BLD-Final | 11/17/2006 | 11/20/2006 | 11/20/2006 | P | PASS |
Tony Young
|
|
|
###-#### nancy
|
DOC - Permit Finaled | 11/20/2006 | 11/20/2006 | 11/20/2006 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Grading Inspection | 8/14/2006 | 8/14/2006 | 8/14/2006 | | DONE |
|
|
|
Final grading and drainage approved on 6/22/06.
|
BLD-Final | 8/10/2006 | 8/10/2006 | 8/10/2006 | P | FAIL |
Tony Young
|
|
|
nancy - call prior for access; Phone #: ###-#### Internet Inspection Request from: Barbara Buckley c/n posted
|
BLD-Energy code compliance | 1/30/2006 | 1/31/2006 | 1/31/2006 | A | PASS |
Tony Young
|
|
|
Cameron -- for energy code and framing; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
BLD-Framing/Rough-in | 1/30/2006 | 1/31/2006 | 1/31/2006 | A | PASS |
Tony Young
|
|
|
Cameron -- for energy code and framing; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
BLD-Framing/Rough-in | 1/26/2006 | 1/27/2006 | 1/27/2006 | A | FAIL |
Jim Sly
|
|
|
Cameron; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong Bogus B.......L Cartwright.........2nd R.......then 1st L all way to top. C/N
|
BLD-Foundation | 11/4/2005 | 11/7/2005 | 11/7/2005 | A | PART |
Tony Young
|
|
|
tim - walls ; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Footing | 10/31/2005 | 11/1/2005 | 11/1/2005 | A | PART |
Tony Young
|
|
|
tim; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
PubWorks Subgrade Approval | 10/25/2005 | 10/25/2005 | 10/25/2005 | | DONE |
|
|
|
Footing subgrade approved by the geotechnical engioneer
|
Issue PAID IN FULL permit | | | 10/14/2005 | | DONE |
|
|
|
|
Plan assigned to (SRZ) | 10/7/2005 | 10/7/2005 | 10/12/2005 | | PASS |
|
|
|
10/12/2005 10:24:08 SRZ - activity updated through activity BLDA022 from case BLD05-02590.
|
Routing - PLAN CHECK | 10/12/2005 | | 10/12/2005 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 10/12/2005 | | 10/12/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/12/2005 | | DONE |
|
|
|
One set red-lined.
|
Permit Ready to Issue | | | 10/12/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/12/2005 | | DONE |
|
|
|
|
Telephone call | | | 10/12/2005 | | DONE |
|
|
|
left mess that permit is ready
|
Plan resubmittals received | | | 10/11/2005 | | |
|
|
|
Received (3) ESC Narratives. Routed to ESC.
|
Routing - Erosion and Sediment | 10/7/2005 | | 10/10/2005 | | FAIL |
|
|
|
Routed to ESC. for approval. Route back to Sam Zahorka.
10/10/05 Have not received ESC resubmittal. Plan is in pending box. Contacted PD.
|
Plan assigned to (SAM) | 9/15/2005 | 9/15/2005 | 10/7/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/30/2005 | | 10/7/2005 | | PASS |
|
|
|
Routed to ESC for approval.
|
Case Summary (BLD) | | | 10/7/2005 | | |
|
|
|
|
Routing - FIRE | 9/29/2005 | | 9/30/2005 | | PASS |
|
|
|
No fire sprinklers required (El Pelar Estates # 5 Sub - per D Miller)
|
Routing - PLANNING | 9/23/2005 | | 9/29/2005 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 9/29/2005 | | 9/29/2005 | | FAIL |
|
|
|
ESC plan does not meet standards as outlined in BMC 8-17 and plan designer manual. Checklist completed and faxed to PD. Re-submittal required.
|
Routing - PUBLIC WORKS | 9/22/2005 | | 9/23/2005 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 9/22/2005 | | 9/22/2005 | | PASS |
|
|
|
Approved as Category 3
|
Routing - PUBLIC WORKS GRADING | 9/15/2005 | | 9/16/2005 | | FAIL |
|
|
|
Soils report from 97. Need updated report.
|
Application received | | | 9/15/2005 | | |
|
|
|
|