Fee Review-notes | 9/2/2005 | 9/2/2005 | 2/6/2007 | | DONE |
|
|
|
|
Third Notice BLD | 1/8/2007 | 1/8/2007 | 1/31/2007 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 9/25/2006 | 9/25/2006 | 1/8/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 8/2/2006 | 9/25/2006 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/1/2006 | 8/2/2006 | 8/2/2006 | A | PASS |
Forrest France
|
|
|
Required correction for the fire dept. access curb painting has been verified for completion, final inspection passed.
|
Permanent Occupancy | | 8/2/2006 | 8/2/2006 | | DONE |
|
|
|
|
Permanent occupancy | | | 8/2/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 11161 issued 8-2-06 to EMI
|
Code Occupancy Approval Temp | | | 7/14/2006 | | |
|
|
|
Signed Temporary w/bond in place on 7/6/2006
|
FIRE-Final Inspection | 7/5/2006 | 7/6/2006 | 7/6/2006 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the curbing has been painted for the fire dept. access.
|
Temporary occupancy | | | 7/6/2006 | | DONE |
|
|
|
Temp. Occ. Cert. # 5415 issued 7-6-06 to EMI.
|
BLD-Final | 6/27/2006 | 6/28/2006 | 6/28/2006 | A | PEND |
Jim Sly
|
|
|
dana - call prior to insp; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley OK for Temp or Perm Occ...........when fire signs for temp or perm, and when bond for landsc complete.
|
FIRE-Final Inspection | 6/27/2006 | 6/28/2006 | 6/28/2006 | A | CANC |
Troy Cobbley
|
|
|
dana - call prior to insp; Phone #: ###-#### I spoke to the contractor on the phone and he stated that he needed a temporary occupancy until he had the curbing changed per the fire dept requirements. Also no pavement was installed yet. I told him no.
|
BLD-Aging Inspection | 4/6/2006 | 4/6/2006 | 4/6/2006 | | DONE |
Jim Sly
|
|
|
WIP
|
Issue PAID IN FULL permit | | | 1/5/2006 | | |
|
|
|
|
Telephone call | | | 12/7/2005 | | DONE |
|
|
|
called ###-#### and told her permit ready and fees and need ACHD
|
Inspection Record Card- Bld | | | 12/6/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/6/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/6/2005 | | DONE |
|
|
|
|
Routing - FIRE | 11/21/2005 | | 12/5/2005 | | PASS |
|
|
|
resubmittal acceptable
|
Routing - PLAN CHECK | 12/5/2005 | | 12/5/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/5/2005 | | |
|
|
|
|
Plan assigned to (JCM) | 9/8/2005 | | 12/5/2005 | | PASS |
|
|
|
12/5/2005 11:58:28 JCM - activity updated through activity BLDA022 from case BLD05-02453.
|
Routing - PLANNING | 11/17/2005 | | 11/21/2005 | | PASS |
|
|
|
Approved per DRH05-00194.
|
Routing - PLAN CHECK | 10/19/2005 | | 11/17/2005 | | |
|
|
|
|
Plan resubmittals received | | | 11/10/2005 | | |
|
|
|
Received 2 review comments,2 landscape plans & 2 copys of sheets AD1,A-2,A-3,A-5,A-6,A-7,M-1,M-2,E2.0L, E3.0 Taken to John M.
|
Routing - FIRE | 10/3/2005 | | 10/19/2005 | | FAIL |
|
|
|
called architect left voicemail, revisions required per intake meeting not resubmitted. CE, Adam with Alliance , called and I explained the req'ts to him and faxed the review to him as well as to the architect.
|
1st review completed | | | 10/19/2005 | | FAIL |
|
|
|
failed plan check, and fire.
|
Routing - PLAN CHECK | 9/30/2005 | | 10/3/2005 | | FAIL |
|
|
|
|
Routing - PLANNING | 9/27/2005 | | 9/30/2005 | | FAIL |
|
|
|
Parking spaces at the northwest area of parking lot do not comply with dimensional criteria. Landscape plan has not been submitted to Design Review staff for review and approval.
|
Routing - PLUMBING | | | 9/27/2005 | | PASS |
|
|
|
per plans and 2003 upc. max hot water to public lavs is 120 deg.
|
Routing - Erosion and Sediment | 9/14/2005 | | 9/15/2005 | | PASS |
|
|
|
plans passed erosion on 9/15, see activity in shell permit Bld05-02452, this TI and shell are on same plans //12/6/05 LEG
|
Routing - PUBLIC WORKS | 9/8/2005 | | 9/14/2005 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/8/2005 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 9/8/2005 | | |
|
|
|
|
Routing - PLANNING Land Div | 9/8/2005 | | 9/8/2005 | | PASS |
|
|
|
|
Application received | | | 9/2/2005 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/2/2005 | | |
|
|
|
|