BLD-Final | 3/15/2006 | 3/16/2006 | 3/16/2006 | P | PASS |
Mike Jordan
|
|
|
troy; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
DOC - Permit Finaled | 3/16/2006 | 3/16/2006 | 3/16/2006 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 1/9/2006 | 1/10/2006 | 1/10/2006 | A | PASS |
Mike Jordan
|
|
|
troy; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Framing/Rough-in | 1/9/2006 | 1/10/2006 | 1/10/2006 | A | PASS |
Mike Jordan
|
|
|
troy; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. Lateral bracing complete.
|
BLD-Framing/Rough-in | 1/3/2006 | 1/4/2006 | 1/4/2006 | A | FAIL |
Mike Jordan
|
|
|
troy; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa. Needs to complete lateral bracing, provide correct set of approved plans. ok to insulate.
|
BLD-Foundation | 10/20/2005 | 10/21/2005 | 10/21/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/20/2005 at 7:31:28 AM. Contact: ###-####. wip ok
|
BLD-Footing | 10/20/2005 | 10/20/2005 | 10/20/2005 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/20/2005 at 7:30:46 AM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 10/6/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/4/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/4/2005 | | DONE |
|
|
|
|
Telephone call | | | 10/4/2005 | | DONE |
|
|
|
Spoke with Barbara and told her that permit is ready & fees///10/04/05 8:30am BAS
|
Plan assigned to (SAM) | 9/6/2005 | 9/6/2005 | 10/3/2005 | | PASS |
|
|
|
10/3/2005 12:50:08 PEP - activity updated through activity BLDA022 from case BLD05-02468.
|
Routing - PLAN CHECK | 9/12/2005 | | 10/3/2005 | | PASS |
|
|
|
|
Plan assigned to (PEP) | 10/3/2005 | | 10/3/2005 | | PASS |
|
|
|
10/3/2005 12:50:09 PEP - activity updated through activity BLDA022 from case BLD05-02468.
|
Case Summary (BLD) | | | 10/3/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/3/2005 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 9/12/2005 | | 9/12/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 9/6/2005 | | 9/9/2005 | | PASS |
|
|
|
|
Application received | | | 9/6/2005 | | |
|
|
|
|