubmittals received  9/28/2005  
Received (2) copies of A3.0. Routed to Carl W.
Routing - PLAN CHECK9/12/2005 9/19/2005 FAIL
The IBC plan review was started on September 16, 2005 and was finished on September 19, 2005. Revised drawings were required. See the plan review report.
Routing - PUBLIC WORKS9/9/2005 9/12/2005 PASS
Plans ACCEPTED BY PLAN TECH  9/6/2005  
Application received  8/31/2005  
Recd Pcfee & Taken To Pln CK  8/31/2005  
Fee Review-notes8/31/20058/31/2005