rce #681//Synergy Office Building (Shell & Core) - To construct a new 6,000 square foot, one story, wood framed office shell and core building and related site improvements. The 335 square foot finished core area of this building includes a comment entry lobby and a men's and women's restroom. This shell building is constructed for two future office tenant spaces. This is a shell and core permit only and no occupancy is allowed under this permit. Separate tenant improvement permit will be required to finish this building for occupancy. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes9/2/20059/2/20052/6/2007 DONE
Third Notice BLD1/8/20071/8/20071/31/2007 DONE
Second Notice has not been responded to.
Second Notice BLD12/27/200612/27/20061/8/2007 DONE
First Notice has not been responded to.
First Notice11/17/200611/17/200612/27/2006 DONE
DetailsJim Sly
DOC - Permit Finaled11/17/200611/17/200611/17/2006PPASS
DetailsJim Sly
(F) Reprint permit  9/19/2006  
FIRE-Final Inspection7/24/20067/25/20067/25/2006APASS
DetailsTroy Cobbley
Life safety finaled
FIRE-Final Inspection7/5/20067/6/20067/6/2006APART
DetailsTroy Cobbley
A temporary occupancy was given until the curbing has been painted for the fire dept. access.
BLD-Final6/19/20066/20/20066/20/2006ANR
DetailsJim Sly
Phone #: Dana ###-####
BLD-Energy code compliance4/24/20064/24/20064/24/2006PPASS
DetailsJim Sly
dana; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Framing/Rough-in4/19/20064/20/20064/20/2006APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 4/19/2006 at 1:36:34 PM. Contact: ###-####.
Just need to check lateral bracing for trusses restrained min. 1 end. and complete draftstop at W. end soffit.
BLD-Framing/Rough-in4/18/20064/19/20064/19/2006APART
DetailsDave Hannah
Dana -- shear insp; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong letter from engineer oking sw2 sear panel as is ok to cover ext will add sheet rock shear to inside
BLD-Other4/13/20064/13/20064/13/2006PPART
DetailsJim Sly
danna - Note: shear ; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Shear......OK except SW2 wall.......Need letter from Eng or nail 10d at 2/12
BLD-Foundation1/27/20061/30/20061/30/2006APASS
DetailsJim Sly
west; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Footing1/25/20061/26/20061/26/2006APASS
DetailsJim Sly
wes ; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
Called Eng....2500 psi design on Conc.
(F) Reprint permit  1/6/2006  
Issue PAID IN FULL permit  1/5/2006  
Telephone call  12/7/2005 DONE
called ###-#### and told her permit is ready and fees and need ACHD
Routing - FIRE11/21/2005 12/5/2005 PASS
Resub approved with conditions; faxed to architect.
Routing - PLAN CHECK12/5/2005 12/5/2005 PASS
PLANS/APPL TAKEN TO FRONT DESK  12/5/2005 DONE
Inspection Record Card- Bld  12/5/2005 DONE
Permit Ready to Issue  12/5/2005 DONE
Plan assigned to (JCM)9/8/2005 12/5/2005 PASS
12/5/2005 11:53:21 JCM - activity updated through activity BLDA022 from case BLD05-02452.
Routing - PLANNING11/17/2005 11/21/2005 PASS
Approved per all conditions of DRH05-00194 and as noted on the landscape plan.
Routing - PLAN CHECK10/19/2005 11/17/2005  
Plan resubmittals received  11/16/2005  
Received (2) copies of sheet E2.0L and E3.0. Routed to John M.
Plan resubmittals requested  11/14/2005 DONE
E-mailed the engineer requesting signed and dated revised electrical plans. JCM
Plan Reviewer's activity  11/14/2005 PASS
Reviewed and approved resubmitted plans sheets for structural and nonstructural revisions. JCM
Plan resubmittals received  11/10/2005 DONE
Received 2 review comments,2 landscape plans & 2 copys of sheets AD1,A-2,A-3,A-5,A-6,A-7,M-1,M-2,E2.0L, E3.0 Taken to John M.
1st review completed  10/19/2005 FAIL
failed planning, plan check, structural and fire.
Routing - FIRE10/3/2005 10/19/2005 FAIL
called architect left voicemail, revisions required per intake meeting not resubmitted. CE, Adam with Alliance , called and I explained the req'ts to him and faxed the review to him as well as to the architect.
Plan resubmittals received  10/12/2005 DONE
Received 3 Response to comments, & 3 Copys of sheets A-0,A-3,A-6 Taken to John M.
Routing - PLAN CHECK9/30/2005 10/3/2005 FAIL
Routing - PLANNING9/27/2005 9/30/2005 FAIL
Parking spaces at the northwest area of parking lot do not comply with dimensional criteria. Landscape plan has not been submitted to Design Review staff for review and approval.
Routing - PLUMBING9/15/2005 9/27/2005 PASS
per4 plans and 2003 upc. max hot water to public lavs is 120 deg.
Plan resubmittals requested  9/26/2005 DONE
E-mailed the project engineer a copy of the plan review comment list requesting revisions. JCM
Routing Off Site - STRUCTURAL9/8/2005 9/22/2005 FAIL
Routed to AHJ Engineering - Received a faxed comment list from the consulting structural engineer requesting revisions. JCM
Plan resubmittals requested  9/22/2005 DONE
Faxed the project engineer a copy of the structural comment list requesting revisions. JCM
Routing - Erosion and Sediment9/14/2005 9/15/2005 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS9/8/2005 9/14/2005 PASS
Pending Assignment by MYS9/2/2005 9/8/2005 DONE
9/8/2005 08:26:31 JCM - activity updated through activity BLDA166 from case BLD05-02452.
Plans ACCEPTED BY PLAN TECH  9/8/2005  
Plan routing begun/NEW & ADDTN  9/8/2005  
Routing - PLANNING Land Div9/8/2005 9/8/2005 PASS
Recd Pcfee & Taken To Pln CK  9/2/2005  
Application received  9/2/2005