BLD-Final | 5/12/2006 | 5/15/2006 | 5/15/2006 | A | PASS |
Dave Hannah
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
DOC - Permit Finaled | 5/15/2006 | 5/15/2006 | 5/15/2006 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 5/12/2006 | 5/12/2006 | 5/12/2006 | P | FAIL |
Mike Jordan
|
|
|
chris ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie. Handrail does not terminate above lowest riser on stairs.
|
BLD-Final | 5/11/2006 | 5/12/2006 | 5/12/2006 | A | NR |
Mike Jordan
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Energy code compliance | 3/2/2006 | 3/3/2006 | 3/3/2006 | A | PASS |
Mike Jordan
|
|
|
Chris; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong
|
BLD-Final | 3/1/2006 | 3/2/2006 | 3/2/2006 | A | NR |
Mike Jordan
|
|
|
Chris; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong. Needs other trades final first.
|
BLD-Framing/Rough-in | 2/22/2006 | 2/23/2006 | 2/23/2006 | P | PASS |
Mike Jordan
|
|
|
Chris; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong. All framing issues have been repaired.
|
BLD-Framing/Rough-in | 2/21/2006 | 2/22/2006 | 2/22/2006 | P | FAIL |
Mike Jordan
|
|
|
Chris -- call 1st before insp; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong. Complete all lateral bracing, Nail off all simpson hangars, provide L bracing on gable ends, Provide header over closet door in master bedroom. ok to insul. c/n posted.
|
BLD-Framing/Rough-in | 2/21/2006 | 2/21/2006 | 2/21/2006 | P | NR |
Mike Jordan
|
|
|
Chris -- call 1st before insp; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong. Still needs trades ri insp.
|
BLD-Foundation | 10/28/2005 | 10/28/2005 | 10/28/2005 | P | PASS |
Tom Arcoraci
|
|
|
rob; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Footing | 10/27/2005 | 10/27/2005 | 10/27/2005 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/27/2005 at 8:32:56 AM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 10/19/2005 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 9/19/2005 | 9/19/2005 | 10/7/2005 | | PASS |
|
|
|
10/7/2005 07:24:25 PEP - activity updated through activity BLDA022 from case BLD05-02614.
|
Routing - PLAN CHECK | 9/21/2005 | | 10/7/2005 | | PASS |
|
|
|
|
Case Summary (BLD) | | | 10/7/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/7/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/7/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/7/2005 | | DONE |
|
|
|
|
Telephone call | | | 10/7/2005 | | DONE |
|
|
|
called ###-#### and left voicemessage that permit is ready and fees
|
Routing - PUBLIC WORKS | 9/20/2005 | | 9/21/2005 | | PASS |
|
|
|
|
Routing - PLANNING | 9/19/2005 | | 9/20/2005 | | PASS |
|
|
|
|
Application received | | | 9/19/2005 | | |
|
|
|
|